Fontaine Brothers, Inc. v. Springfield

617 N.E.2d 1002, 35 Mass. App. Ct. 155, 1993 Mass. App. LEXIS 820
CourtMassachusetts Appeals Court
DecidedAugust 18, 1993
Docket92-P-40
StatusPublished
Cited by6 cases

This text of 617 N.E.2d 1002 (Fontaine Brothers, Inc. v. Springfield) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fontaine Brothers, Inc. v. Springfield, 617 N.E.2d 1002, 35 Mass. App. Ct. 155, 1993 Mass. App. LEXIS 820 (Mass. Ct. App. 1993).

Opinion

Kass, J.

Early in the construction of a fire station for the city of Springfield, a dispute erupted about whether certain excavation work entitled the general contractor, Fontaine Brothers, Inc. (Fontaine), to extra compensation or was within the scope of the work as described by the plans and specifications. The architect for the project, exercising authority to interpret the plans and specifications, ruled that Fontaine was not entitled to extra compensation. Fontaine brought a contract action against the city, insisting that the architect had exceeded his authority, and secured a jury verdict of $145,947.85, which, with contract interest, resulted in a judgment of $178,820.10. We are of opinion that the architect’s interpretation of the plans and specifications was bind *156 ing and final and that, therefore, the city was entitled to the directed verdict for which it had timely moved. See Mass.R.Civ.P. 50(a), 365 Mass. 814 (1974). Accordingly, we reverse the judgment and order judgment for the defendant. 1

On the site of the fire station there had once stood a junior high school, demolished some thirteen years before the date of the construction contract. The project drawings depicted the “assumed foundation of the former Buckingham School” in a blue shaded area, overlaid by the footprint of the fire station to be built. It was removal of the residual rubble 2 of the demolished school, a manifestly unsuitable support for the foundation slab of a new building, that became the point of controversy.

Such a problem had been anticipated in the specifications prepared by the architect. The “Site Clearing” specifications required that the contractor “[rjemove existing and below-grade improvements necessary to permit construction, and other work as indicated, including all building debris from previous demolition work which is encountered below new building slabs and foundations, . . . and other locations indicated on drawings.” 3 Fontaine preferred reading the specifications for the next phase of the job, “Earthwork.” The earthwork specifications provided that, after the contractor had reached designated subgrade elevations, it was to notify the architect, so that he might inspect the conditions. If the materials at the designated subgrades were not suitable bearing materials, and that condition had been concealed or changed in a manner materially different from what was in *157 dicated 4 in the contract documents or those encountered in normal construction activity, then the contractor was to be paid extra for the unanticipated work.

If it were our duty to interpret the contract we would have little difficulty deciding that § 02110 of the specifications, relating to site clearing, unmistakably and, indeed, repetitively requires the contractor to remove old building rubble from the job site, and that Fontaine had been forewarned by sheet No. L-l of the architectural drawings that the job was on an old building site. Any apparent disharmony in § 02200 of the specifications, relating to earthwork, evaporates upon recognition that it deals with the bearing quality and suitability of soil at the job site, not debris. To the extent that Fontaine detected an obvious discrepancy — as it now contends — between § 02110 and § 02200 of the specifications, it should have asked for clarification if it intended to bridge the purported crevasse in its. favor. John F. Miller Co. v. George Fichera Constr. Corp., 7 Mass. App. Ct. 494, 498-499 (1979).

The question in the case, however, is not what we think the specifications mean. Rather, the question is: was the architect authorized to decide definitively what the specifications mean?

Regarding the architect’s authority, art. II of the construction contract provides:

“The work shall be done under the general direction of the Architect and his decision as to the true construction and meaning of the drawings and specifications shall be final.”

*158 As to that authority there is some amplification in art. 4 of the general conditions of the contract for construction. 5 Paragraph 4.4.4, notably, provides that the architect’s decision concerning a disputed claim “shall be final and binding on the parties but subject to arbitration.” A tailor-made supplementary condition, however, deletes all “references to ‘arbitrators’ and ‘arbitration’ from paragraphs 4.1.1, 4.3.2, 4.4.4, 8.3.1, 10.1.2, 11.3.9 and 11.3.10.” What is left in the general conditions is that the architect’s decision shall be final and binding.

Construction contracts frequently contain provisions giving an architect the power to decide disputes which arise under a construction contract. Fred C. McClean Heating Supplies, Inc. v. Jefferson Constr. Co., 339 Mass. 356, 363 (1959). Henry B. Byors & Sons v. Water Commrs. of Northborough, 358 Mass. 354, 363 (1970). 3A Corbin, Contracts § 652 (1960). Randall & Franklin, Municipal Law and Practice § 1332 (4th ed. 1993). See Acmat Corp. v. Daniel O’Connell’s Sons, 17 Mass. App. Ct. 44, 49 (1983). Such is the number of details in construction drawings and specifications that inevitably there are disputes about methods, materials, and the extent of what a contractor is to do and for what the owner is to pay. It is important that someone more or less on the spot can resolve those disputes, and the architect, as we have seen, is commonly the designated referee. See J.A. Sullivan Corp. v. Commonwealth, 397 Mass. 789, 800-801 (1986).

Although the words “final” and “binding” have a terminal and unconditional quality, the power of the architect on a construction job is, of course, not without limit. The architect may not act in bad faith, fraudulently, arbitrarily, capriciously, or outside the scope of her or his authority. G. L. c. 30, § 39J (applies to public jobs). 6 J.A. Sullivan Corp. v. *159 Commonwealth, 397 Mass. at 801. J.J. Finn Elec. Serv., Inc. v. P.& H. Gen. Contractors, Inc., 13 Mass. App. Ct. 973 (1982). Acmat Corp. v. Daniel O’Connell’s Sons, 17 Mass. App. Ct. at 49.

Those limitations on an architect’s power of final and binding decision afford cold comfort to the plaintiff Fontaine. There is no suggestion that the architect acted fraudulently or arbitrarily, 7 and, as to the scope of his authority, interpretation of the meaning of drawings and specifications is precisely the subject matter remitted to the architect’s power of decision. With no hay to be made on a claim of fraudulent or arbitrary conduct, Fontaine advances the argument that the architect may not by his power of decision change the contract. That is sound principle. See

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tribble & Stephens Co. v. RGM Constructors, L.P.
154 S.W.3d 639 (Court of Appeals of Texas, 2005)
Ostrow Electrical Co. v. J.L. Marshall & Sons, Inc.
798 N.E.2d 310 (Massachusetts Appeals Court, 2003)
Massachusetts Highway Department v. Perini Corp.
13 Mass. L. Rptr. 564 (Massachusetts Superior Court, 2001)
John J. Petruzzi-William E. Forrester, Inc. v. Massachusetts Turnpike Authority
9 Mass. L. Rptr. 184 (Massachusetts Superior Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
617 N.E.2d 1002, 35 Mass. App. Ct. 155, 1993 Mass. App. LEXIS 820, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fontaine-brothers-inc-v-springfield-massappct-1993.