Rapid Transit Subway Construction Co. v. City of New York

129 Misc. 714
CourtNew York Supreme Court
DecidedApril 15, 1927
StatusPublished
Cited by1 cases

This text of 129 Misc. 714 (Rapid Transit Subway Construction Co. v. City of New York) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rapid Transit Subway Construction Co. v. City of New York, 129 Misc. 714 (N.Y. Super. Ct. 1927).

Opinion

Mullan, J.

The plaintiff was awarded by the city the contract for the construction of section 7, route 5, of the Lexington Avenue subway, extending from the south side of Forty-third street to a point fifty feet north of the center line of Fifty-third street. After completion of the work the plaintiff brought this action to [717]*717recover moneys claimed to be due to it from the city under provisions of the contract, and as damages it alleges it was caused by breaches on the part of the city. The action originally came on for trial before Mr. Justice Wagner, and it was stipulated that a jury should be waived, but that a jury should be deemed present, so that the disposition of the case could be made by way of the direction of a verdict, thus avoiding the need of findings. After Mr. Justice Wagner had taken testimony for several days, an adjournment of indefinite length was agreed upon in order to afford opportunity to the parties to negotiate for the settlement of some at least of the plaintiff’s claims. Several months elapsed, and counsel then reported that they were unable to come to any agreement, except as to certain minor" items. Meantime Mr. Justice Wagner had been designated to sit on the bench of the Appellate Division, and I consented to take over the trial, and did so take it over, upon a stipulation that the testimony taken before Mr. Justice Wagner should be deemed to have been taken before me. After taking further testimony for several weeks, I decided that it would be advisable to order an adjournment pending the handing down by the Court of Appeals of its decision in the case of Litchfield Construction Co. v. City of New York (244 N. Y. 251), another subway case, in which the court had before it the question whether the city was liable for the acts and conduct of the Public Service Commissioners, and their employees, in and "about the construction of the subways, the Rapid Transit Act having provided that subway construction, if resorted to by the city, must be under the control and supervision of the Commission as a State agency. The highest court having decided that the city, by its contracts with the contractors, voluntarily nominated the Commissioners and their employees as its representatives for the prosecution of the work, and that thus the city was liable for their acts and conduct to the same extent as if they were city officials and employees (Litchfield Case, supra), the trial was resumed and concluded. The volume of testimony was great, and the exhibits were many. In passing upon the numerous claims, I shall endeavor to be as brief as properly consists with a desire to lighten the burden of the appellate courts, to which this case will in all probability go.

Claim No. 1. (For payment for side wall drains.) This claim was settled as to principal, the city agreeing to pay the sum of $1,420.63, with interest. There is conflict of view as to the law governing the date from which interest should be computed. A similar controversy rims throughout the action, and I shall deal with it at the close of my memorandum, there passing upon all interest questions in one place.

[718]*718Claim No. 2. (For payment for underpinning of buildings.) This claim involves the construction of certain provisions of sections 69 and 70 of the contract in relation to the underpinning of buildings along the line of excavation. In subdivision 2 of section 69 appears the following: “ By underpinning is meant such method of construction as will transmit the foundation loads directly through the underpinning structure to such lower level as is necessary to secure the buildings and which will relieve the adjacent ground from improper lateral pressures. The underpinning shall be designed to furnish a safe and permanent support for each independent building.” In section 70 it is provided that the specified prices for underpinning are per lineal front foot of building underpinned.” The plaintiff was paid at the contract unit price ($60 per lineal foot) for the lineal footage of the length of the actual underpinning. Its contention is that it should have been paid for the entire front footage of every building it underpinned, regardless of the nature or extent of the underpinning work. Its counsel argues, for example, that if the corner, or other small part, of a building having a frontage of 100 feet is underpinned, at a cost no matter how trifling, the contractor would be entitled to receive payment in the sum of $6,000. A literal reading of the price provision quoted undeniably supports that contention. Its counsel concedes that plaintiff would receive a very considerable profit by the adoption of the construction it urges, and as there is no suggestion that the payment for underpinning it has already received was not compensatory, I am free to infer that the adoption of the city’s theory would not entail an actual loss to plaintiff on this item. Moreover, it was asserted by the corporation counsel, and not disputed by plaintiff’s counsel, that the practical construction placed by the city and contractors generally on these underpinning provisions in subway contracts has always been that urged by the city in the instant case. Nevertheless, although at first I was strongly inclined to a contrary view, I believe the plaintiff is entitled to the construction it contends for. Some underpinning is of the pier type, in which a small area of actual underpinning supports a very much larger area of building frontage, and I have come to the conclusion that it was the intention roughly to average the cost, and that it is of no materiality that the contractor may in a given case be showm to have profited through the law of chance having run in his favor. Support to the literal meaning of the price provision is derived from the estimate of approximate quantities contained in the contract with respect to underpinning work. It is there estimated that the underpinning for this section of the subway will protect 1,300 lineal front feet of buildings, 1,200 feet (buildings under [719]*719seven stores in height) at $60 per lineal foot, or $72,000, and 100 feet (buildings over seven stories in height) at $100 per lineal foot, or $10,000. The subway section covered by the contract runs from Forty-third street to Fifty-third street, making twenty blocks of approximately 200 feet each, counting both sides of the avenue. If the city’s construction were to be adopted, the estimated footage of underpinning would be greatly in excess of probable need. Additional support is lent to the construction plaintiff contends for by a provision in section 449 of the contract, entitled Special Matters,” in which the following is to be found: “ If it is found necessary to underpin * * * the retaining wall on the westerly side of Lexington Avenue along the New York Central and Hudson River Railroad Company’s yard or property, the contractor * * * ghall be paid for such underpinning * * * at the unit prices specified in the Schedule applicable to the several classes of work and material involved. * * * The prices stipulated in [naming the price items for underpinning] do not apply to the work of underpinning * * * said retaining wall.” That provision furnishes argument for the connotation that all other underpinning work should be priced at an underpinning unit designed to operate arbitrarily and regardless of the amount of work and labor involved. This claim covers another item as to which the plaintiff should, I think, also succeed. Under that item the plaintiff claims payment for underpinning a building in a side street and not at a station.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rapid Transit Subway Construction Co. v. City of New York
231 A.D. 721 (Appellate Division of the Supreme Court of New York, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
129 Misc. 714, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rapid-transit-subway-construction-co-v-city-of-new-york-nysupct-1927.