Peter Salvucci & Sons, Inc. v. State

268 A.2d 899, 110 N.H. 136, 1970 N.H. LEXIS 118
CourtSupreme Court of New Hampshire
DecidedFebruary 27, 1970
Docket5900
StatusPublished
Cited by23 cases

This text of 268 A.2d 899 (Peter Salvucci & Sons, Inc. v. State) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peter Salvucci & Sons, Inc. v. State, 268 A.2d 899, 110 N.H. 136, 1970 N.H. LEXIS 118 (N.H. 1970).

Opinion

Lampron, J.

Action by plaintiff under RSA 491:8 to recover damages from the State for a breach of contract involving the construction of a part of Interstate Route 93 in Franconia. Trial before a Master ( Charles J. Flynn, Esq. ). A view of the different sites involved was taken on July 5, 1966. Evidence was presented before the master on various days between July 11 and September 23, 1966. The master’s report included 60 specific findings and rulings made after a consideration of plaintiff’s 113 requests for findings and rulings and of 31 such requests submitted by the defendant. The parties also filed memoranda of law and written arguments. The master’s recommendation that the plaintiff be awarded the sum of $111,114.41 was accepted by the Superior Court (Botones, J.) and judgment for plaintiff entered in that amount plus interest and costs in accordance with a motion by plaintiff.

Defendant excepted to the denial of its motion to dismiss made at the end of plaintiff’s case and at the close of all the evidence. Defendant also excepted to the denial of its motions to set aside die master’s report and for a continuance of plaintiff’s motion for judgment on the report until the transcript of the evidence was available to the defendant. These exceptions were reserved and transferred by the Superior Court.

On January 13, 1958, Peter Salvucci and Sons, Inc., a Massachusetts corporation, entered into a contract with the State of *138 New Hampshire, for the bid price of $837,267.63, to construct 7200 feet of highway in the town of Franconia running from Station 1 to Station 72. This project (P-3293-A ) will be referred to as “Job A” or “Job I.” On April 29, 1958, the same parties entered into an agreement for the construction of 10,600 feet of highway adjoining the former and running from Stations 72 to 178. This project (P-3293-B) will be called “Job B” or “Job 2.” The completion date for both of these projects was October 15,1959.

The essentials of plaintiff’s claims are that in soliciting the bids for Job A the State represented to it that the work could be performed with materials obtained by widening the slopes of the highways; that free gravel and borrow could be obtained from the National Forest lands through which the highways were to be built; that the only cost to the contractor would be the cost of replanting the areas from which such materials were taken at a cost of approximately $50 per acre.

Plaintiff alleged “that when [it] undertook to do the work in the manner represented to it by THE STATE, it was denied the right to widen the slopes, and was denied the right to obtain free gravel and borrow from the National Forest Land, so that it had to obtain large quantities of gravel and borrow from other locations.

“THE STATE’S failure to make free gravel and borrow available, as represented, not only required that the Plaintiff pur - chase large quantities of material, which it was entitled to receive without charge, but also put the Plaintiff to great additional expense for the cost of digging and hauling the same, instead of being able to construct the projects as anticipated, by the use of much more economical machinery and equipment.”

The plaintiff further alleged that the State, subsequent to the awarding of these two contracts, reaffirmed its promise to make free borrow and gravel available to the plaintiff in quantities and qualities sufficient to satisfy the 340,000 cubic yards required to perform Job A at places and times necessary for its performance.

The plaintiff alleged that as a result of the breach of its contract by the State, both in its original misrepresentations and in its subsequent promises, it was put to great additional expense and suffered severe damages in its performance, not only of Job A, *139 but also of Job B. These breaches it is alleged caused the plaintiff direct extra expenses in the amount of $225,726.23 and also overall intangible inefficiencies on both jobs which together resulted in a net overall loss to the plaintiff of $454,614.93.

The master made the following findings:

1. The plaintiff Salvucci obtained its first road construction contract from the Highway Department in 1949 and worked almost continuously in New Hampshire from 1954 until the completion of Job A on October 20, 1959. During this period, the plaintiff did a considerable amount of road work for the State and built about 35-40 miles of roads in New Hampshire. The plaintiff was, in general, familiar with the policies, practices, and procedures of the Highway Department applying to road construction jobs and the handling of the clauses that appear in highway construction contracts.

2. On or about December 2, 1957, the State advertised for bids for the construction of a hot asphaltic concrete highway section ... [Job A] ... a portion of which passed through the White Mountain National Forest .... This was the first time that either the plaintiff or the defendant had been involved in the construction of a section of such a major highway through a portion of the White Mountain National Forest. A peculiar characteristic of the construction of this road was that it involved a considerable amount of more earth moving in the way of excavation and fill than is usually involved in the ordinary high - way job.

“ 3. As the Highway Department usually puts out a 6 month projection of pending projects, the plaintiff was aware of this Franconia job a few months prior to the advertising of bids on December 2, 1957. The plaintiff’s president, Peter Salvucci, had visited the site in question in October and November of 1957. On these occasions, he walked, where feasible, over the area where the road was to be constructed and looked over the area for material to do the job. There was no snow on the ground.

“ 4. After December 2, 1957, when the Highway Department sent out invitations to bid on Job A, the plaintiff obtained copies of the plans, profiles, test borings and soils data- applicable to this job.

“ 5. With a view to making a bid on Job A, the plaintiff’s key personnel . . . inspected the job site around the middle of *140 December 1957. At this time, there was some snow on the ground. Although they could not walk the base line of the road, these men, all experienced road builders, could get within a hundred feet or so of it and had a good idea as to the center line from observing stakes. Peter Salvucci, who had previously toured this job area, showed his brother, Ralph, [vice-president and general superintendent], and Eugene Kalafarski [plaintiff’s project engineer] the general layout and indicated where material might be obtained. Louis Thompson [plaintiff’s superintendent] who lived in the area, was also quite familiar with the job locale. Ralph scaled off an area between Stations 10-40 . . . and satisfied himself that there was sufficient material in this area in quantity to do Job A if the material were available.

6. After the aforesaid inspection, Ralph Salvucci had Eugene Kalafarski, who was an experienced engineer and knew what was needed in the way of material for this job, check (sic) on the boring and soils data of the Highway Department. Based on the information given to him by Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Missouri Consolidated Health Care Plan v. Community Health Plan
81 S.W.3d 34 (Missouri Court of Appeals, 2002)
Phillips v. Verax Corp.
637 A.2d 906 (Supreme Court of New Hampshire, 1994)
Palazzi Corp. v. Stickney
619 A.2d 1001 (Supreme Court of New Hampshire, 1992)
Cook v. Oklahoma Board of Public Affairs
1987 OK 22 (Supreme Court of Oklahoma, 1987)
R. Zoppo Co. v. City of Dover
475 A.2d 12 (Supreme Court of New Hampshire, 1984)
Ideker, Inc. v. Missouri State Highway Commission
654 S.W.2d 617 (Missouri Court of Appeals, 1983)
S & M Constructors, Inc. v. City of Columbus
434 N.E.2d 1349 (Ohio Supreme Court, 1982)
M. W. Goodell Construction Co. v. Monadnock Skating Club, Inc.
429 A.2d 329 (Supreme Court of New Hampshire, 1981)
Progressive Survey, Inc. v. Pearson
410 A.2d 1123 (Supreme Court of New Hampshire, 1980)
King v. Thomson
400 A.2d 1169 (Supreme Court of New Hampshire, 1979)
Erin Food Services, Inc. v. 688 Properties
401 A.2d 201 (Supreme Court of New Hampshire, 1979)
L-J, Inc. v. South Carolina State Highway Department
242 S.E.2d 656 (Supreme Court of South Carolina, 1978)
Emery v. Caledonia Sand and Gravel Co.
374 A.2d 929 (Supreme Court of New Hampshire, 1977)
Marcou Construction Co. v. Tinkham Industrial & Development Corp.
371 A.2d 1187 (Supreme Court of New Hampshire, 1977)
Paras v. City of Portsmouth
335 A.2d 304 (Supreme Court of New Hampshire, 1975)
Dove v. Knox Mountain Corp.
319 A.2d 640 (Supreme Court of New Hampshire, 1974)
Ass'n of Portsmouth Teachers v. Portsmouth School District
312 A.2d 573 (Supreme Court of New Hampshire, 1973)
Vitic v. New England Mortgage Investment Corp.
283 A.2d 490 (Supreme Court of New Hampshire, 1971)
State v. Peter Salvucci & Sons, Inc.
272 A.2d 854 (Supreme Court of New Hampshire, 1970)
J. Dunn & Sons, Inc. v. Paragon Homes of New England, Inc.
265 A.2d 5 (Supreme Court of New Hampshire, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
268 A.2d 899, 110 N.H. 136, 1970 N.H. LEXIS 118, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peter-salvucci-sons-inc-v-state-nh-1970.