City of Pawhuska v. Dahlstrom

243 P. 248, 116 Okla. 21
CourtSupreme Court of Oklahoma
DecidedNovember 10, 1925
Docket15838
StatusPublished
Cited by4 cases

This text of 243 P. 248 (City of Pawhuska v. Dahlstrom) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Pawhuska v. Dahlstrom, 243 P. 248, 116 Okla. 21 (Okla. 1925).

Opinion

Opinion

by FOSTER, C.

The defendants in error were plaintiffs and the plaintiff in error was defendant in the trial court, and they will be so designated here.

The plaintiffs, T. Dahlstrom and J. W. Kelso, copartners, doing business under the firm name and style of Dahlstrom Improvement Company, recovered a judgment against the defendant, city of Pawhuska, in the district court of Osage county for the sum of $3,788.10, alleged to be due them under a contract whereby they performed certain extra labor in the construction of a sewage disposal plant, which they were under contract to construct for said defendant. Issues were joined and the cause was tried to the court and a jury, resulting in judgment for the amount stated. From this judgment, and from an order overruling its motion for a new trial, the defendant brings the cause regularly on appeal to this court, by petition in error and case-made attached, for review.

The specifications of error relied on by the defendant for a reversal of the judgment are: (a) Error by the trial court in rejecting competent testimony offered, and (b) error by the trial court in not directing the jury to render a verdict in favor of the defendant, upon the ground that the undisputed evidence showed that the plaintiffs and the defendant had a final settlement of all claims on March 26, 1923.

*22 • The facts necessary to he stated, in order to dispose of the legal propositions raised and discussed by the defendant in its brief, are substantially as follows: In the early part of the year 1921, the defendant voted bonds in the sum of $51,000, for the construction of a sewage disposal plant. On December 21, 1921, the defendant entered into a written contract with the plaintiffs to construct this plant for the sum of $39,400, according- to plans and specifications drawn by the Olmslead Engineering Company, at the instance of the defendant, which company was also under contract with the defendant to supervise the construction thereof. Work proceeded under this contract until in June, 1922, when the defendant made a contract with Phelps & Son, engineers, to succeed the Olmstead Engineering Company, who prepared new plans and specifications. On August 5, 1922, the plaintiffs and the defendant entered into another written contract, whereby the plaintiffs agreed to build a plant to conform to the new plans made by Phelps & Son, for an additional sum of $6,500, and to waive any claim for damages under the original contract. It appears that in the month of September, 1922, after the plaintiffs had commenced work under the new contract of August 5, 1922, certain changes in the plans and specifications were made by the superintendent of Phelps & Son, in charge of the work of construction, whereby the plant was moved back into the bank of the creek a distance of 17 1-2 feet, making necessary an additional excavation of some 1,912 cubic yards of dirt. The record further discloses that under the contract between Thelps & Son and defendant, the engineers had full authority to supervise the work of constructing the plant, and that the aforesaid changes in the plans and specifications ordered by them were approved by the defendant with full knowledge. Defendant at the same time had notice that the cost of moving the plant a distance of 17 1-2 feet would be extra. The plant was finally completed in March, 1923, accepted by the defendant, and the sum of $45,900, payable under both contracts, was finally received by the plaintiffs on March 26, 1923. Subsequently a claim for extra work and material under the second contract, in the sum of $9,-794, was filed by plaintiffs, and rejected by the city, whereupon plaintiffs entered suit therefor, resulting in a judgment as stated, in the sum of $3,788.10.

It is apparent from the foregoing statement, that the only .question before the trial court was whether or not plaintiffs were entitled to recover for extras under the second contract. This question was submitted to the jury, and the jury, by its verdict, found ttjat they were entitled to recover the sum of $3,-788.10, and if no prejudicial errors of law were committed by the trial court in its ruling upon law questions presented during the trial, and there is evidence reasonably tending to support the verdict, it must be sustained on appeal. It is insisted by the plaintiffs, however, that the trial court erred in excluding - the first contract offered in evidence by defendant. We cannot agree to this contention. It being specifically pleaded by defendant that the contract of August 5, 1922, covered the extras for which this action was brought, we cannot see how the first contract would be material or competent, unless the two contracts are to be considered as parts of one and the same contract.

Under the issues, as framed by the pleadings in the case, it would seem that the only question was whether the plaintiffs, by accepting the full amount of $6,500, provided for in the contract of August 5, 1922, could claim an additional sum thereunder for extras furnished. However that may be, we observe nothing in the situation of the parties, at the time the contract of August 5, 1922, was executed, indicating that that contract was to be used rn connection with or as a part of the first contract. The situation and conduct of the parties support rather the conclusion that the parties regarded the first contract as having accomplished its purpose, and that a new and independent contract was necessary in order to cover new matters not comprehended in the first contract.

The second contract specifically provided that the contractor should do the work shown on the construction drawings made by Phelps & Son for a specified sum. The mere fact that the work and payments under each contract proceeded contemporaneously, and that they were with the same contractor, did not make one contract in any way dependent upon the other.

There is no contention made, as we understand it, that the second contract was ambiguous so as to make extrinsic evidence competent to explain it, and if the contract be in writing, it must be permitted to speak for itself. Virginia-California Gasoline Co. v. Jordan, 98 Okla. 148, 224 Pac. 325.

It is apparent that the parties, by the contract of August 5, 1922, intended to contract concerning new and different work not covered by the original contract, and we think the contractors are entitled to recover for extras furnished under the new tr tract without reference to anything that fljlj have *23 been contained in the original agreement. This result would follow, even without a, new contract, where the contractor was required to perform large quantities of work different in character from that originally contemplated by the parties when they made the contract. Salt Lake City v. Smith, 104 Fed. 457.

We do not think that the exclusion of this contract operated to the substantial prejudice of the plaintiffs, justifying a reversal of the judgment. Nor do we think the refusal of the trial court to admit the contract of defendant with the Olmstead Engineering Company reversible error.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thorp v. Rutherford
43 P.2d 907 (Oregon Supreme Court, 1934)
City of Healdton v. Blackburn
1934 OK 573 (Supreme Court of Oklahoma, 1934)
Oldenburg v. Claggett
20 P.2d 234 (Oregon Supreme Court, 1933)
Walbridge-Aldinger Co. v. Rudd
26 F.2d 636 (Eighth Circuit, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
243 P. 248, 116 Okla. 21, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-pawhuska-v-dahlstrom-okla-1925.