Richman v. City of New York

89 Misc. 213, 151 N.Y.S. 744
CourtNew York Supreme Court
DecidedFebruary 15, 1915
StatusPublished
Cited by1 cases

This text of 89 Misc. 213 (Richman v. City of New York) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richman v. City of New York, 89 Misc. 213, 151 N.Y.S. 744 (N.Y. Super. Ct. 1915).

Opinion

Giegerich, J.

The action is to foreclose a lien claimed to have been acquired under a contract entered into on or about March 14, 1913, between the city of New York, by and through the public service commission for the first district, acting for the said city, and the defendant Cooper & Evans Company, whereby the [215]*215latter agreed to furnish all materials for and construct a steel elevated structure, part of the subway extension and designated as section 2 of the Astoria, Wood-side and Corona Rapid Transit railroad. The defendant Mulcahy & Gribson, Inc., was a subcontractor of the said defendant Cooper & Evans Company, undertaking the work of .erecting and painting the steel structure. The said defendant Mulcahy & Gribson, Inc., sublet the painting of the entire structure to the substituted plaintiff in this case, Joseph A. Rich-man, trading as the Pennsylvania Steel Painting Company of Philadelphia, Penn., by a contract dated July 3, 1913. On December 31,1913, the said Joseph A. Rich-man filed a lien with the public service commission of the first district and with the comptroller of the city of New York, alleging that there was due him from the defendant Mulcahy & Gribson, Inc., the sum of $8,333.32. On or about January 29, 1914, such lien was, pursuant to an order of this court, bonded by the filing with the comptroller of the city of New York of the bond on which the defendant Cooper & Evans Company was principal and the American Fidelity Company of Montpelier, Vt., was surety. The plaintiff claims that after he had completed sixty per cent of the work called for by his contract with the defendant Mulcahy & Gribson, Inc., the latter forcibly ejected him from the work on December 26, 1913, and refused to permit him and his employees to complete the work which he claims he could have done had he been allowed to continue on the job. Upon this claim, however, I find against the plaintiff upon the facts. A fair preponderance of the evidence shows that he proceeded so slowly with the work that numerous complaints were made in writing by the defendant Mulcahy & Gribson, Inc., to him of the slow progress of the work and insufficient number of men engaged upon it; [216]*216that complaints were also made by the engineer in charge of the work for the public service commission and by the inspectors under him of the bad work, slow progress and shortage of men; that the paint was improperly applied by the plaintiff’s men by applying it unevenly and failing to use brushes properly and sufficiently so as-to spread it out into a uniform layer and that in consequence thereof the red (first) coat showed through the black (second) coat and the black showed through the green (third) coat. The evidence further satisfies me that workmen employed by the plaintiff quit the job repeatedly on account of. a lack of money to pay them; that such wages were not paid on Saturday at the end of the week, but on the following Monday or Tuesday, and on Thursday, December 18, 1913, for the preceding week; that this delay caused continual trouble with the men on the work, who finally struck about noon on December 23 because they had not been paid their wages for the preceding week; that they also refused to work the next day, although the weather was clear; that no work was done on December 26, the day after Christmas, and that on Saturday, the 27th, the men were rioting and destroying property. The defendant Mulcahy & Gibson, Inc., took possession of the work on the afternoon of December 27, 1913, and proceeded to complete it under the contract, after having first given the plaintiff the following notice in writing, viz.:

“ December 23,1913.
“ The Pennsylvania Steel Painting Co., 1416 South Penn Square, Phila., Pa.:

“ Gextlemex—Upon going over the painting of the above job this morning we find that all your men have stopped work and will not continue until they are paid for their services. You are hereby again formally notified that the painting of the structural steel in con[217]*217nection with the above mentioned contract is not proceeding in a satisfactory manner, and unless you have a sufficient number of men employed on your work within three days from this date to insure the completion of same without further delay this company will, without further notice to you, take possession of this part of the work under your contract and complete same in accordance with the contract. We will consider this letter a three days ’ written notice in conformity with our contract.

“ Very truly yours,
“ Mulcahy & Gibson, L. 0. Reuss, Sec.”

The evidence shows that on the morning of December 27th the plaintiff came on from Philadelphia and went to the work and that his life was threatened by striking workmen; that in order to save himself from bodily harm he promised to come back at 1 o’clock in the afternoon and pay them, and that he never returned and never paid the men. The notice in question was mailed in New York city on December 23, 1913, and reached the plaintiff in Philadelphia on the following day. It was given pursuant to paragraph 7 of the said agreement between, the defendant Mulcahy & Gibson, Inc., and the plaintiff, which paragraph reads as follows: “ Seventh. The said party of the first part further agrees that if at any time it shall abandon the work or any part thereof, or shall refuse or neglect to prosecute the same with a force sufficient in the opinion of the party of the second part to insure its completion within the time specified in this agreement, or if the work is not being done or progressing according to the terms of this contract, the party of the second part shall have full power to notify said party of the first part to discontinue all work under this contract or any part of such work by a three days ’ written notice to be served upon the said party of the [218]*218first part, and thereupon the said party of the second part after said three days ’ notice shall discontinue the work or part thereof and the said party of the second part shall thereupon have the power to enter upon, take possession of and complete said work or to contract for the completion of the contract, and it shall have full power to take possession, without cost, of any or all plant, rigging, tools, equipment, paint, &c., and finish the work at the party of the first part’s expense, and the party of the first part shall forfeit all claim to the difference.” The defendant Mulcahy & G-ibson, Inc., completed the work at a cost of $6,336.69 in excess of the price fixed in the contract in question, and for this amount it has interposed a counterclaim. Instead of having painted sixty per cent of the structure on December 23, 1913, as claimed by the plaintiff, the evidence satisfies me that out of a total of two hundred and six sections in the entire structure the plaintiff had painted with two coats only fifty-eight sections, and that but twenty-eight additional sections had been painted one coat up to that day. This is less than thirty per cent of the work. The contract in suit required the painting of the structure to be finished within ten days after the completion of the riveting work by the defendant Mulcahy & G-ibson, Inc. The evidence shows that the painting work was far behind the riveters on December 23, 1913, when the plaintiff’s men quit work, as above stated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Troughton v. Digmore Holding Co.
105 Misc. 638 (New York Supreme Court, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
89 Misc. 213, 151 N.Y.S. 744, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richman-v-city-of-new-york-nysupct-1915.