Finch, J.
The questions which arise upon this appeal have to do with the liability of the city under a written contract made by the Public Service Commission, on behalf of the city, for the construction of a section of subway work. The contractor sues the city, in part, for moneys which may be said to be due under the contract and, in part, for damages. The alleged liability of the city upon these various items makes necessary the determination upon this appeal of certain limits of the liability of the city under such a contract.
The complaint alleges that on or about May 21, 1915, the Public Service Commission for the First District, on behalf of the city, entered into a contract with the Litchfield Construction Company, one of the plaintiffs herein, for the construction of certain sections of the Broadway-Fourth Avenue Rapid Transit Railroad in accordance with certain specifications and drawings and at certain unit prices to be paid by the city of New York. By section 4 of chapter 3 of the contract it is provided that Working drawings necessary to amplify the contract would be furnished by the engineer of the Public Service Commission to the contractor; that the first of these would be furnished within thirty days after the delivery of the contract and thereafter from time to time, as might be reasonably and necessarily required by the contractor. The contract was delivered on May 26, 1915. It required actual Work to be commenced within sixty days thereafter, completion for railroad operation in twenty-two months, or by March 26, 1917, and entire completion in twenty-six months, or by July 26, 1917. [520] The work was completed for railroad operation March 4, 1919, and was entirely completed May 9, 1919, a delay of twenty-three months and six days in respect to the first period and of twenty-one months and fifteen days in respect to the second or final period. The contract provided that time was of the essence. The complaint alleges two causes of action.
By the first cause of action the sum of $79,889.85 is demanded, consisting of two items, namely, an item of $71,090.15, for percentages retained from various payments pursuant to article XXXIII of the contract, and an item of $7,799.70 for extra work, labor and materials claimed to have been furnished under article XII of the contract.
The second cause of action consists of three items: First, for $982,336.85 claimed as damages for breach of the contract Because of alleged delays in furnishing working drawings and in approving sheet drawings of structural steel necessary to the progress of the work; second, a claim for $72,666.28, suSdivided as follows: (a) Damages for breach of contract in that there was eliminated a section of the construction work which was the subject of the contract, namely, the spur under Central Park from Seventh avenue and West Fifty-ninth street; (b) by requiring the contractor to use fourteen per cent more cement in making the concrete than was required by the specifications; (c) by requiring the plaintiff to underpin certain buildings'which were founded upon rock and to rebuild certain duct lines; the third item was for $82,134.07 for damages claimed because of false estimates of the quantities, nature and extent of the Work to be performed.
At the close of the whole case the following took place: Both parties moved for the direction of a verdict on the claim for the pumping of certain sewage under the second item of the first cause of action. The court directed a verdict in favor of the plaintiffs on this item for $9,850.75.
Likewise both parties moved for the direction of a verdict in connection with the claim for damages for the elimination of the spur under Central Park. The court directed a verdict in favor of the plaintiffs on this item for $16,813.65.
The plaintiffs moved for a directed verdict on the claim for excess cement required to be used in making concrete as claimed in item (b) above. The defendant asked to go to the jury on the question as to whether or not the contractor had complied with the specifications. The court granted the plaintiffs’ motion for the direction of a verdict in the sum of $5,578.19.
The plaintiffs moved for the direction of a verdict on the claim for damages because of alleged false estimates of quantities of [521] work to be done. As to this, the defendant asked to go to the jury on the question as to whether or not the contractor was in fact misled, and as to whether there were any damages suffered. The court, however, directed a verdict in favor of the plaintiffs for the sum of $40,296.05.
The total of the directed verdicts in favor of the plaintiffs amounted to $72,538.64.
There were then submitted to the jury issues arising in connection with retained percentages of money earned and damages for breach of contract by delay in furnishing plans. As to these, the jury returned a verdict of $89,876.59 on the first item, and on the second item, namely, damages for breach of contract for delay, the jury returned a verdict for $813,000, a total in all of $975,415.23.
A counterclaim interposed by the city, claiming liquidated damages of $159,684.85 for the contractor’s delay in completing the work on time and $87.56 for work which it is claimed the contractor failed to perform, or a total counterclaim of $159,772.41, was dismissed on the merits. Interest upon said verdict was assessed at $3,206.84 and the costs were taxed at $177.04 together with an additional allowance of $2,000, making a total of $980,799.11 for which judgment was rendered.
Taking up first the item of damages for the delay of the engineer of the Public Service Commission in furnishing plans, the question arises whether the city is liable for damages resulting from the negligence of the employees of the Public Service Commission as distinguished from liability for what can be said to be moneys due under the contract, and for extra work and materials ordered by the Public Service Commission and actually supplied by the contractor.
Free access — add to your briefcase to read the full text and ask questions with AI
Finch, J.
The questions which arise upon this appeal have to do with the liability of the city under a written contract made by the Public Service Commission, on behalf of the city, for the construction of a section of subway work. The contractor sues the city, in part, for moneys which may be said to be due under the contract and, in part, for damages. The alleged liability of the city upon these various items makes necessary the determination upon this appeal of certain limits of the liability of the city under such a contract.
The complaint alleges that on or about May 21, 1915, the Public Service Commission for the First District, on behalf of the city, entered into a contract with the Litchfield Construction Company, one of the plaintiffs herein, for the construction of certain sections of the Broadway-Fourth Avenue Rapid Transit Railroad in accordance with certain specifications and drawings and at certain unit prices to be paid by the city of New York. By section 4 of chapter 3 of the contract it is provided that Working drawings necessary to amplify the contract would be furnished by the engineer of the Public Service Commission to the contractor; that the first of these would be furnished within thirty days after the delivery of the contract and thereafter from time to time, as might be reasonably and necessarily required by the contractor. The contract was delivered on May 26, 1915. It required actual Work to be commenced within sixty days thereafter, completion for railroad operation in twenty-two months, or by March 26, 1917, and entire completion in twenty-six months, or by July 26, 1917. [520] The work was completed for railroad operation March 4, 1919, and was entirely completed May 9, 1919, a delay of twenty-three months and six days in respect to the first period and of twenty-one months and fifteen days in respect to the second or final period. The contract provided that time was of the essence. The complaint alleges two causes of action.
By the first cause of action the sum of $79,889.85 is demanded, consisting of two items, namely, an item of $71,090.15, for percentages retained from various payments pursuant to article XXXIII of the contract, and an item of $7,799.70 for extra work, labor and materials claimed to have been furnished under article XII of the contract.
The second cause of action consists of three items: First, for $982,336.85 claimed as damages for breach of the contract Because of alleged delays in furnishing working drawings and in approving sheet drawings of structural steel necessary to the progress of the work; second, a claim for $72,666.28, suSdivided as follows: (a) Damages for breach of contract in that there was eliminated a section of the construction work which was the subject of the contract, namely, the spur under Central Park from Seventh avenue and West Fifty-ninth street; (b) by requiring the contractor to use fourteen per cent more cement in making the concrete than was required by the specifications; (c) by requiring the plaintiff to underpin certain buildings'which were founded upon rock and to rebuild certain duct lines; the third item was for $82,134.07 for damages claimed because of false estimates of the quantities, nature and extent of the Work to be performed.
At the close of the whole case the following took place: Both parties moved for the direction of a verdict on the claim for the pumping of certain sewage under the second item of the first cause of action. The court directed a verdict in favor of the plaintiffs on this item for $9,850.75.
Likewise both parties moved for the direction of a verdict in connection with the claim for damages for the elimination of the spur under Central Park. The court directed a verdict in favor of the plaintiffs on this item for $16,813.65.
The plaintiffs moved for a directed verdict on the claim for excess cement required to be used in making concrete as claimed in item (b) above. The defendant asked to go to the jury on the question as to whether or not the contractor had complied with the specifications. The court granted the plaintiffs’ motion for the direction of a verdict in the sum of $5,578.19.
The plaintiffs moved for the direction of a verdict on the claim for damages because of alleged false estimates of quantities of [521] work to be done. As to this, the defendant asked to go to the jury on the question as to whether or not the contractor was in fact misled, and as to whether there were any damages suffered. The court, however, directed a verdict in favor of the plaintiffs for the sum of $40,296.05.
The total of the directed verdicts in favor of the plaintiffs amounted to $72,538.64.
There were then submitted to the jury issues arising in connection with retained percentages of money earned and damages for breach of contract by delay in furnishing plans. As to these, the jury returned a verdict of $89,876.59 on the first item, and on the second item, namely, damages for breach of contract for delay, the jury returned a verdict for $813,000, a total in all of $975,415.23.
A counterclaim interposed by the city, claiming liquidated damages of $159,684.85 for the contractor’s delay in completing the work on time and $87.56 for work which it is claimed the contractor failed to perform, or a total counterclaim of $159,772.41, was dismissed on the merits. Interest upon said verdict was assessed at $3,206.84 and the costs were taxed at $177.04 together with an additional allowance of $2,000, making a total of $980,799.11 for which judgment was rendered.
Taking up first the item of damages for the delay of the engineer of the Public Service Commission in furnishing plans, the question arises whether the city is liable for damages resulting from the negligence of the employees of the Public Service Commission as distinguished from liability for what can be said to be moneys due under the contract, and for extra work and materials ordered by the Public Service Commission and actually supplied by the contractor.
To the contention of the contractor that the city is also liable under such a contract for damages as distinguished from moneys due and extra work and materials furnished as aforesaid, the first answer is that this court is already committed to a contrary view. In Degnon Contracting Co. v. City of New York (202 App. Div. 390), where Mr. Justice Greenbaum wrote for a majority of the court, it was held that the city was not liable for the acts of the Public Service Commission in delaying the preparation of plans under a similar subway contract. Such holding Was upon the ground that the Public Service Commission, and not the city, was the body charged by law with the preparation of plans for the construction of subways. It Was further held that the Public Service Commission was not the agent, in a general sense, of the city of New York and that the city Was not responsible for damages arising out of the negligence of the Commission or its agents. For this proposition a number of authorities are cited. In each of the [522] cases cited the action was predicated upon negligence. Mr. Justice Greenbaum further took the position that negligence was the theory upon which the Degnon Contracting Co. case was predicated, stating: “ In the instant case the theory of the complaint is that the acts of the Commission or its chief engineer were careless, in that they delayed in giving certain plans to the plaintiffs. In other words, the real basis of the claim is the negligence of the engineer or his subordinates.”
While it is possible to distinguish the cases cited as authorities in Degnon Contracting Co. (supra) upon the ground that they may be said to have arisen in tort, rather than in contract, said decision itself squarely held that a failure of the Public Service Commission to furnish plans as provided by the contract (which is the identical act complained of in the case at bar) did not give rise to an action for damages against the city. Also it is to be noted that although the failure to furnish plans as required by the contract Was occasioned by negligence on the part of the engineer, such failure, nevertheless, constituted a breach of contract. At page 394, Mr. Justice Greenbaum said:
“ The contract in suit specifically provided as to detail drawings as follows: ‘ Section No. 36. The Engineer [referring to the engineer of the Public Service Commission] will prepare and furnish to the contractor, from time to time as required, drawings and plans amplifying such details of the contract drawings as may be necessary; and drawings and plans necessary to show the adjustment and reconstruction of all surface and sub-surface structures Wherever the reconstruction of the same is necessitated by the construction of the railroad. These plans must be strictly followed, unless local conditions should develop, during the construction, suggesting changes, when, with the approval of the engineer, such changes may be permitted.’
“ Under article 24 it is provided that the engineer ‘ shall determine all questions in relation to the works and the construction thereof and shall in all cases determine every question which may arise relative to fulfillment of this contract on the part of the contractor. His determination and estimate shall be final and conclusive upon the contractor, and in case any question shall arise between the parties hereto, touching this contract, such determination and estimate shall be a condition precedent to the right of the contractor to receive any money under this contract.’
“ It thus appears that the parties by express agreement have recognized that the engineer occupies a position over which the defendant has no control and that both the defendant and the plaintiff would in many instances be absolutely bound by the [523] decision which the engineer may make, assuming, of course, that it is not made as the result of fraud or of bad faith. It is difficult to understand upon what theory the city may be held liable for the acts of the engineer in delaying the delivery of plans to plaintiff who knew or was presumed to know the provision of the statute and the contract, which conferred the power upon the engineer to prepare plans and furnish them to the contractor.
“ It would seem to follow that it must have been understood by the parties that for any negligence or delay occasioned by the engineer in respect of a matter under his jurisdiction and over which the city had no control whatever, the city could not be held responsible."
While it might be contended that the above holding was dicta since the decision can be sustained upon another ground, yet so clearly Was the issue raised by the prevailing and dissenting opinions as to whether the city was liable for damages arising because of the failure of the engineer of the Public Service Commission to furnish plans in accordance with the provisions of the contract, that it must be held that this court is bound to follow such decision as authority. When the Degnon case was reviewed by the Court of Appeals (235 N. Y. 481), said court specifically refrained from passing upon the question of the liability of the city for damages under the contract in question, saying: “We agree with the Appellate Division that this plaintiff was not entitled to recover for the increased cost and expense of executing the contracts in question because of the failure of the engineer of the Public Service Commission to furnish plans as provided in the agreement. We hold this conclusion even though we assume, without deciding it, that the city was liable for damages caused by the neglect of an engineer in the employ and under the control of the Public Service Commission which had executed in its behalf the contract in question."
By what has just been said with reference to the Degnon Contracting Co. Case (supra) there is no disposition to question the correctness of its holding that the city of New York is not liable for damages based upon the negligence of the employees of the Public Service Commission in failing to carry out the provisions of the contract. The respondents claim that the city is in no different situation from that of any voluntary party to a contract who chooses its own agent to carry out its voluntary acts. The city, however, in these subway contracts, occupies a very different position. Just as municipal contracts differ from ordinary contracts, so do contracts such as in the case at bar, where the State seeks to impose upon the municipality certain obligations in connection [524] with work which affects the whole State, differ from contracts voluntarily and directly entered into by a municipality. No one will seriously dispute that rapid transit is a matter of public interest with which the people of the entire State are concerned. The Legislature of the State undertook- to provide means of adequate rapid transit and in formulating a plan in order to carry out the same, appointéd as officers of the State the Public Service Commission. That the agents so constituted are agents of the State independent of the municipal government in the performance of their designated duties has been repeatedly adjudicated. As was said by Mr. Justice Greenbaum in the Degnon Case (supra): “ It has been repeatedly held that the Rapid Transit Railroad Commissioners, as they Were formerly termed, or the Public Service Commissioners of the First District, as their successors at the time in question were called, and who have been since superseded by the Transit Commissioners, are not agents in a general sense of the city of New York, nor are any of their employees to be regarded as such agents. The Public Service Commission is a State body, independent of the municipal government. (People ex rel. New York Dock Co. v. Delaney, 192 App. Div. 734, 739.) ” The State, therefore, appointed its agent the Public Service Commission to carry out these contracts and in connection therewith placed certain obligations upon the city. In some instances, however, the action of the city in accepting the contracts involves a voluntary approval by the city. The city thus gives its approval to the cost of construction, the use of its streets and in a general way its consent to the general plan of construction and in certain other particulars; but many of the obligations of the city are involuntary and are placed upon it by the State; As was said by Mr. Justice Shearn in McGovern v. City of New York (185 App. Div. 609, 624), quoting from his opinion in People ex rel. Holbrook, Cabot & Rollins v. Mitchel (N. Y. L. J. Aug. 24, 1915): “ An analysis of the entire act and of each provision under which the board of estimate and apportionment is directed or authorized to take action concurrently with the Public Service Commission, or after the Commission has acted, will demonstrate that the sole function of the board of estimate and apportionment, with reference to construction contracts, is to provide funds to meet the cost of such construction, and that the board has no authority or jurisdiction whatever with regard to the terms and conditions of the contracts. A detailed analysis would too greatly extend this opinion, but it may be noted here that the act (section 6-1)