John J. Petruzzi-William E. Forrester, Inc. v. Massachusetts Turnpike Authority

9 Mass. L. Rptr. 184
CourtMassachusetts Superior Court
DecidedSeptember 22, 1998
DocketNo. 9400690
StatusPublished

This text of 9 Mass. L. Rptr. 184 (John J. Petruzzi-William E. Forrester, Inc. v. Massachusetts Turnpike Authority) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John J. Petruzzi-William E. Forrester, Inc. v. Massachusetts Turnpike Authority, 9 Mass. L. Rptr. 184 (Mass. Ct. App. 1998).

Opinion

Donohue, J.

This action arises out of a public construction contract entered into between the plaintiff, John J. Petruzzi-William E. Forrester, Inc. (“Petruzzi-Forrester”), and the defendant, the Massachusetts Turnpike Authority (“MTA”), for rock and earth excavation and the stabilization and construction of boulder walls and ditches. Petruzzi-Forrester claims that it is entitled to (1) additional compensation for time lost as a result of bad weather; (2) payment for certain blasting work beyond that delineated in the contract (“overbreak’j; (3) full payment for the installation of a barrier wall; and (4) payment due for installation of a guard rail. The MTA now moves for summary judgment on the grounds that Petruzzi-Foixester is liable under the contract for any cost incurred for time lost due to bad weather, that Petruzzi-Forrester is precluded from disputing its other claims because it failed to follow the required claim filing procedures set forth in the contract, and that the project engineer’s decisions satisfied G.L.c. 30, §39J standards of review. For the reasons set forth below, summary judgment is allowed as to Petruzzi-Forrester’s claims for additional compensation for lost time due to bad weather, payment due for overbreak, and full payment for the installation of a barrier wall and is denied as to Petruzzi-Forrester’s claim for the contract price owed. on the installation of the guard rail.

BACKGROUND

The following facts are undisputed. On October 30, 1992, Petruzzi-Forrester and the MTA entered into Contract No. 851-426, which'called for the removal of rock and earth, earth slope excavation and stabilization, and the construction of boulder walls and ditches. The contract sets forth procedures for processing independent and general contractors’ claims, including specific requirements for the proper filing of each claim, the MTA engineer’s consideration of and decision on each such claim, and the Authority’s payment of approved claims for compensation. The contract further provides that the engineer’s decisions are final and conclusive.

During its performance of the contract, Petruzzi-Forrester submitted several claims seeking additional compensation under the contract for time lost on account of bad winter weather. The engineer denied those claims. Subsequently, on December 1, 1993, the engineer submitted to Petruzzi-Forrester a final payment estimate, which Petruzzi-Forrester did not accept. Petruzzi-Forrester disputed certain items, contending that (1) the MTA failed to pay for a portion of overbreak; (2) the MTA did not pay the full contract price for the installation of a barrier wall; and (3) the MTA bid out to another contractor the installation of a guard rail which was an item included in Petruzzi-Forrester’s contract with the MTA.1 The MTA made a final determination as to the disputed items, denying Petruzzi-Forrester’s claims, and conveyed its decision in a letter to Petruzzi-Forrester dated December 13, 1993. Petruzzi-Forrester subsequently filed a complaint against the MTA on March 23, 1994.

DISCUSSION

Summary judgment shall be granted where there are no material facts in dispute and the moving party is entitled to judgment as a matter of law. Cassesso v. Commissioner of Correction, 390 Mass. 419, 422 (1983); Community National Bank v. Dawes, 369 Mass. 550, 553 (1976); Mass.R.Civ.P. 56(c). The moving party bears the burden of affirmatively demonstrating the absence of a triable issue and that the moving party is entitled to judgment as a matter of law. Pederson v. Time, Inc., 404 Mass. 14, 16-17 (1989). With respect to any claim on which the moving party does not have the burden of proof at trial, the movant may demonstrate the absence of a triable issue either by submitting affirmative evidence that negates an essential element of the opponent’s case or “by demonstrating that proof of that element is unlikely to be forthcoming at trial.” Flesner v. Technical Communications Corp., 410 Mass. 805, 809 (1991); Kourouvacilis v. General Motors Corp., 410 Mass. 706, 716 (1991). “If the moving party establishes the absence of a triable issue, the party opposing the motion must respond and allege specific facts which would establish the [185]*185existence of a genuine issue of material fact in order to defeat [the] motion . . .” Pederson, 404 Mass. at 17.

Under public works construction contracts, as in the one at issue here, the engineer frequently possesses the authority to interpret contract terms and to resolve disputes arising from the contract. Fontaine Brothers, Inc. v. Springfield, 35 Mass.App.Ct. 155, 158 (1993). In Benjamin Foster Co. v. Commonwealth, 318 Mass. 190, 209 (1945), the Supreme Judicial Court characterized the role of the engineer in such projects as that of a “quasi arbitrator!] by whose judgment the parties agree in advance to be bound.” The purpose of such a broad grant of authority to the engineer is that “[s]uch is the number of details and construction drawings and specifications that inevitably there are disputes about methods, materials, and the extent of what a contractor is to do and for what the owner is to pay”; and, therefore, “[i]t is important that someone more or less on the spot [be available to] resolve those disputes . . .” Fontaine Bros., Inc., 35 Mass.App.Ct. at 158.2 A prerequisite to the engineer’s consideration of any contractor claim is that the contractor follow the procedures set forth in the contract which govern filing of claims. Failure to do so forfeits tb<= contractor’s claims. Sutton Corp. v. Metropolitan District Commn, 38 Mass.App.Ct. 764, 767 (1995).

Although Article 28 (Authority of the Engineer) of the subject contract provides that “the determination and decision of the Engineer shall be final and conclusive,” a limited judicial review of such decisions has developed atcommonlaw, see Morgan v. Burlington, 316 Mass. 413, 419-20 (1994); Benjamin Foster Co., 318 Mass. at 208, and was codified in 1961 with the enactment of G.L.c. 30, §39J. Under this statute, decisions of an engineer are final and conclusive unless such decision “is made in bad faith, fraudulently, capriciously, or arbitrarily is unsupported by substantial evidence, or is based upon error of law.” G.L.c. 30, §39J.3

The parties dispute whether or not a trial de novo should be afforded in regard to the Superior Court’s review of the engineer’s decision. G.L.c. 30, §39J fails to address that issue. However, prior to the enactment of G.L.c. 30, §39J, the Supreme Judicial Court implied that de novo review exceeds the parameters of its limited review in such cases. Benjamin Foster Co., 318 Mass. at 209 (the Court refused to substitute its judgment for that of the engineer’s because the parties, by contract, entrusted such decisions to the engineer). Accordingly, a trial de novo is unnecessary and inappropriate to review the engineer’s decision in this case; and, therefore, in considering the instant motion, the Court has carefully reviewed the submission of the parties, including affidavits, depositions and contract documents.

I.Additional Compensation for Lost Time Due to Weather Delays

The MTA appropriately denied Petruzzi-Forrester’s claim for additional compensation for time lost as a result of the MTA’s issuance of a number of work cessation orders due to inclement weather.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
Fontaine Brothers, Inc. v. Springfield
617 N.E.2d 1002 (Massachusetts Appeals Court, 1993)
Community National Bank v. Dawes
340 N.E.2d 877 (Massachusetts Supreme Judicial Court, 1976)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Flesner v. Technical Communications Corp.
575 N.E.2d 1107 (Massachusetts Supreme Judicial Court, 1991)
Cassesso v. Commissioner of Correction
456 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1983)
Morgan v. Town of Burlington
55 N.E.2d 758 (Massachusetts Supreme Judicial Court, 1944)
Benjamin Foster Co. v. Commonwealth
61 N.E.2d 147 (Massachusetts Supreme Judicial Court, 1945)
Sutton Corp. v. Metropolitan District Commission
652 N.E.2d 627 (Massachusetts Appeals Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
9 Mass. L. Rptr. 184, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-j-petruzzi-william-e-forrester-inc-v-massachusetts-turnpike-masssuperct-1998.