United States v. B. Perini & Sons

159 F. Supp. 911, 1958 U.S. Dist. LEXIS 2711
CourtDistrict Court, N.D. Florida
DecidedMarch 20, 1958
DocketCiv. A. No. 304
StatusPublished

This text of 159 F. Supp. 911 (United States v. B. Perini & Sons) is published on Counsel Stack Legal Research, covering District Court, N.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. B. Perini & Sons, 159 F. Supp. 911, 1958 U.S. Dist. LEXIS 2711 (N.D. Fla. 1958).

Opinion

DE VANE, District Judge.

This is an action brought under the Miller Act, 40 U.S.C.A. § 270b, by J. A. Postell, a subcontractor, against several contracting companies joined together as the prime contractors for the construction of the Government lock and fixed crest spillway at the Jim Woodruff Dam project just below the confluence of the Chattahoochee and Flint Rivers near Chattahoochee, Florida. These two rivers are the headwaters for the Appalachicola River, which flows peacefully from their confluence to the Gulf of Mexico approximately 100 miles south.

Hereafter in this Memorandum-Decision, plaintiff will be referred to as Postell and defendants as Perini or the Perini group.

The prime contract between the Perini group and the Government was entered into on May 16, 1949. The contract and the specifications divided the work into 111 pay items and the total contract price was the sum of $8,714,972.70. Other pay items were subsequently added, but they are not pertinent to this •litigation. The Postell sub-contract bears date of May 31, 1950, and called for a turnkey job for item 55 at an overall cost of $58,580. The awarding of this sub-contract to Postell brought on a battle royal between him, the Corps of Engineers and the Perini group, which will not end until this case is finally assigned to the closed cases in someone’s filing cabinet.

In order to properly understand and appreciate the effect this controversy had upon this case, it is necessary for the Court to detail briefly the background that brought it about.

The Corps of Engineers desired to use a new type of hydraulic equipment to operate the lock gates at the dam, and after an investigation of various types of hydraulic equipment, those in charge of the preparation of the plans and specifications arrived at a preference for hydraulic equipment manufactured by the Vickers Company of Detroit, Michigan. Upon reaching that conclusion, the Corps of Engineers consulted with engineers of the Vickers Company in connection with the preparations of the plans and specifications for item 55, and included in the contract and the specifications a provision that Vickers Company or “similar and equal” equipment should be used in the hydraulic system. The Corps of Engineers in its specifications went one step further and provided that each power unit should “be factory assembled by the pump manufacturer and tested at his plant”.

The Corps of Engineers was fully aware that it had no authority to specify the equipment of any particular manufacturer for this dam project, but the use of the language just quoted was put into the specifications as a red flag that the Corps of Engineers expected Vickers equipment to be used, as no other manufacturer in the United States was equipped to factory assemble and test the equipment at its plant.

Mr. George Putnam Collier, the Chief Engineer of the Mobile, Alabama, office of the U. S. Corps of Engineers and in charge of this project, forthrightly testified that the contract and specifications were so drawn as to insure that Vickers equipment would be used on this project.

[913]*913The evidence in the case shows that there are a number of manufacturers of hydraulic equipment similar to that manufactured by the Vickers Company, and that one of these, Logansport Machine Company, Inc., of Logansport, Indiana, furnished prices to Perini for the hydraulic equipment called for under item 55 of the specifications prior to the time Perini filed with the United States its bid for the entire project, and shortly after the contract had been awarded to Perini, Postell wrote Perini, advising him that he was and for some years had been the representative of Logansport Machine Company in this area and requested an opportunity to be permitted to bid on item 55 when Perini was ready to send out invitations for bids on this item. Postell was subsequently given an opportunity to bid and his bid turned out to be the lowest of several bids received by Perini, and the sub-contract awarding item 55 to Postell was executed May 31, 1950. The contract provided that the work was to begin on item 55 not later than April 1, 1951, and to be completed on or before July 1, 1951.

The specifications required the submission of shop drawings of the entire hydraulic power unit to the contracting officer for approval before manufacture, assembly for test, or shipment. This provision meant that Mr. Collier of the Corps of Engineers, or persons under his supervision, had to approve the drawings before Postell and his suppliers could start the manufacture or assembly of the units for the project. Mr. Collier in no uncertain words, so Postell testified and this is not disputed, notified Postell that he would approve only Vickers units and he refused to approve shop drawings of Logansport units.

It was this attitude of Mr. Collier that started the chief controversy in this case. The evidence shows that Mr. Collier stood pat on his demand for Vickers equipment until after Postell took the controversy to Washington, secured the assistance of some members of Congress in his behalf, and finally on or about May 21, 1951, secured verbal assurance from Mr. Collier that he would consider shop drawings of other manufacturers than the Vickers Company, but it was not until October 23, 1951, that Collier specifically approved in writing the use of Logansport equipment. After that, drawings had to be submitted and approved, the equipment assembled and tested, and final approval given to its use before it could be shipped to the job. Final approval was not secured until December, 1951, and on some of it as late as April 7, 1952.

Postell had begun work as far as he could go after receiving Collier’s letter under date of October 23, 1951, agreeing to the use of equipment other than that manufactured by Vickers, and he testified that he moved along as rapidly as he could, and after securing final approval of the last of the equipment on April 7, 1952, completed his contract by May 20, 1952, except for certain minor adjustments, which will be more fully referred to later.

This unpleasant controversy could have been avoided easily in the beginning had the parties thereto desired to do so in the public interest. Postell in one breath testified there was nothing unusual in the wording of the specifications calling for Vickers or “similar and equal” equipment, that this is frequently done to avoid unnecessary details in specifications, and then in the next breath he testified that the provision in the specifications that the power units should be “factory assembled by the pump manufacturer and tested at his plant”, if strictly construed, eliminated all but Vickers power units, as no other manufacturer could meet this requirement.

Therefore, this Court, based upon all the evidence touching this phase of the controversy, is forced to the conclusion that Postell and his supplier, Logansport Machine Company, Inc., deliberately submitted the low bid for this project item with the full expectation of forcing the Corps of Engineers to accept other than Vickers equipment.

The evidence further shows that Perini assumed an air of righteous indigna[914]*914tion towards Postell for the delay occasioned by the controversy over the use of equipment other than Vickers, which has not as yet subsided.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
159 F. Supp. 911, 1958 U.S. Dist. LEXIS 2711, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-b-perini-sons-flnd-1958.