Modern Continental South v. Fairfax County Water Authority

70 Va. Cir. 172, 2006 Va. Cir. LEXIS 39
CourtFairfax County Circuit Court
DecidedFebruary 9, 2006
DocketCase No. (Law) 225019
StatusPublished
Cited by3 cases

This text of 70 Va. Cir. 172 (Modern Continental South v. Fairfax County Water Authority) is published on Counsel Stack Legal Research, covering Fairfax County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Modern Continental South v. Fairfax County Water Authority, 70 Va. Cir. 172, 2006 Va. Cir. LEXIS 39 (Va. Super. Ct. 2006).

Opinion

BY JUDGE STANLEY P. KLEIN

This matter came before the court on the four remaining pleas in bar of owner, Fairfax County Water Authority (the Authority) to the amended motion for judgment filed by contractor, Modem Continental South (MCS).1 MCS alleges that the Authority breached the parties’ contract by refusing to pay it for work done at the Authority’s insistence but not required by the Contract. Specifically, MCS contends that the Contract did not require it to install torque tubes in certain butterfly valves in the Filter Building on this project.

In its First Plea in Bar, the Authority argues that MCS’s claim is barred because MCS failed to notify the Authority about an alleged conflict in the contract documents and drawings before proceeding with the work, as required by the Contract. In its Third Plea in Bar, the Authority asserts that the claim is barred because MCS failed to give notice of its claim at the time of the occurrence or the commencement of the relevant work, as required by the Contract and the Virginia Public Procurement Act (VPPA). In its Fourth Plea in Bar, the Authority contends that MCS did not comply with the five-day notice of protest requirement mandated by the Contract. Finally, in its Fifth Plea in Bar, the Authority claims that MCS waived its right to bring a claim regarding this dispute when it agreed to the provisions stipulated in Change Order 3 to the Contract.

After full consideration of the arguments presented and all of the applicable authorities, this court holds that MCS is barred from bringing its claim because it (1) breached the Contract by failing to notify the Authority about the conflicts in the contract documents and drawings prior to proceeding with the work; and (2) failed to give timely notice of its claim as required by the Contract and the VPPA. Therefore, this court sustains the First and Third Pleas in Bar. The court overrules the Second, Fourth, and Fifth Pleas in Bar. Because of other potential disputes relating to this project, the parties urged the court to explicitly rule on each of the issues in the pleas in bar, even if it sustained the first plea. The court has complied With this reasonable request of the parties.

[174]*174I. Background

This dispute arises out of a March 23, 2000, contract between the Authority and MCS for the construction of a $ 109,000,000.00 water treatment plant, known as the Frederick P. Griffith, Jr., Water Treatment Plant (the Project). The contract documents relevant to this case consist of the Agreement, the General Conditions, the Specifications, the Supplementary Conditions, the Contract Drawings (collectively the Contract Documents), and particular change orders, Change Order # 1 (COI) and Change Order # 3 (C03). See Joint Stipulation of Facts (JSF) ¶ 16. The controversy centers on the requirements for the construction of certain valves in the Filter Building. The parties agree that the Contract called for MCS to construct fourteen 42 inch Backwash Drain valves and fourteen 36 inch Filter Influent valves (collectively the Filter Butterfly Valves) in the Filter Building. See JSF ¶ 4. They disagree, however, whether the mechanisms operating the valves were to be extension stems, as claimed by MCS, or torque tubes, as claimed by the Authority.

On May 10,2000, the Authority issued its Notice to Proceed for MCS to commence its work on the Project pursuant to the Contract. See JSF ¶ 2. Between July 2000, when MCS sub-contracted with M & H Valve Company to install the Filter Butterfly Valves, and March 2002, MCS presented to representatives of the Authority four submittals for the installation of the Filter Butterfly Valves as well as a Request for Clarification (RFC 312). Each of theses documents called for the use of extension stems. See JSF ¶¶ 13,14. In March 2002, M & H Valve Company, MCS’s subcontractor, began furnishing valves with extension stems. See JSF ¶ 16.

After MCS commenced the installation of the Filter Butterfly Valves, field inspectors of the Authority’s engineer, Black and Veatch, Inc. (Black and Veatch), noted that the installation of the gear boxes on the Filter Butterfly Valves was creating potential problems for future valve repairs and maintenance. See JSF ¶ 17. As a result, employees of Black and Veatch reviewed the original Contract Drawings on May 3,2002, at the request of the Authority, and advised the Authority in writing that the drawings required torque tubes, not extension stems, for the Filter Butterfly Valves. See JSF ¶ 18, Exh. 12. Consequently, on May 7, 2002, the Authority forwarded Black and Veatch’s May 3,2002, letter to MCS as a “Record Copy” of the Butterfly Valves Submittal. See JSF ¶ 20. Additionally, during the same time frame, the Authority notified representatives of MCS that torque tubes were in fact required for the Filter Butterfly Valves. See JSF ¶ 19.

[175]*175In late June 2002, the parties executed C03. See Exh. 3. Among other things, C03 called for MCS to be paid an additional $133,283.00. In C03, MCS agreed that it would not make any claims pursuant to the General Conditions of the Contract for the period ending June 7,2002, except pursuant to certain Requests for Change Proposals (RCP) delineated in C03. No reference was made to the Filter Butterfly Valves in any of the listed RCPs.

At a meeting during the summer of 2002, representatives of MCS requested compensation for the claimed “extra work” it was performing on the Filter Butterfly Valves to replace the extension stems with torque tubes. In response, the Authority withheld part of a payment due to MCS because of MCS’s failure to have installed the torque tubes. In September 2002, Frederick Thompson, then MCS’s project manager on the Project, became involved in the discussions concerning the valve issue. Between September 2002 and May 2003, additional conversations took place between representatives of the Authority and representatives of MCS concerning the Filter Butterfly Valve issue. While making it clear that MCS believed that the installation of torque tubes would constitute a change to the Contract, the representatives of MCS proposed alternative ways of operating the valves, which included both torque tube and extension stem options. See JSF ¶¶ 21, 23. Steve Weisberger, the Authority’s Resident Engineer in Charge of Construction (REICC), asked MCS on multiple occasions to explain in writing why torque tubes were not required pursuant to the Contract. At no time during these discussions did the Authority ever agree to change its position on this issue and issue a change order. See JSF ¶ 23.

Eventually, on May 23, 2003, the Authority issued a non-compliance notice to MCS (NCN 187) officially informing MCS that its installation of the extension stems, instead of the torque tubes, was in contravention of the Contract between the parties. See JSF ¶ 26. MCS nonetheless continued to attempt to convince the Authority to change its position and by letter dated October 17, 2003, MCS requested that the Authority either “reconsider” its decision on the Filter Butterfly Valves issue or issue an RCP for a change to the Contract authorizing additional payment to MCS. See Exh. 26. On January 15, 2004, Chris Triolo, the Authority’s project manager for the Project, advised MCS in writing that the Authority was denying MCS’s request for additional compensation for the claimed “extra work” it was required to undertake to install the torque tubes. See Exh. 29.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kearney v. Robinson Land Trust
80 Va. Cir. 467 (Charlottesville County Circuit Court, 2010)
AMEC Civil, L.L.C. v. Commonwealth
74 Va. Cir. 492 (Norfolk County Circuit Court, 2008)
Modern Continental South v. Fairfax County Water Authority
72 Va. Cir. 268 (Fairfax County Circuit Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
70 Va. Cir. 172, 2006 Va. Cir. LEXIS 39, Counsel Stack Legal Research, https://law.counselstack.com/opinion/modern-continental-south-v-fairfax-county-water-authority-vaccfairfax-2006.