Thilemann v. Mayor of New York

66 A.D. 455, 73 N.Y.S. 352
CourtAppellate Division of the Supreme Court of the State of New York
DecidedDecember 15, 1901
StatusPublished
Cited by3 cases

This text of 66 A.D. 455 (Thilemann v. Mayor of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thilemann v. Mayor of New York, 66 A.D. 455, 73 N.Y.S. 352 (N.Y. Ct. App. 1901).

Opinion

Patterson, J.:

This appeal is from a judgment in favor of the plaintiffs entered upon the verdict of a jury and from an order denying a motion for a new trial. Three causes of action are set forth in the complaint, and in submitting the cause to the jury the trial judge required them to make a special 'finding, with respect to each of the three causes of action separately. On the first cause of action the jury found for the plaintiff in the sum of $1,750, on the second $450, on the third $4,500. The plaintiffs were contractors with the city of New York for regulating, grading and paving Jerome avenue from One Hundred and Sixty-second street to Elliot street. In the performance of that contract the plaintiffs were required to furnish certain filling, and by the first cause of action they sought to recover 15,000 cubic yards of filling, which they allege .they furnished over and above the amount certified by the engineer and inspectors upon the work. The contract contained the provision that the contractor should be bound and concluded by the final certificate of the engineer. It also provided that all quantities of work and matérials ,to be paid for should be measured and determined by the engineer and his assistants, according to the plans and the working lines that might be given and the specifications when the work came up to such lines, and that no allowance should be made for any excess, above the quantities required by such plans, lines and specifications on any part of the work, and, further, that all loss or damage arising out of the nature of the Work to be done, or from the action of' the elements, was to be sustained by the contractor; also, that an embankment, which formed part of the work, should be maintained at its designated' width and grade' until finally accepted, and no allowance would be made to the contractor for shrinkage, sinkage or settlement.

The final certificate of the engineer stated- that the plaintiffs had [457]*457furnished, in the progress of the work,, 72,297.05 cubic yards of, filling. The plaintiffs claim that they had placed in the work 90,871 cubic yards of such filling. The contract price of the filling was thirty cents a cubic yard. The plaintiffs claim for 15,00& cubic yards, apparently .making an allowance of about 3,000 cubic yards for sinkage or shrinkage. In drawing the complaint the pleader evidently recognized that the final certificate of the engineer was an obstruction to the right of the plaintiffs to recover, and that certificate was attacked, it being alleged in the first (as well as in the second cause of action) that the engineer and inspector, or inspectors, in charge of the work under the contract, made certificates that were false and untrue, and given in bad faith and under a misconstruction of the contract. It has been held that where parties to a cohtract of this character have provided for a final and conclusive estimate of an engineer as an essential prerequisite to any payment of the contractor, the provision of* the contract shall be taken as binding and that the contractor is concluded thereby; and that where a certificate is given it is conclusive upon the parties, in the absence of proof of corruption, bad faith or misconduct on the part of the person signing, the certificate. It was held in Smith v. Mayor (12 App. Div. 391) that in the face of a certificate relating to the quantity of filling done on a contract of a character similar to that involved in this action, the contractor could not recover for an extra amount of filling unless he alleged and proved facts which would impeach the certificate as false, fraudulent or made in bad faith, or unless the final certificate was .based upon an erroneous construction of the contract. (Burke v. Mayor, 7 App. Div. 128.)

Unquestionably there may be such a gross mistake in a final certificate as would indicate fraud, or at least bad faith, in which case the contractor would not be concluded, but in the case before us there is no evidence of actual fraud or bad faith, nor can either of those qualities be impressed upon the certificate in consequence of a gross mistake appearing either upon the face of the certificate or extrinsically. When the evidence is critically examined, in connection with the provisions of the contract respecting the filling to be done and the duty of the contractor respecting the filling to be furnished, it does not appear that such a mistake as would avoid [458]*458the effect of the certificate was made. True, the final certificate of •the engineer was, or might have been, based upon' measurements made when the work was completed, but the plaintiffs were not entitled to any allowance for settlement or shrinkage of the embankment, or for the action of the elements. The indefiniteness of the evidence with respect to the causes which required additional filling •renders it impossible to conclude that any serious mistake was made by the engineer or inspectors in their measurements or in the final certificate by which the plaintiffs agreed to be bound.

The plaintiffs not having made proof of their allegation respecting the falsity or fraudulent character of the certificate, were not entitled to recover on this first cause of action. At the close of the plaintiffs’ case in chief a motion was made to dismiss the complaint on the ground that they had failed to establish a cause of action against the city. The defendant’s counsel had previously moved to strike out testimony given by the plaintiffs as to the amount of filling they had furnished and certain other testimony connected with, that subject, and he expressly moved again to strike out that testimony and that the first cause of action be dismissed. The court denied the motion, saying that it did not appear that the contract between the parties covered the contingency' of the plaintiffs, through the willful act or negligence of the city, being obliged tó do work in addition to that required by the contract; that in such case the plaintiffs were entitled to recover the value of that additional work in the way of labor or material or both, and all that the inspector or engineer was required to do was to furnish a certificate of the work that actually remained and appeared, in sight and was. a subject of measurement, and that if additional material were consumed for a cause which originated through and was entirely due to the negligence of the city and which was not contemplated in the contract and should not be the subject-matter of a certificate, the contractor was entitled to recover for that, independently of the amount agreed upon in the contract. To that ruling an exception was taken.

The rule of law which the learned judge had in mind was evidently that laid down in Horgan v. Mayor (160 N. Y. 516) and Mulholland v. Mayor (113 id. 631). Ho such claim or cause of action is counted upon in the first cause of action as would render [459]*459that rule applicable. If we are correct in our construction of the complaint as to that cause of action, it is founded upon the wrongful character of the certificate, and not upon any. neglect of the city. In submitting the case to the jury, the learned judge made no reference to the averments of the complaint concerning the falsity of the certificate, but sent that cause of action to the jury on the plaintiffs’ right to recover for negligence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Duffy Bros. v. Bing & Bing, Inc.
217 A.D. 10 (Appellate Division of the Supreme Court of New York, 1926)
E. E. Smith Contracting Co. v. City of New York
209 A.D. 271 (Appellate Division of the Supreme Court of New York, 1924)
Thilemann v. Mayor of New York
71 A.D. 595 (Appellate Division of the Supreme Court of New York, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
66 A.D. 455, 73 N.Y.S. 352, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thilemann-v-mayor-of-new-york-nyappdiv-1901.