Kniess v. American Surety Co.

300 N.W. 913, 239 Wis. 261, 1941 Wisc. LEXIS 142
CourtWisconsin Supreme Court
DecidedNovember 5, 1941
StatusPublished
Cited by11 cases

This text of 300 N.W. 913 (Kniess v. American Surety Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kniess v. American Surety Co., 300 N.W. 913, 239 Wis. 261, 1941 Wisc. LEXIS 142 (Wis. 1941).

Opinion

Wickhem, J.

No particular significance appears to attach to the fact that this is an appeal from two separate orders. It is assumed by the parties that there are now before the court on the basis of a complaint and answer enough facts upon which to determine the question of law argued upon this appeal; hence the facts will merely be stated without reference to the pleadings.

During the years 1939 and 1940 Jefferson Construction Company as principal contractor built an interceptor sewer in the city of Wausau. The contract price was approximately $201,000. The contract required that before work was commenced the contractor obtain compensation insurance, public-liability, and property-damage insurance. Riders or separate policies covering the special hazards arising from the operation of trucks, the undermining of adjacent structures or blasting operations were also required. The contract was specific as to the amount of coverage for public-liability and property-damage insurance. While blasting rock the contractor negligently damaged plaintiffs’ property. Plaintiff sued the contractor and recovered judgment in the sum of $3,577.19. This judgment was affirmed upon appeal to this court. The Wisconsin Mutual Insurance Company assumed *264 defense of the action under its policy, but before paying the judgment got into financial difficulties and is in the hands of the state insurance commissioner for liquidation. Defendants sustained large losses by reason of contributions to the cost of completing the project and the payment of valid claims for labor and materials. The contract of guaranty upon which defendants are sued was given in compliance with sec. 289.16 (1), Stats., which provides in substance that all contracts for the performance of labor or furnishing of materials involving $100 or more and having to do with public work of any kind shall contain a provision for the payment by the contractor of all claims for labor performed and materials furnished, including fuel, lumber, building materials, machinery, vehicles, motor oil, premiums for workmen’s compensation insurance, etc. It is further provided that no such contract shall be made unless the contractor shall give a bond, the penalty of which shall not be less than the contract price, conditioned for the faithful performance of the contract and payment to each person entitled thereto of all claims for labor performed, materials furnished, etc. There is no doubt upon the record that the bond was furnished to comply with this statutory requirement. The conditions of the bond are that the principal shall well and truly perform and fulfil all the undertakings, covenants, terms, and conditions of the proposal and agreement, and that the principal shall promptly make payments to all persons supplying the principal with labor and materials in the prosecution of the work. The bond is no broader than the calls of the statute. To engage that the principal will well and truly perform and fulfil all of the undertakings, covenants, terms, and conditions of the proposal and agreement is nothing more than an agreement that he will faithfully perform his contract, and the .detail in which the bond is stated does not in any way enlarge the duties of the principal. The contract executed in this case contains internal evidence that the bond required by it and actually executed was intended simply to be *265 a compliance with sec. 289.16. Section (1) of the general conditions of the contract, which by the express terms of the contract prevails over and supersedes any other provisions in the contract, provides as follows:

“The contractor shall furnish a surety bond (form attached) in an amount at least equal to 100 per cent of the contract price as security for the faithful performance of this contract and for the payment of all persons performing labor and furnishing materials in connection with this contract.”

This is nothing more than the requirement of an ordinary performance bond.

In addition the contract contains the following rules relating to the performance bond:

“1. Exhibit 1 is a performance bond to be used in those cases when an executed contract and bond for 100 per cent of the bid price is submitted with the bid. (See sections 62.15 and 40.54, Wisconsin statutes 1935, which apply to cities and city school boards.) This form must be fully executed when submitted with a bid.
“2. Exhibit 2 is a form of bond to be used in all cases where a certified check, cash or government bond is submitted as a bid guarantee. This form of bond is executed by the successful bidder only after the award of a contract.
“3. Care should be observed to' execute bonds fully and properly. Approval by the owner is required. (Section 289.16, Wisconsin statutes 1935.)”

Exhibit 1 which was the bond used in this case contains the following note:

“ (Note: This is not a bid bond form. It is for use in those cases where a signed contract and 100% performance bond are submitted with the proposal.)

Following the signatures is the following note:

“Note: The bond must be approved and the approval date in every case; refer to section 289.16, Wisconsin statutes 1935. The title of the person signing must be indicated.”

*266 These notations fortify the conclusion that nothing more than a conventional performance bond was contemplated and executed. Under the decisions in this state the bond given under the terms of sec. 289.16, Stats., has for its statutory beneficiaries: (1) The municipality; (2) laborers; (3) such holders of claims for materials and supplies as are listed in the statute itself. Milwaukee County v. H. Neidner & Co. 220 Wis. 185, 263 N. W. 468, 265 N. W. 226, 266 N. W. 238.

In Kolb v. Hayes, 194 Wis. 40, 215 N. W. 578, it was held that an abutting property owner having claim for blasting damage against a public contractor is not entitled to a lien under sec. 289.'53, Stats., and is not entitled to- recover under a performance bond given in satisfaction of sec. 289.16.

The plaintiff’s claim can be very simply put: One provision of the contract is to the effect that any damage done by blasting rock shall be immediately settled for by the contractor. Another is that the “contractor and his bonding company shall be responsible for all damages caused by the contractor’s operation and save, defend, indemnify, protect and hold harmless the city and its engineers against all manner of claims, demands, liability, damages or any other costs which may accrue in the prosecution of the work.” Plaintiff contends that since defendant guaranteed faithful performance of the contract, together with all its undertakings, terms, and conditions, and since one of these covenants by the contractor is to settle for damages by blasting, the bond must be considered to run to the benefit of those who sustain damages by reason of these operations.

We consider this to be contrary to the rule laid down by the decisions cited and to the terms and conditions of the contract itself. The intent of sec.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

5 Walworth, LLC v. Engerman Contracting, Inc.
2023 WI 51 (Wisconsin Supreme Court, 2023)
State Highway Administration v. Transamerica Insurance
367 A.2d 509 (Court of Appeals of Maryland, 1976)
WATER W., G. & S. BD., ONEONTA v. PA Buchanan Cont. Co.
318 So. 2d 267 (Supreme Court of Alabama, 1975)
Healy Plumbing & Heating Co. v. Minneapolis-St. Paul Sanitary District
169 N.W.2d 50 (Supreme Court of Minnesota, 1969)
HEALY PLUMB. & HEAT. CO. v. Mpls.-St. Paul San. Dist.
169 N.W.2d 50 (Supreme Court of Minnesota, 1969)
Ryder v. Baco Realty Co.
207 So. 2d 155 (Louisiana Court of Appeal, 1968)
Tri-State Insurance Company v. United States
340 F.2d 542 (Eighth Circuit, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
300 N.W. 913, 239 Wis. 261, 1941 Wisc. LEXIS 142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kniess-v-american-surety-co-wis-1941.