United States ex rel. Jennings v. Cooke

207 F. 682, 1913 U.S. Dist. LEXIS 1341
CourtDistrict Court, E.D. Washington
DecidedAugust 6, 1913
DocketNo. 1,581
StatusPublished
Cited by3 cases

This text of 207 F. 682 (United States ex rel. Jennings v. Cooke) is published on Counsel Stack Legal Research, covering District Court, E.D. Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Jennings v. Cooke, 207 F. 682, 1913 U.S. Dist. LEXIS 1341 (E.D. Wash. 1913).

Opinion

RUDKIN, District Judge.

On the 11th day of April, 1910, the' defendants George Cooke & Sous entered into a contract with the United States for the construction of 36 miles of laterals in connection with what is commonly known as the “Tieton project” under the Reclamation Service in Yakima county in this state, according to certain advertisements, proposals, plans, and specifications which were made a part of the contract. At the same time Cooke & Sons executed a bond to the United States in the penal sum of $30,000', with the defendant National Surety Company as surety, conditioned for the faithful performance of this contract and prompt payment to all persons supplying labor and material for the prosecution of the work provided for, as required by the acts of Congress in such cases made and provided. On the 21st day of September, 1911, P. A. Jennings, a subcontractor under Cooke & Sons, commenced an action in this court on the bond in the name of the United States to recover from the contractors and the surety company a balance of $5,181 alleged to be due under the subcontract with Cooke & Sons. Thereafter Minney & Maxwell, James Lineham, W. L. Carpenter, and O. F. Leonard, subcontractors under Cooke & Sons, and Samuel Bowles, P. O. Berglund, and W. E. Rahier, subcontractors under Minney & Maxwell, filed their complaints in intervention, likewise claiming a balance due from the principal contractors and the surety company under the terms of their several contracts.

Issues have been made up, and bj" stipulation of parties the case was tried by the court without a jury. The original contract and each of the subcontracts classify the material to be removed or excavated in the construction of the laterals as follows:

‘•(’lass 1. All material that is loose and can be handled with scrapers, and all material that, can be plowed by a six horse team, each animal weighing not less than 1,400 pounds, attached to a suitable plow, all well handled by at least three men; also all loose rocks in pieces not exceeding two cubic feet in volume occurring in loose material or in material that can bo thus plowed.
‘‘Class 2. All material not included in classes 1 and 3.
“Class 3. All rock in place that cannot be removed without the use of powder, and all detached masses of rock exceeding ten cubic feet in volume.”

The several contracts also contain the following stipulations:-

“It is mutually agreed between said parties that to prevent all disputes and misunderstandings between them in relation to any of the stipulations contained in this agreement, or their performance by either of said parties, that the said chief engineer or assistant engineers shall be and hereby is made an umpire to decide all matters arising or growing out of this contract between them.”
[684]*684“It is further mutually agreed and expressly understood that the decision of said chief engineer on any point or matter touching this agreement shall be final and conclusive between the parties hereto, and each and every of said parties hereby waives any and all right of action, suit or suits, or other remedy, in law or otherwise, under this contract, or arising out of the same.”
“And the said first party, in consideration of the fulfillment and performance of all the stipulations contained in this contract by said second party, to be by said second party fulfilled and performed, and whenever said work shall have been, in the opinion of said chief or assistant engineers, completely finished in every respect, and performed agreeably to the various stipulations and specifications of this agreement, and said chief or assistant engineers shall have furnished to said first party a certificate of the fact under his hand, together with his estimate of the quantities of the various kinds of work done by said second party under this agreement, which estimate shall be final and conclusive between the parties hereto, will pay to said second party, within thirty days after said certificate and estimate shall have been furnished by said chief engineer, the sum which may be due under this contract, agreeably to said estimates, at the following rates and prices.”

The rates differ in the different contracts, but all are based on the. same classification. In addition to the construction contract, the contractors further agreed to furnish supplies to the subcontractors at cost, with 10 per cent, added. The contracts for supplies were oral in all cases, and the witnesses naturally differ as to the language used. The terms of the supply contracts, if such they may be called, are perhaps correctly stated in a telegram and letter sent by the contractors to the subcontractor Uineham before the contracts were let. The telegram reads:

“Pay roll and fhrnishing supplies optional. If we handle, charge 10 per cent.”

This was explained in a letter of the same date as follows:

“We stated in our telegram that the handling of the pay roll and furnishing supplies were optional with you. This was in part an error, as we invariably make a stipulation with subcontractors that we shall furnish supplies, for which we charge 10 per cent, above actual cost, including freight. In case, however, you should wish to buy your supplies elsewhere, you would be perfectly free to do this, provided we receive the said 10 per cent. As to the pay roll, this is entirely optional with you. If you wish us to handle it, we will charge the 10 per cent, as stated.”

On the 13th day of October, 1910, the contractors sent to the subcontractor Lineham the following letter:

"We have this day raised the prices on various classes of material covered by your contract with us, dated May 2, 1910, as follows:
“Excavation—Glass No. 2, .48 (forty-eight cents).
“ — “ No. 8, 1.00 (one dollar ).
“Subject to the following provision: That you make a corresponding increase in the prices paid by you to your subcontractors, and that you pay the cost of liability insurance, which amounts to one-half of 1 per cent of your gross pay roll; also that you complete your work in the time allowed by the government engineer.”

Similar letters were sent to all other subcontractors under Cooke & Sons, but the date of the contracts and the amount of the increase were not the same in all cases.

Under the foregoing facts the following claims are made by the respective parties:

[685]*685First. The subcontractors under Cooke & Sons, other than Jennings and Minney & Maxwell, seek to avoid the force and effect of the certificate of the chief engineer of the Reclamation Service, or his assistants, because of their classification in part of what is commonly known as cement gravel under class 2 and their failure to classify it as “rock in place that cannot be removed without the use of powder, and all detached masses of rock exceeding ten cubic feet in volume,” under class 3.

Second.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Asfalto
45 F.2d 857 (S.D. New York, 1930)
Walbridge-Aldinger Co. v. Rudd
26 F.2d 636 (Eighth Circuit, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
207 F. 682, 1913 U.S. Dist. LEXIS 1341, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-jennings-v-cooke-waed-1913.