People ex rel. Cranford Co. v. Willcox

153 A.D. 759, 138 N.Y.S. 1055, 1912 N.Y. App. Div. LEXIS 9359
CourtAppellate Division of the Supreme Court of the State of New York
DecidedDecember 20, 1912
StatusPublished
Cited by4 cases

This text of 153 A.D. 759 (People ex rel. Cranford Co. v. Willcox) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
People ex rel. Cranford Co. v. Willcox, 153 A.D. 759, 138 N.Y.S. 1055, 1912 N.Y. App. Div. LEXIS 9359 (N.Y. Ct. App. 1912).

Opinion

Scott, J.:

'The relator is a contractor for building a section of the underground rapid transit railway. The defendants are the Public Service Commissioners for the First District in the State of New York, who have succeeded to all the powers and duties of the board of rapid transit railroad commissioners (Public Service Commissions Law, Laws of 1907, chap. 429). The purpose of this proceeding is to compel the defendants to certify to the comptroller of the city of New York for payment the amount of an award in arbitration. The relevant facts, although somewhat complicated, are not in dispute.

On May 27, 1907, the board of rapid transit commissioners, in the name and behalf of the city of New York, contracted with relator for the construction of a section of the subway. On February Í8, 1908, the contract was amended in certain, particulars with the consent of the relator and the Public Service Commission, which had then succeeded to' the powers and duties of the rapid transit board. There is no question made as to the validity of this amendment. The powers of the Commission are very broad in that respect, and the contract itself provided for changes in the plans and specifications at the will of the Commissioners, and for compensation for increased or additional work necessitated thereby. It also provided that it might be altered in more material provisions by a written instru[761]*761ment duly authorized by the board and consented to by the contractor.

The contract, as amended, called for the driving of certain wooden piles of a specified size and length at the intersection of Canal and Centre streets. As the work progressed the engineer determined that it was impracticable or inadvisable to use wooden piles, and directed that steel piles filled with concrete should be used instead. The contractor, as he was bound to do, complied with this requirement, but promptly notified the Commission that he should claim that the work thus ordered was additional to that included in the contract, and that it would be more expensive than the piling required by the contract. The contractor has fully completed his contract, his work has been accepted and wholly paid for, except as to the matter involved in this proceeding, the determination as to which has been expressly reserved, so that relator is not concluded as to this claim by reason of having accepted payment for the amount conceded to be due him.

The contract provided that in case there should be a dispute as to whether any work required was within the contract price, the contractor should do the work as ordered, leaving the question of its right to be compensated therefor as extra or additional work to be decided by arbitration in the manner elaborately provided for in the contract. The arbitration provisions were in brief that (a) the contractor shall file a claim; (b) the engineer shall make a written determination thereon allowing or disallowing it; (c) either party may appeal to two arbitrators, one chosen by each; (d) if the arbitrators disagree, and so certify, the controversy shall be determined within five days (unless time is extended by his order) by an umpire chosen by the executive committee of the Chamber of Commerce, whose award shall be effectual if concurred in within such five days by one of the arbitrators.

The contractor duly filed claims with the engineer for extra compensation for driving piles during the months of August, September and October, 1908. The engineer disallowed these claims, which were duly referred to two arbitrators chosen as provided in the contract. Pending the decision of the arbitrators, it was mutually agreed that other claims for the same [762]*762work during the months succeeding October, 1908, should be deemed to be decided according to the decision of the arbitrators. After considering the claims the arbitrators disagreed, one holding that the work was extra or additional work for which the contractor was entitled to be paid, and the other holding that it was not. The arbitrators did not consider or attempt to pass upon the question as to how much the contractor should be paid if the work was to be considered as extra or additional work. Upon their disagreement an umpire was appointed, who duly decided that the work was extra or additional work and that the contractor was entitled to be paid therefor. Having thus decided, he proceeded tó inquire how much should be paid to the contractor. A question as to his jurisdiction to pass upon this question at once arose, the Commission contending that under the terms of the contract the umpire had authority only to pass upon questions as to which the arbitrators had disagreed, and inasmuch as the arbitrators had not considered the question as to the amount to be paid to the contractor, and consequently had not disagreed thereon, it was not competent for the umpire to pass upon it. To avoid any question upon this score the contractor and the Commissioners entered into a further arbitration agreement, which recited the arbitration proceedings theretofore had, and the question which had arisen as to the authority of the umpire 'to determine the amount of additional compensation to which the contractor is entitled. The arbitrators appointed were the same persons who had been arbitrators and umpire under the earlier arbitration, and the submission to them was in the following terms:

“Now, therefore, the parties to this agreement do agree that said Charles Strauss, said Edward S. Clinch and said Edward- G. Whitaker be and they hereby are constituted and appointed arbitrators (the determination of any two of them to be binding) to hear and determine the question of the amount of additional compensation which the contractor is entitled to receive on account of all of said pile driving work (including so much of said work as was in arbitration as aforesaid), and that all fees and expenses of said arbitrators shall be borne and paid equally by the parties to this agreement.
[763]*763“ In making their determination said arbitrators shall assume as having been finally determined that the contractor is entitled to receive from the city as extra compensation the excess in cost of driving the piles in the manner in which they were driven over and above the cost of driving the piles required under said contract, as modified, the city not conceding, however, by this agreement that the cost of driving the piles in the manner in which they were driven exceeded the amount which it would have cost to drive the piles as required under said contract, as modified.
“ If said arbitrators shall determine that reasonable profit and administration expenses should be added to the actual cost of the work as done and to the actual cost of the work required to be done, as aforesaid, the word ‘cost ’ as hereinbefore used shall be interpreted to include such profit and administration expenses.”

The arbitrators, in due course, made an award to the relator of the sum of $59,867.64, with interest from August 4, 1910, being the date of the certificate of final completion of relator’s work under said contract.

The Commission having refused to certify this amount to the comptroller of the city of New York for payment, this proceeding was instituted to compel such certification.

The Special Term, without passing upon the validity of the award, denied the motion upon the ground that mandamus was not the proper remedy, but that the plaintiff should enforce his right by action against the city of New York, and this • presents the first question to be considered.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jannis v. Ellis
308 P.2d 750 (California Court of Appeal, 1957)
In re the Arbitration between C. F. Simonin's Sons, Inc. & Antonio Corrao Corp.
285 A.D. 953 (Appellate Division of the Supreme Court of New York, 1955)
Oscar Daniels Co. v. City of New York
196 A.D. 856 (Appellate Division of the Supreme Court of New York, 1921)
People ex rel. New York Dock Co. v. Delaney
192 A.D. 734 (Appellate Division of the Supreme Court of New York, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
153 A.D. 759, 138 N.Y.S. 1055, 1912 N.Y. App. Div. LEXIS 9359, Counsel Stack Legal Research, https://law.counselstack.com/opinion/people-ex-rel-cranford-co-v-willcox-nyappdiv-1912.