Neidlinger v. Onward Construction Co.

107 A.D. 398
CourtAppellate Division of the Supreme Court of the State of New York
DecidedAugust 15, 1905
StatusPublished
Cited by6 cases

This text of 107 A.D. 398 (Neidlinger v. Onward Construction Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neidlinger v. Onward Construction Co., 107 A.D. 398 (N.Y. Ct. App. 1905).

Opinion

The following is the opinion of Herrick, J.:

Herrick, J.:

This case turns upon the sufficiency and effect of an architect’s certificate and the circumstances under which it was given.

“ It is now too well settled in this State to be questioned that where the parties have selected an arbitrator who is to determine the questions that arise during the performance of the contract, and [400]*400upon whose certificate the payments are to be made,; and it is provided in the contract that the determination of such arbitrator is to be binding upon them, his determination is a condition precedent to the right of either party to recover under the contract, and that, in the absence of fraud or palpable mistake, his certificate is final.” (Del Genovese v. Third Ave. R. R. Co., 13 App. Div. 412.)

“ A valid award or. estimate operates as a final and conclusive judgment, and however disappointing it may be, the parties must abide by it. * * * It is well settled that while an award may be set aside for a palpable mistake of fact in the nature of a clerical error, such as a miscalculation of figures, still in general such mistake to be available must appear on the face of the award or in some paper delivered with it.. * * * In the absence of proof of corruption, bad faith or misconduct on his part or palpable mistake appearing on the face of the estimate, neither party can be allowed to prove that he decided wrong as to the law or facts.” (Sweet v. Morrison, 116 N. Y. 19.)

The award of an arbitrator cannot be set aside for mere error of judgment as to the law or facts of the case submitted to him. If, in making his award, he keeps it within his jurisdiction and is not guilty of fraud, corruption or other misconduct affecting his award, then his award is unassailable.” (Masury v. Whiton, 111 N. Y. 679.)

“ The conclusiveness of awards is based upon the principle that the parties having chosen judges of their own and agreed to abide by their decision, they are bound by their agreement.and compelled to perform the award.” (Matter of Wilkins, 169 N. Y. 494, 499.)

By the provisions of the contract in this case the architect of the defendant was made the arbitrator between the parties subject to an appeal to three arbitrators in the manner provided for in the contract.

The contract here provides for the giving of a final certificate by the architect.

It provides that no alteration shall be made in the work called for by the contract and specifications, except by the written order of the owner, and when so made the value of the work added or omitted shall be computed by the architect and added to or deduéted from the contract price.

There is also a provision in the contract that the owner shall pay any damage to the contractor caused by the owner delaying the [401]*401material progress of the work, and that the contractor shall pay any damage that the owner shall suffer because of any delay to¿¡the material progress of 'the work caused by the contractor, and that the amount of snch damage suffered, by either party, shall in every case be fixed and determined by the architect.

There are also provisions as to the appointment of arbitrators when either party is dissatisfied with the determination of the architect upon any of these matters.

As to the determination of the architect of the value of added or omitted work which -shall be added to or deducted from the contract price, the value of such work necessarily has to he passed upon separately, and a separate certificate of determination is proper, although not perhaps .necessary.. In the event of a separate certificate being made, then another would be made of the balance due upon the contract as such, and the amount of the one added to or deducted from the other. Or there may be a determination and certificate of the balance due upon the contract, which shall, in fact, include the value of the work added to or omitted from the contract price, although not separately stated as such in the determination and certificate. So also as to the damages caused by the delay, either of the contractor or of the owner, it is obvious that there may be a separate determination and certificate as to each of

them, -or there may be a certificate of determination which simply sets forth the balance due to either on account of such damages.

A certificate upon any one of these subjects, upon which the architect is empowered to pass, is final unless appealed from to arbitrators, as provided for in the contract.

If there has been no determination made, or certificate given, upon or for any matter left to his determination, then as to .such matters the parties should be precluded from litigating them here; they have by their contract agreed upon the court to pass upon such matters, and "unless it has unreasonably or corruptly passed upon or refused to pass upon them they are not excused for the non-production of its certificate of determination.

If there has been no determination made or eerfifieate given upon any matter left to the determination of the court agreed upon, then, unless that lack of determination or furnishing of a certificate [402]*402thereof is attributable to the unreasonableness or fraud of such court, such matter should not be passed upon here.

In this case the certificate of the architect embodied a determination of three things, all of which he was empowered to determine by the contract.

First. The fact that the contract was completed.

Second. The amount due upon the contract, not determining or certifying, however, the value of added or omitted work caused by alterations to the contract.

Third.. The damages sufferted by the plaintiff because of delays caused by the defendant.

The schedule of damages affixed to the certificate shows that this, was made up entirely and exclusively of the plaintiff’s damages, no deduction being made therefrom of damages suffered by the defendant, caused by the plaintiff’s action.

The owner seeks to impeach the validity of this certificate in all particulars, because, as he says, he was not heard upon these questions, and that the architect passed upon them without considering his claims; that he had a large number of men at work going through the building, making' an examination of the work done, and that they had not completed that examination at the time the architect gave his certificate.

While not necessary, it is perhaps well to consider briefly the justice of these complaints. The contract requires that payment shall be made thirty days after the completion of the contract.

The specifications which are made a part of the contract provide that when the work' is completed the contractor shall notify the owner or its agent that he is ready to" receive a settlement, so that if it has any bills to file or statements to make it can do so before the architect makes his final certificate.

On the 7th of February, 1903, the contractor notified^ the owner that it ■ was “ ready to receive a settlement so that you can file any bills or statements which yon have to make with the architect at once.” This request was repeated in letters dated March twenty-eighth and April sixth, thirteenth and twenty-seventh.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barash v. Board of Education
226 A.D. 249 (Appellate Division of the Supreme Court of New York, 1929)
E. E. Smith Contracting Co. v. City of New York
209 A.D. 271 (Appellate Division of the Supreme Court of New York, 1924)
Oscar Daniels Co. v. City of New York
196 A.D. 856 (Appellate Division of the Supreme Court of New York, 1921)
Wm. P. Jungclaus Co. v. Ratti
118 N.E. 966 (Indiana Court of Appeals, 1918)
Condict v. . Onward Construction Co.
103 N.E. 886 (New York Court of Appeals, 1913)
Neidlinger v. Onward Construction Co.
124 A.D. 26 (Appellate Division of the Supreme Court of New York, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
107 A.D. 398, Counsel Stack Legal Research, https://law.counselstack.com/opinion/neidlinger-v-onward-construction-co-nyappdiv-1905.