Ippolito v. Borough of Ridgefield

109 A. 337, 94 N.J.L. 97, 1920 N.J. LEXIS 144
CourtSupreme Court of New Jersey
DecidedMarch 8, 1920
StatusPublished
Cited by1 cases

This text of 109 A. 337 (Ippolito v. Borough of Ridgefield) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ippolito v. Borough of Ridgefield, 109 A. 337, 94 N.J.L. 97, 1920 N.J. LEXIS 144 (N.J. 1920).

Opinion

The opinion of the court was delivered hy

Walker, Chancellor.

This appeal brings up for review the action of the Bergen County Circuit Court in granting defendant a nonsuit on counts 2, 3, 4, 5 and 6 of the complaint. At the close of the'plaintiff’s case counsel for the defendant moved to strike out a large part of the testimony and made what he said would lie in effect a motion for a non-suit. This was addressed to all six of the counts in the complaint. The court overruled the motion as to the first count, and, declining to strike out tine testimony, turned the motion into one for a nonsuit and granted it as to the last fiv'e counts. ■The case was then submitted to the jury on the first count, who returned a verdict for plaintiff. A money judgment was thereupon entered in favor of the plaintiff and against the defendant for the sum found due hy the jury, with judg[99]*99ment against the plaintiff on the nonsuit. The plaintiff has appealed to this court from the judgment of: nonsuit against him. The colloquy between court and counsel on the motion to strike out evidence, turned into a motion for nonsuit, is reported verbatim and covers some fifteen printed pages of the state of the case. This is not in accord with approved practice. In moving for a nonsuit, counsel should state specifically the grounds upon which the motion is rested; but the arguments thereon should not he taken down by the stenographer, and should not be returned with the record or printed. Koch v. Costello, 93 N. J. L. 367. The trial judge gave no reasons for his action in granting tire nonsuit. This also is not in accord with approved practice. While the arguments of counsel on a motion to nonsuit should not be taken down, the judged deliverance in granting or refusing it, should be, as counsel for the defeated party is entitled to know the reasons upon which the judge’s determination is rested, so that lie may the better answer them in the court above, in case of appeal, and, besides, the appellate court is entitled to be informed of the grounds of the decision which it is required to review.

The respondent received competitive bids after due advertisement for constructing a sewage disposal plant. The form of proposal required lump sum bids for the disposal plant complete, as per plans and specifications, and also unit price bids for contingent extras., if required in the construction of the plant, work on which no unit prices were bid to be done for actual cost plus fifteen per cent. Appellant bid $10,300 for the sewage disposal plant, complete, unit prices for contingent extras, and work on which no unit prices were bid for cost plus fifteen per cent. This bid was accepted and a contract between him and the borough was executed in accordance therewith. The plans' and specifications described the plant as made up of a settling tank of the Tmhoff type, supported on a double circle of piles, the inner circle to support the upper section of the tank; sludge drying beds formed of steam cinders compacted by ramming and sealed with clay, and Ihe necessary piping to convey the sewage from [100]*100the settling tank to the sludge beds, and to convey the effluent into an adjacent creek. -

Before the plant was completed, defendant stopped the work. The first count of the complaint is upon this breach of contract, for the value of his work, labor and materials done and performed under the original contract, and for plaintiffs profit on the work not done, and on this count he had a judgment, from which no appeal has been taken. As to count Kb. 2. While the contractor was in the midst of the work, and the foundation which had been called for originally was nearly completed, the borough -decided it to be unsafe to bear the burden proposed to be placed on it, and passed a formal resolution that the contractor be authorized and required to do certain -work for which no unit prices were provided in the bid and proposal made by him, at a cost which proved to be far in excess of $500. After this work was practically finished the borough became doubtful as to whether it. wanted- to complete the Imhoff system, and called in an additional engineer who investigated the subject and stopped all -work, and the contractor was subsequently ordered off the job.

It is true that by the statute (chapter 342, Fmvph. L. 1912, p. 593), it is provided that whenever it shall be lawful for a public body to let contracts for doing work or furnishing materials or labor, where the sum to be expended exceeds the sum of $500, the action of such public body in entering into any such contract shall be invalid unless there shall first be public advertising for bids and the award made to the lowest responsible bidder. In this case the contract, as already remarked, was let after advertising, and it contained a provision for what were called contingent extras, and pay for all work for which1 unit prices were not provided, at actual cost plus fifteen per cent. The original lump- sum contract price was $10,300, and it is true that the cost of the extra work for which unit prices were not provided, plus fifteen per cent., amounted to $13,358.75', a sum considerably in excess of the original contract price.

[101]*101The defence was not fraud but ultra vires. It is not disputed that the plaintiff’s bid was tlie lowest under the notice, proposal and specifications, all constituting part of the contract, and all prepared by the borough. But it is claimed that the provision for payment on the basis of cost plus fifteen per cent., as to work not covered by the original plans and specifications, and the “contingent extras',” made the bidding non-competitive and the entire contract void. These provisions in and of themselves do not avoid the conrtaet.

In Browning v. Freeholders of Bergen, 79 N. J. L. 494, it was held in this court (at p. 497) :

“While there is nothing in the statute that expressly authorizes a call for these unit prices, the demand for them, as a protective measure to the public in the event of modification of the work to be clone by the contractor, ÍS' entirely unobjectionable. Clearly this was the only purpose for such a demand as expressed in the present proposal. The competitive feature of the proposal was the bids (called in the proposal dump sum’ bids) which each bidder was required to make for the completion of the entire work according to the plans and specifications exhibited to all alike; the call for ■ unit prices, on the other hand, was a protective measure in. view of possible demands that might be made upon the successful bidder when he should have become the contractor, for modification, in the details of the contract, presumably not }7et determined upon by the hoard, and certainly not disclosed to the bidders, or to all of them alike.”

City of Chicago v. McKechney, 91 Ill. App. 442, was a suit by contractors for compensation for extra work under an agreement for constructing a tunnel in the city of Chicago. They had a verdict and the city appealed. The judgment was affiianed. The agreement contained a provision that when the tunnel was partly in earth and partly in rock an additional price per cubic foot for rock excavation above the unit price per lineal foot of earth would be allowed. There were disputes between the parties including extra allowances for rock excavation, and all work on the contract was suspended. The contract had been let under a statute which [102]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Busch v. Joint Drainage District No. 49-79
198 Iowa 398 (Supreme Court of Iowa, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
109 A. 337, 94 N.J.L. 97, 1920 N.J. LEXIS 144, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ippolito-v-borough-of-ridgefield-nj-1920.