Modern Continental South v. Fairfax County Water Authority

72 Va. Cir. 268, 2006 Va. Cir. LEXIS 263
Fairfax County Circuit Court·Decided November 21, 2006·No. Case No. (Law) 225019·Published·Cited by 3 cases

Opinion

By Judge Stanley P. Klein

This matter remains before the court on Plaintiffs Motion for Reconsideration of this court’s orders of February 9,2006, and February 13, 2006, sustaining Defendant’s First and Third Pleas in Bar and dismissing this matter with prejudice.

The underlying dispute arises out of a March 23, 2000, contract between the Fairfax County Water Authority (the Authority) and Modem Continental South (MCS) for the construction of a $109,000,000.00 water treatment plant, known as the Frederick P. Griffith, Jr., Water Treatment Plant (the Project). The controversy centers on the requirements for the construction of certain valves in the Filter Building. The parties disagree as to whether the mechanisms operating the valves were to be extension stems, as claimed by MCS, or torque tubes, as claimed by the Authority.

In its letter opinion of February 9,2006 [70 Va. Cir. 172], this court has already addressed almost all of the issues raised by MCS in its Motion for Reconsideration, including all of the arguments relating to the court’s mling on the Authority’s Third Plea in Bar. The Court remains convinced that both Virginia law and the Contract between the parties supports its mling on the [269] Third Plea in Bar, and, therefore, the portion of the Motion for Reconsideration challenging the court’s ruling on the Third Plea in Bar is denied for the reasons set out in the court’s February 9,2006, opinion letter. However, MCS did raise one issue concerning the Authority’s First Plea in Bar which merits further discussion, as it was not addressed in the court’s original opinion letter. The court notes that MCS’s argument concerning the “Spearin Doctrine” was addressed solely in one footnote in MCS’s original briefing of the issues raised in the Authority’s Pleas in Bar. See Plaintiffs Brief in Opposition to Defendant’s Pleas in Bar, at 6, n. 9.

In its Motion for Reconsideration, MCS argues that this court erred by interpreting the Contract between the parties as imposing an “unlimited obligation” upon MCS to identify and point out any and all errors or conflicts in the Contract Documents. MCS asserts that this court must interpret the Contract in light of the so called Spearin Doctrine of contract interpretation which dictates against “shifting unlimited risk for owner-caused conflicts to the contractor.” Plaintiffs Memorandum in Support of Motion for Reconsideration p. 5, referencing United States v. Spearin, 248 U.S. 132, 39 S. Ct. 59, 63 L. Ed. 166, 54 Ct. Cl. 187 (1918). MCS contends that it was only required to report patent or obvious errors or conflicts that it knew or should have known existed in the Contract Documents and that it did not assume unlimited responsibility for owner-originated design flaws. Thus, this court is asked to re-evaluate the duty imposed upon MCS by not only the express language of the Contract but also an analysis of the Spearin Doctrine.

In United States v. Spearin, the United States Supreme Court addressed a federal contract containing language requiring Spearin, the contractor, to assume responsibility for verification of plans and specifications for the construction of a dry-dock at the Brooklyn Navy Yard. United States v. Spearin, 248 U.S. 132, 133, 39 S. Ct. 59, 60, 63 L. Ed. 166, 54 Ct. Cl. 187 (1918). The contract, in part, required the contractor to divert and relocate a section of a sewer piping and the plans included specific provisions directing the dimensions, material, and location of the section of the sewer pipe to be relocated. Prior to entering into the dry-dock contract, neither the Government nor Spearin was aware that there was a dam in a connecting piece of sewer pipe which would divert large quantities of water to the replacement pipe during periods of heavy water flow. Id. at 134, 39 S. Ct. at 60. The Government was aware, however, that the sewers in the area of the dry-dock had overflowed from time to time in the years prior to the start of the dry-dock construction, but this information was not communicated to Spearin. Spearin complied with the plan requirements for relocation of the sewer pipe, and the Government accepted the work as satisfactory. Id.

[270] Approximately one year after the sewer pipe relocation, during a period of heavy rain coincident with high tide, excess internal pressure caused the new pipe to break and flood the excavation area for the dry-dock. Spearin promptly informed the Government that he considered the sewers under the construction area to be “a menace to the work” and that he would not continue construction until the Government either “made good or assumed responsibility” for the damage which had already occurred. Id. at 135, 39 S. Ct. at 60. He also informed the Government that he would not continue construction until the Government either made appropriate changes to the sewer system in the area or assumed responsibility for “damage which might thereafter be occasioned.” Id. In response, the Government insisted that Spearin bore the responsibility for addressing the existing conditions and, after many months of unproductive discussions, the Government annulled the contract and sought a new contractor to complete the project. Id. at 135, 39 S. Ct. at 61. As a result, Spearin filed suit, and at trial was awarded not only the sum due for the work already completed but also the profit he would have earned had he completed the project. Id.

On appeal, the Supreme Court observed that principles of federal contract law dictated that the Government could not pass on to Spearin the responsibility for the failure of the relocated pipe. The Court reasoned as follows:

Where one agrees to do, for a fixed sum, a thing possible to be performed, he will not be excused or become entitled to additional compensation, because unforeseen difficulties are encountered.... But if the contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specifications. ... This responsibility of the owner is not overcome by the usual clauses requiring builders to visit the site, to check the plans, and to inform themselves of the requirements of the work. . ..

Id. at 136, 39 S. Ct. at 61 (citations omitted).

The risk of the existing system proving adequate might have rested upon Spearin, if the contract for the dry-dock had not contained the provision for relocation of the six-foot sewer. But the insertion of the articles prescribing the character, dimensions, and location of the sewer imported a warranty that, [271] if the specifications were complied with, the sewer would be adequate. This implied warranty is not overcome by the general clauses requiring the contractor to examine the site, to check the plans, and to assume responsibility for the work until completion and acceptance. ... The duty to check plans did not impose the obligation to pass upon their adequacy to accomplish the purpose in view.

Free access — add to your briefcase to read the full text and ask questions with AI

Modern Continental South v. Fairfax County Water Authority, 72 Va. Cir. 268, 2006 Va. Cir. LEXIS 263 (Va. Super. Ct. 2006).

72 Va. Cir. 268 (Modern Continental South v. Fairfax County Water Authority) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related