Milwaukee Metropolitan Sewerage District, a Special Purpose Wisconsin Municipal v. Fidelity & Deposit Company of Maryland, a Maryland Corporation

56 F.3d 821, 1995 U.S. App. LEXIS 13935, 1995 WL 338509
CourtCourt of Appeals for the Seventh Circuit
DecidedJune 7, 1995
Docket94-1896
StatusPublished
Cited by3 cases

This text of 56 F.3d 821 (Milwaukee Metropolitan Sewerage District, a Special Purpose Wisconsin Municipal v. Fidelity & Deposit Company of Maryland, a Maryland Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Milwaukee Metropolitan Sewerage District, a Special Purpose Wisconsin Municipal v. Fidelity & Deposit Company of Maryland, a Maryland Corporation, 56 F.3d 821, 1995 U.S. App. LEXIS 13935, 1995 WL 338509 (7th Cir. 1995).

Opinion

CUDAHY, Circuit Judge.

The Milwaukee Metropolitan Sewerage District sued Fidelity and Deposit Co., the surety on a performance bond, seeking to recover for damage caused by the failure of an odor control system. The district court granted summary judgment in favor of Fidelity, concluding that the action was time-barred. We affirm.

I.

In February of 1984, the Milwaukee Metropolitan Sewerage District (the District) solicited bids from contractors interested in the installation of odor control systems at the South Shore Wastewater Treatment Plant. On May 17, 1984, the District entered into a contract with Kramer Heating and Manufacturing, Inc. (Kramer). Work commenced shortly thereafter. In connection with this work, Fidelity and Deposit Co. (Fidelity) issued the District a performance bond.

On December 25, 1987, the parties certified the work under the contract as “substantially complete.” Kramer completed some additional “punchlist” items in August, 1989. The District began experiencing problems and on September 27, 1991, it determined that Kramer had breached its contract. The District therefore brought suit on the performance bond on March 9, 1992.

The relevant provisions of the parties’ contract are General Conditions 42 and 57. They provide in part:

42. PERFORMANCE BOND. The Contractor shall file with the Owner prior to the time of execution of the Contract a Performance Bond ... The bond shall also provide a guarantee against defective workmanship or materials or both, for a period of 1 year after Contract Completion.
57. GUARANTEE. Unless specifically stated otherwise in the Contract Documents, all work provided under this Contract by the Contractor or any of his subcontractors shall be warranted to the Owner as follows:
All work shall be ... guaranteed by the Contractor against all defects in workmanship and material for a period of 1 year following Contract Completion or ... for a period of 1 year following the date of Substantial Completion as established by the Engineer ...
The Owner’s rights under this Article shall be in addition to, and not a limitation of, any other rights and remedies available by law.

The. district court determined that the suit was time-barred. Specifically, it concluded that the action was governed by a one-year limitations period. This was not because Wisconsin’s statute governing public works, *823 Wis.Stat. § 779.14, provides for a one-year limitation on actions, but because the parties, in the language of the contract and the bond, provided for a one-year guarantee period. In making this determination, the district court relied on Milwaukee County v. H. Neidner & Co., 220 Wis. 185, 263 N.W. 468 (1935), which it believed mandated reliance upon the parties’ contract.

The District appeals from the district court’s determination, suggesting ultimately that the case should be governed by Wisconsin’s general six-year limitations period for contract actions, Wis.Stat. § 893.43.

II.

Resolution of this case therefore turns on whether the action is governed by a one-year limitations period, or whether Wisconsin’s general six-year limitations period for contract actions applies. The district court determined that the relevant date to begin counting for limitations purposes was either December, 1987, the time the work was certified as “substantially complete,” or later in August, 1989, when Kramer had completed some’additional punchlist items. The District does not dispute the usé of either date on appeal. Given the fact that the District did not file this action until March, 1992, over two years after the most recent time period, only application of the six-year limitations period can save the District’s case. We hold the six-year period inapplicable and therefore affirm the district court.

State law determines the applicable period of limitations. See Moser v. Universal Engineering Corp., 11 F.3d 720, 724 n. 6 (7th Cir.1993). Fidelity suggests that the present action is governed by Wisconsin’s statute regulating public works, Wis.Stat. '§ 779.14. That statute generally requires contracts “involving $500 or more for the performance of labor or furnishing materials [for] any public improvement or public work” to be bonded. The statute further provides that actions upon these bonds can be maintained “[n]ot later than one year after the completion of work under the contract.” Id.

Section 779.14, by its terms, would appear to apply in the case before us. The statute clearly sweeps municipalities and special districts within its ambit. In its specification of persons who may approve the bond, for instance, it designates a city’s “mayor,” a town’s “president,” a village’s “chairman,” and the “presiding officer” of “any other public board or body.” Wis.Stat. § 779.14(1). In addition, the statute applies to “all contracts with the state” and to “all other contracts involving $500 or more.” Id. See also Kniess v. American Surety Co., 239 Wis. 261, 300 N.W. 913 (1941) (describing the municipality as one of the statutory beneficiaries). This language seems to cover the contract here, in which a metropolitan sewerage district sought the construction of odor control systems for a public sewerage facility.

The district court found, however, that Section 779.14 did not apply. It rested its holding on Milwaukee County v. H. Neidner & Co., 220 Wis. 185, 263 N.W. 468 (1935), a Wisconsin Supreme Court decision interpreting Section 779.14, which it believed mandated looking to the language of the parties’ contract for a limitation. While we too are bound by the decisions of a state’s highest courts, see Kutsugeras v. AVCO Corp., 973 F.2d 1341, 1346 (7th Cir.1992), we read Neidner differently than did the district court.

Neidner involved a county’s suit for damages resulting from the defective installation of tiling. In it, the Wisconsin Supreme Court declined to apply the one-year limitations provision of Section 779.14. Instead, the court turned to the specific guaranty provision of the parties’ contract, which guaranteed the work against defects for a two-year period. The court found, specifically, that one of the conditions of the contract “is that the tiling, should stand for two years from the time of final payment.” 263 N.W. at 476. In light of this express contractual provision, tbe court believed that it would be anomalous to apply the statute’s one-year provision to defeat the county’s cause of action. Id.

Application of section [779.14] to the county would make impossible a suit on the bond and utterly defeat the purpose of the bond so far as benefit to the municipality is concerned.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
56 F.3d 821, 1995 U.S. App. LEXIS 13935, 1995 WL 338509, Counsel Stack Legal Research, https://law.counselstack.com/opinion/milwaukee-metropolitan-sewerage-district-a-special-purpose-wisconsin-ca7-1995.