Litchfield Construction Co. v. City of New York

216 A.D. 517, 215 N.Y.S. 450, 1926 N.Y. App. Div. LEXIS 9262
Appellate Division of the Supreme Court of the State of New York·Decided April 30, 1926·Published·Cited by 5 cases

Opinion

Finch, J.

The questions which arise upon this appeal have to do with the liability of the city under a written contract made by the Public Service Commission, on behalf of the city, for the construction of a section of subway work. The contractor sues the city, in part, for moneys which may be said to be due under the contract and, in part, for damages. The alleged liability of the city upon these various items makes necessary the determination upon this appeal of certain limits of the liability of the city under such a contract.

The complaint alleges that on or about May 21, 1915, the Public Service Commission for the First District, on behalf of the city, entered into a contract with the Litchfield Construction Company, one of the plaintiffs herein, for the construction of certain sections of the Broadway-Fourth Avenue Rapid Transit Railroad in accordance with certain specifications and drawings and at certain unit prices to be paid by the city of New York. By section 4 of chapter 3 of the contract it is provided that Working drawings necessary to amplify the contract would be furnished by the engineer of the Public Service Commission to the contractor; that the first of these would be furnished within thirty days after the delivery of the contract and thereafter from time to time, as might be reasonably and necessarily required by the contractor. The contract was delivered on May 26, 1915. It required actual Work to be commenced within sixty days thereafter, completion for railroad operation in twenty-two months, or by March 26, 1917, and entire completion in twenty-six months, or by July 26, 1917. [520] The work was completed for railroad operation March 4, 1919, and was entirely completed May 9, 1919, a delay of twenty-three months and six days in respect to the first period and of twenty-one months and fifteen days in respect to the second or final period. The contract provided that time was of the essence. The complaint alleges two causes of action.

By the first cause of action the sum of $79,889.85 is demanded, consisting of two items, namely, an item of $71,090.15, for percentages retained from various payments pursuant to article XXXIII of the contract, and an item of $7,799.70 for extra work, labor and materials claimed to have been furnished under article XII of the contract.

The second cause of action consists of three items: First, for $982,336.85 claimed as damages for breach of the contract Because of alleged delays in furnishing working drawings and in approving sheet drawings of structural steel necessary to the progress of the work; second, a claim for $72,666.28, suSdivided as follows: (a) Damages for breach of contract in that there was eliminated a section of the construction work which was the subject of the contract, namely, the spur under Central Park from Seventh avenue and West Fifty-ninth street; (b) by requiring the contractor to use fourteen per cent more cement in making the concrete than was required by the specifications; (c) by requiring the plaintiff to underpin certain buildings'which were founded upon rock and to rebuild certain duct lines; the third item was for $82,134.07 for damages claimed because of false estimates of the quantities, nature and extent of the Work to be performed.

At the close of the whole case the following took place: Both parties moved for the direction of a verdict on the claim for the pumping of certain sewage under the second item of the first cause of action. The court directed a verdict in favor of the plaintiffs on this item for $9,850.75.

Likewise both parties moved for the direction of a verdict in connection with the claim for damages for the elimination of the spur under Central Park. The court directed a verdict in favor of the plaintiffs on this item for $16,813.65.

The plaintiffs moved for a directed verdict on the claim for excess cement required to be used in making concrete as claimed in item (b) above. The defendant asked to go to the jury on the question as to whether or not the contractor had complied with the specifications. The court granted the plaintiffs’ motion for the direction of a verdict in the sum of $5,578.19.

The plaintiffs moved for the direction of a verdict on the claim for damages because of alleged false estimates of quantities of [521] work to be done. As to this, the defendant asked to go to the jury on the question as to whether or not the contractor was in fact misled, and as to whether there were any damages suffered. The court, however, directed a verdict in favor of the plaintiffs for the sum of $40,296.05.

The total of the directed verdicts in favor of the plaintiffs amounted to $72,538.64.

There were then submitted to the jury issues arising in connection with retained percentages of money earned and damages for breach of contract by delay in furnishing plans. As to these, the jury returned a verdict of $89,876.59 on the first item, and on the second item, namely, damages for breach of contract for delay, the jury returned a verdict for $813,000, a total in all of $975,415.23.

A counterclaim interposed by the city, claiming liquidated damages of $159,684.85 for the contractor’s delay in completing the work on time and $87.56 for work which it is claimed the contractor failed to perform, or a total counterclaim of $159,772.41, was dismissed on the merits. Interest upon said verdict was assessed at $3,206.84 and the costs were taxed at $177.04 together with an additional allowance of $2,000, making a total of $980,799.11 for which judgment was rendered.

Taking up first the item of damages for the delay of the engineer of the Public Service Commission in furnishing plans, the question arises whether the city is liable for damages resulting from the negligence of the employees of the Public Service Commission as distinguished from liability for what can be said to be moneys due under the contract, and for extra work and materials ordered by the Public Service Commission and actually supplied by the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Litchfield Construction Co. v. City of New York, 216 A.D. 517, 215 N.Y.S. 450, 1926 N.Y. App. Div. LEXIS 9262 (N.Y. Ct. App. 1926).

216 A.D. 517 (Litchfield Construction Co. v. City of New York) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ryan Co. v. Sanitary District
47 N.E.2d 576 (Appellate Court of Illinois, 1943)
Sandy Hites Co. v. State Highway Commission
149 S.W.2d 828 (Supreme Court of Missouri, 1941)
Rapid Transit Subway Construction Co. v. City of New York
129 Misc. 714 (New York Supreme Court, 1927)
Litchfield Construction Co. v. City of New York
219 A.D. 369 (Appellate Division of the Supreme Court of New York, 1927)
Litchfield Construction Co. v. City of New York
155 N.E. 116 (New York Court of Appeals, 1926)