Standhardt v. Flintkote Co.

508 P.2d 1283, 84 N.M. 796
CourtNew Mexico Supreme Court
DecidedApril 13, 1973
DocketNo. 9292
StatusPublished
Cited by16 cases

This text of 508 P.2d 1283 (Standhardt v. Flintkote Co.) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standhardt v. Flintkote Co., 508 P.2d 1283, 84 N.M. 796 (N.M. 1973).

Opinion

OPINION

MONTOYA, Justice.

This cause comes before us for the second time on appeal. Initially, the plaintiff Board of Education, School District No. 16, Artesia (School Board), filed its complaint, subsequently amended, in the District Court of Chaves County, against W. R. Bauske, d/b/a W. R. Bauske and Company (Bauske) ; his bonding company, United States Fidelity and Guaranty Company (Fidelity), for breach of contract for the construction of a school building; against Frank M. Standhardt (Standhardt), the general architect, for breach of architectural contract and negligence; against Hamilton Roofing Company (Hamilton), the roofing contractor for breach of its roofing guarantee; and against the Flintkote Company (Flintkote), the manufacturer of a monoform roofing compound used by Hamilton, to recover damages from Flintkote for breach of express and implied warranties. Standhardt filed a third party complaint against Flintkote seeking indemnity. After a trial on the merits, judgment was entered dismissing the School Board’s complaint against Bauske and Hamilton. Standhardt’s third party complaint was also dismissed. The trial court entered judgment for the School Board against Standhardt and Flintkote, jointly and severally, in the amount of $34,600, plus interest. Defendants’ appeal from that judgment was considered by this court in Board of Education, School District 16 v. Standhardt, 80 N.M. 543, 458 P.2d 795 (1969), to which reference is made for a more complete statement of facts and issues involved in the prior appeal. In that case, we affirmed the judgment in favor of the School Board against Standhardt, but reversed the School Board’s judgment against Flintkote. We also reinstated the third party complaint of Standhardt against Flintkote, and remanded for a trial of the issues raised by the third party complaint.

On remand, the trial court entered judgment for Standhardt against Flintkote, based upon contribution in the amount of $25,085, plus interest from the date of judgment. Flintkote appeals this decision. Standhardt, the third party plaintiff, cross-appeals seeking indemnity for $50,170, the full amount awarded the School Board.

At the trial of the issues raised by the third party complaint, the evidence submitted was only one exhibit showing payment of the judgment by Standhardt. The trial court heard a motion to dismiss the third party complaint, which motion was overruled. The trial court then entered its decision to the effect that all previous findings and conclusions left undisturbed by the Supreme Court were still in effect, and readopted the same. The trial court further held that both Standhardt and Flintkote were in pari delicto and joint tortfeasors, and awarded Standhardt judgment for $25,085, or one-half of the sum previously paid by Standhardt.

Flintkote appeals, contending the court erred in entering judgment against Flinlkote in favor of Standhardt. Standhardt cross-appeals, seeking indemnity for the full amount of $50,170.

The issues raised in Flintkote’s appeal seeking reversal are to the effect that it was not a tortfeasor under the strict products liability rule; that it was under no duty to warn the architect of a possible defect in architect Standhardt’s revised plans and specifications; that the acts and omissions of Standhardt were the sole and proximate cause of the damage; that Flintkote cannot be held liable for any breach of warranty or representation because of change in plans and specifications made by the architect; and finally, that there was absence of proof that the damage was proximately caused by a defect in its product.

On the other hand, Standhardt also appeals claiming indemnity from Flintkote, claiming that as the manufacturer and supplier the material furnished did not perform as represented; that he is entitled to judgment against Flintkote on the theory of breach of express as well as implied warranty ; and further claims common law liability on the part of Flintkote, asserting the latter was actively negligent; and finally asserts he is entitled to recover under the doctrine of strict liability in tort.

Since, by its action upon remand, the trial court readopted all findings and conclusions previously made and left undisturbed by our prior opinion, we must examine the original findings and conclusions made by the trial court to dispose of the issues on this appeal. The findings that we are concerned with in disposing of this appeal are as follows:

“10. Defendant Standhardt’s plans and specifications were faulty in design and defective, insufficient and unsuitable for the purpose for which they were intended insofar as the slab roof and general waterproofing over the main structure of said school building is concerned. The design and the waterproofing materials specified were insufficient and defective; the same was and is not impervious to the elements and acts of nature and has leaked precipitation since its completion and still continues to do so.
«* *
‘T3. The plans and specifications prepared by defendant Standhardt did not produce a structure reasonably fit for its intended purpose, and designed to keep out rainfall or other precipitation.
“ * *
“18. The original specifications for the Abo School roof slab provided for a 15 inch monolithic layer of concrete measuring 201 feet in length by 144 feet in width, all without expansion or other joints and laid on top of steel trusses; the specifications, as modified, provided that on top of the monolithic slab would be laid a waterproof type of roofing capable of withstanding a one-foot hydrostatic head of water; on top of the roofing would be laid three inches of insulating material (pumice), and the latter would, in turn, be topped with three inches of concrete, this being the outside or top surface of the school.
lt ‡ :{!
“21. During the time defendant Standhardt was preparing the plans and specifications for the Abo School, defendant Flintkote, acting by and through its agents, servants and employees, represented and warranted to defendant Standhardt that the Flintkote Company manufactured and sold a monoform roofing material known as Monofilm Compound CMR/FM 200 and Monoform Glass Roofing Type 1 which, if applied to the Abo Elementary School by Hamilton Roofing Company, would provide proper protection against the elements and make the roof thereof waterproof; that Hamilton was an applicator of said Flintkote product approved by defendant Flintkote; that Flintkote is a company of many years’ standing, nationwide in the scope of its business operations, manufacturing a multitude of products from railroad cars to chemicals, and that reliance on the integrity of its products could reasonably be expected.
“22. These representations and warranties of defendant Flintkote were made by duly qualified agents of Flintkote to defendant Standhardt in Roswell, New Mexico.
“23. Relying upon said representations and warranties, the defendant Standhardt provided in the specifications for the Abo School that said Flintkote product above-mentioned be used.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bellman v. NXP Semiconductors USA, Inc.
248 F. Supp. 3d 1081 (D. New Mexico, 2017)
Norwood v. Raytheon Co.
237 F.R.D. 581 (W.D. Texas, 2006)
Parker v. E.I. Du Pont De Nemours & Co.
1995 NMCA 086 (New Mexico Court of Appeals, 1995)
Olson v. Prosoco, Inc.
522 N.W.2d 284 (Supreme Court of Iowa, 1994)
Fernandez v. Ford Motor Co.
879 P.2d 101 (New Mexico Court of Appeals, 1994)
Dessauer v. Memorial General Hospital
628 P.2d 337 (New Mexico Court of Appeals, 1981)
Larson MacHine, Inc. v. Wallace
600 S.W.2d 1 (Supreme Court of Arkansas, 1980)
Sanchez v. City of Espanola
615 P.2d 993 (New Mexico Court of Appeals, 1980)
Bendorf v. Volkswagenwerk Aktiengeselischaft
540 P.2d 835 (New Mexico Court of Appeals, 1975)
Standhardt v. Flintkote Company
508 P.2d 1283 (New Mexico Supreme Court, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
508 P.2d 1283, 84 N.M. 796, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standhardt-v-flintkote-co-nm-1973.