Walbridge-Aldinger Co. v. Rudd

26 F.2d 636, 1928 U.S. App. LEXIS 3756
CourtCourt of Appeals for the Eighth Circuit
DecidedMay 7, 1928
DocketNo. 7941
StatusPublished
Cited by5 cases

This text of 26 F.2d 636 (Walbridge-Aldinger Co. v. Rudd) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walbridge-Aldinger Co. v. Rudd, 26 F.2d 636, 1928 U.S. App. LEXIS 3756 (8th Cir. 1928).

Opinions

SYMES, District Judge.

The appellant, plaintiff below, contracted with the city of Tulsa to excavate and lay a water conduit from what is known as Spavinaw Lake to Tulsá. The entire job was divided into 20-odd contracts, two of which, numbers 4 and 6, were awarded to appellant, and comprise the major portion of the project. The controversies that arose out of both contracts have been litigated in the same action. In the course of the work disputes arose between the city and the contractor, and, upon failure to adjust the same, the contractor abandoned the work and brought a suit in the United States District Court to enjoin the city from taking over its plant and equipment, which it had assembled on the job, and for other relief. The injunction was refused, and on appeal to this court the judgment of the lower court was affirmed. Thereafter the case was tried upon its merits before a master, who found generally against appellant, the contractor. The District Court affirmed the master’s findings, and the ease is now here on appeal for the second time.

[637]*637Plaintiff contends in its argument and brief in this court that the master and lower court felt themselves bound to follow the construction of the contract by this court on the former appeal; that this was error, because the essential elements of the contract were not considered in the former opinion, and therefore it did not become the law of the ease — and asks us to construe the whole contract and grant the plaintiff rights which it claims it lost as a result of the former opinion, found in 1 F.(2d) 187.

The contract in question is lengthy and voluminous, and refers to and incorporates detailed specifications. The points urged here are: (1) Extra foot of ditch; that is, the contractor is entitled to recover for widr ening the ditch, one foot in excess of the dimensions required by the specifications. (2) Was the contractor entitled to extra compensation, by reason of the fact that he was compelled to do the backfilling in two operations rather than one? (3) Is the plaintiff entitled to additional pay for certain material referred to as hardpan, excavated, and claimed to have been wrongly classified? (4) Did the contractor have the right to quit work prior to completion, by reason of the alleged breach of the contract by the city; i. e., because the city lacked sufficient funds to pay for the full completion of the work?

The appellees raise a preliminary question, which, if resolved in their favor, eliminates the first two questions. It is: Is the construction placed upon the contract in question by this court on the first appeal the law of the case, and, if so, to what extent? Appellant claims that the previous decision and what was there considered is not binding, because it was an appeal from an interlocutory order, and consequently the whole case is now open for consideration de novo.

Point 3, supra, to wit, alleged wrongful classification of certain material, was not involved on the first appeal. Both sides concede it is here on the merits. The rule contended for, and which is supported by the great weight of the authorities, is stated in 4 C. J. p. 1104, § 3084: “Questions decided on appeal from an interlocutory decree will not be reconsidered on appeal from the final decree, and where no new questions are presented, on appeal from a final decree, that were not fully considered and settled on appeal from an interlocutory decree, the decree must be affirmed.” This rule is followed in this circuit. See Field v. Kansas City Refining Co., 9 F.(2d) 213; Brown v. Lanyon Zinc Co., 179 F. 309; Haley v. Kilpatrick, 104 F. 647. In Field v. Kansas City Refining Co., supra, it was held that the decision on a former appeal from an interlocutory injunction order was the law of the case on appeal from the final order, where no new facts were adduced, and the submission was substantially upon the same record. The Supreme Court and other circuits hold the same. Smith v. Vulean Iron Works, 165 U. S. 518, at page 522, 17 S. Ct. 407, 41 L. Ed. 810; Bissell Carpet-Sweeper Co. v. Goshen (C. C. A.) 72 F. 545.

The eases cited in opposition recognize the rule. For instance, in the Chase Case (C. C. A.) 261 F. 833, it is limited to those issues of law which- were before the appellate court on the previous hearing, and by it determined to be the law of the case, and no other. In City of Council Bluffs v. Omaha R. R. (C. C. A.) 9 F.(2d) 246, all Judge Sanborn states is that, on appeals from preliminary injunctions, only questions necessarily raised and necessary to a decision should, for obvious reasons," be decided. In Luminous Unit Co. v. Freeman-Sweet Co. (C. C. A.) 3 F.(2d) 577, the court simply points out that the rule is not an inexorable one, and should not be applied when the law is clearly erroneous, establishes a practice contrary to the best interests of society, and works a manifest injury in the particular case.

We now inquire: What questions were raised on the former appeal, and what was there decided? In that opinion Judge Scott says that the plaintiff abandoned, on application for a temporary injunction, its third contention, to wit, the alleged wrongful classification of excavated material. That the matters material on the appeal were the alleged wrongful insertion of the word “these” in the so-called whiteprint specification, as distinguished from the original blueprint one — a question not pressed in the instant case; the contentions relative to the “extra foot” of trench excavated, and the order dividing the backfilling into two operations, instead of one — both of which were made necessary by the breaking of the pipe.

The opinion discusses the contract generally, quotes the provisions material to the above on the points and the relevant evidence, and announces definite conclusions thereon. It fully sustains the powers of the engineers to pass upon these questions, and holds that the .contractor was not justified in stopping work and abandoning the contract. It would therefore seem that, unless we are of the opinion, which we are not, [638]*638that the previous decision of this court on these three points was clearly erroneous, and establishes a practice contrary to the best interests of society, or works a manifest injury in the particular ease, within the rule stated in Luminous Unit Co. v. Freeman-Sweet Co., supra, we are concluded from again considering the same questions.

This leaves for consideration, first, the contractor’s claim for additional allowance for excavating hardpan, said to have been erroneously classified and paid for as earth. The findings of the master on this point are as follows:

“Hwdpctn. — During the progress of the work a substance called hardpan was encountered, which was very difficult and expensive to excavate. It was a hard, gritty, conglomerate of clay and sand, or small pebbles, and was not uniform in its composition. The steam shovel could only operate in it by paring or scaling it off; dynamite would not blast it, because it would not shatter, and no progress could be made in it with a pick and shovel. It was in a compact mass and did not exist in a shattered condition. It was more expensive and difficult to excavate than shale or loose rock. It varied in depth from 1 to 4 feet, and when encountered would extend upwards for 300 lineal feet in the trench. It is commonly encountered in trench excavating and road work, and had been encountered by Mr. Aldinger, president of the plaintiff company, in other work done by him.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
26 F.2d 636, 1928 U.S. App. LEXIS 3756, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walbridge-aldinger-co-v-rudd-ca8-1928.