WATER W., G. & S. BD., ONEONTA v. PA Buchanan Cont. Co.

318 So. 2d 267
CourtSupreme Court of Alabama
DecidedJuly 31, 1975
StatusPublished
Cited by1 cases

This text of 318 So. 2d 267 (WATER W., G. & S. BD., ONEONTA v. PA Buchanan Cont. Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
WATER W., G. & S. BD., ONEONTA v. PA Buchanan Cont. Co., 318 So. 2d 267 (Ala. 1975).

Opinion

318 So.2d 267 (1975)

The WATER WORKS, GAS & SEWER BOARD OF the CITY OF ONEONTA, INC., a corporation
v.
P. A. BUCHANAN CONTRACTING CO., a partnership, etc., et al.

SC 1168, 1169.

Supreme Court of Alabama.

July 31, 1975.

Simmons, Torbert & Cardwell, Gadsden, for appellant.

Spain, Gillon, Riley, Tate & Etheredge and H. H. Grooms, Jr., Birmingham, for appellees.

MERRILL, Justice.

These appeals are from judgments granting the motion of United States Fidelity & Guaranty Company (USF&G), a third party defendant, for a summary judgment in cross-claim against it by The Water Works, Gas & Sewer Board of the City of Oneonta, hereinafter referred to as the Board. We affirm.

*268 In this case, we do not perceive any genuine issue as to any material fact, ARCP 56(c), and the only question presented is a question of law—whether, under the facts, USF&G is liable to the Board under the public works Completion and Performance Bond which it made for P. A. Buchanan Contracting Company, hereinafter referred to as Buchanan.

In August, 1952, Buchanan entered into a contract with the Board for the construction of a natural gas system for the City of Oneonta. USF&G executed the statutory public works Completion and Performance Bond and the Labor and Materials Bond. Goodwin Engineers of the South, Inc. and J. W. Goodwin Engineering Co. (also third party defendants) were the project engineers.

Buchanan completed the work; it was approved and accepted and Buchanan was paid in full under the terms of the contract in 1953.

On March 7, 1969, some 16 years later, a pipe exploded and damaged a building owned by Dorothy Gartrell. Her suit is S.C. 1168. Her husband, Dr. L. S. Gartrell, was a tenant in the building and his suit is S.C. 1169. The basis of each suit against the Board, Buchanan and the engineers was that the pipe was negligently laid and as a proximate consequence the building was damaged, and in S.C. 1169, Dr. Gartrell's practice was disrupted and records destroyed.

The Board filed a third-party summons and complaint against Buchanan, USF&G and the engineers. The engineers also filed cross-complaint against USF&G. USF&G filed a motion for summary judgment accompanied by affidavits. The Board filed its opposition to the motion.

The trial court found in favor of USF&G as to the cross-claims of the Board and the engineers, and rendered a summary judgment in favor of USF&G as to the Board and the engineers. Only the Board appealed.

The Board's position is expressed in brief as follows:

"The pleadings consisting of the summons and complaint and third-party complaints and cross-claims in the transcript are all based on the claim by Appellant [the Board] here in that the performance bond is a common law bond and the contract between Appellant and P. A. Buchanan Contracting Company is made a part thereof, which includes page 11 of this contract. Accordingly, the question is whether or not it is a common law bond and whether the contract and bond are read together to require United States Fidelity & Guaranty Company to indemnify Appellant from any loss."

The undisputed evidence is that the bond in question was required and given under the provisions of Tit. 50, § 16, Code 1940, which provides in pertinent part:

"Any person, firm or corporation entering into a contract with the state or any county or municipal corporation or subdivision thereof in this state for the repair, construction or prosecution of any public buildings or public work, highways or bridges, shall be required, before commencing such work, to execute a performance bond, with penalty equal to fifty percent of the amount of the contract price, * * *
"The contractor shall immediately after the completion of the contract give notice of said completion by an advertisement in some newspaper of general circulation published within the city or county wherein the work has been done for a period of four successive weeks. In no instance shall a final settlement be made upon the contract until the expiration of thirty days after the completion of same. * * *"

It is undisputed that these requirements were met.

This statute, Alabama's public works bond statute, enacted in 1927 and *269 amended in 1935, is patterned after the Miller Act, Tit. 40, §§ 270a & 270b, U.S.C.A. In State v. Southern Surety Co., 221 Ala. 113, 127 So. 805 (1930), this court, after comparing our statute with the federal statute in parallel columns, stated in part:

"The doctrine that a Legislature, in enacting a statute from another jurisdiction, enacts it with its authoritative interpretation, is universal and firmly established.

******

"* * * The rule is that the borrowed statute is presumed to come with its authoritative interpretation. We have cited our case to such effect."

That decision was followed in National Surety Corporation v. Wunderlich (8th Cir.), 111 F.2d 622 (1940), where our public works statute was being construed and applied.

It is clear that a public works performance bond required by Tit. 50, § 16, carries with it the federal interpretation of the Miller Act.

This court has held that even when a bond under § 16 is not literally in statutory form, if it was given "for the purposes named in the statute and accepted and acted upon as such," the statute will be read into the bond. Royal Indemnity Co. v. Young & Vann Supply Co., 225 Ala. 591, 144 So. 532. And in American Casualty Co. of Reading, Pa. v. Define, 275 Ala. 628, 157 So.2d 661, this court said:

"With reference to said act, [Tit. 50, § 16] this court has said that there was no compulsion on the surety to execute such a bond, but since the surety did so, knowing the purpose for which the bond was given and being charged with knowledge of the law which required the bond, the bond must be construed and applied as if the parties making it had complied with the law. Universal Electric Const. Co. of Alabama v. Robbins, 239 Ala. 105, 194 So. 194. The bond shows on its face that it was executed in compliance with the statute and the court is authorized to read into it the provisions of the statute, `and give it the form and effect the statute contemplated, regardless of its contents.' 239 Ala. 109, 194 So. 198. In short the statute is written into the bond.
"We are of opinion that if the statute is written into the bond as to the contractor and surety, the statute is also written into the bond as to the obligee and the suppliers of labor and materials who rely on the bond."

A public works bond surety is not liable to third parties for injuries caused by negligence of the contractor-principal. The general rule is stated in 63 C.J.S. Municipal Corporations § 1172, p. 859:

"A bond to secure the performance of a municipal improvement contract is for the benefit and protection of the city and all property owners interested in the improvement, but it does not cover the claims of adjoining landowners for torts committed by the contractor in the performance of the work even though the contract provided that the contractor and his surety should be responsible for all damage caused by the contractor's operations. * * *"

Many federal court cases support this principle, some of which are: United States v. Fidelity & Deposit Co. of Maryland (D.C., La.), 144 F.Supp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Marshall v. American General Insurance Co.
623 S.W.2d 445 (Court of Appeals of Texas, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
318 So. 2d 267, Counsel Stack Legal Research, https://law.counselstack.com/opinion/water-w-g-s-bd-oneonta-v-pa-buchanan-cont-co-ala-1975.