O'Brien v. . Mayor, Etc., of New York

35 N.E. 323, 139 N.Y. 543, 55 N.Y. St. Rep. 596, 94 Sickels 543, 1893 N.Y. LEXIS 1036
CourtNew York Court of Appeals
DecidedNovember 28, 1893
StatusPublished
Cited by32 cases

This text of 35 N.E. 323 (O'Brien v. . Mayor, Etc., of New York) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Brien v. . Mayor, Etc., of New York, 35 N.E. 323, 139 N.Y. 543, 55 N.Y. St. Rep. 596, 94 Sickels 543, 1893 N.Y. LEXIS 1036 (N.Y. 1893).

Opinion

Peckham, J.

For a number of years prior to 1883 the city of New York had experienced the discomforts of an inadequate supply of water.

The necessity in that year for at once entering upon some work of magnitude sufficient to insure a largely increased supply for the city became imminent and inexorable. The past growth of the municipality had been phenomenal, and provision was to be .made for water not only enough for present necessities, but also sufficient for a population which the coming years were reasonably certain to see congregated within the corporate limits. The expense of such an undertaking could, of course, be only approximately estimated, but it was certain to cost, in any event, many millions of dollars. It is obvious that the machinery provided for the administration of the ordinary affairs of the city would be insufficient and inappropriate for devising and adopting a plan and superintending the due execution of an undertaking such as would be required in order to insure to New York the water necessary fo'r'its present prosperity and future growth. It was necessary to resort to the legislature in order to procure the passage of a-statute, by virtue of which the powers appropriate for such a work might be called into requisition and a body created'fitted to discharge the functions, in some respects, of a governing and controlling tribunal, with regard both to the work itself and to the men by whom that work should be accomplished.

The legislature accordingly passed an act which is entitled “An act to provide new reservoirs, dams and a new aqueduct with the appurtenances thereto, for the purpose of supplying the city of New York with an increased supply of pure and wholesome water.” The act is known as chapter 490; of the Laws of 1883, and it contains an elaborate scheme for the accomplishment of the end in view.

The learned presiding justice who delivered the opinion of the Supreme Court in this case has made a careful synopsis, of *555 the material portions of the act, and I cannot do better than reproduce it here. It is as follows :

“ By the first section of this act the mayor, comptroller, commissioner of public works and three citizens were authorized, empowered and directed to carry out the provisions of the act in the manner thereinafter provided, and they were to be known as the aqueduct commissioners. By the second section it was provided that the commissioner of public works should, under the direction of the aqueduct commissioners, as soon as possible after the passage of the act, submit to them a plan or plans- for the construction of a new aqueduct of conduit for water, and for the construction of one or more dams or reservoirs to retain such water, and" for the construction of the appurtenances thereto. These plans the aqueduct commissioner's might adopt, modify or reject in whole or in part, and might cause such surveys to be made as they might deem expedient to enable them to act intelligently in the premises; and it was provided that in case of the rejection of any such plan or plans by the said aqueduct commissioners, the said commissioner of public works should, in like manner, prepare and submit another plan or plans, etc., which course should be continued until a plan or plans covering the entire work contemplated by the act should be approved by the aqueduct commissioners.
“The act then provided for the acquisition of the land necessary to carry out the work. And by the twenty-fifth section it was provided that the commissioner of public works should, from time to time, as might be necessary, prepare and submit to the aqueduct commissioners and to the counsel to the corporation forms of contract and specifications, and bonds for the faithful performance thereof, for the doing of the work and the furnishing of the materials required to be done and furnished by the said approved plan, or for the doing of such parts of such work and the furnishing of such parts of such materials as might from time to time be required for that purpose; which forms of contracts, specifications and bonds were to be approved by the aqueduct commissioners, and *556 approved as to.form by the counsel of the corporation ; and that the said aqueduct commissioners should have"the exclusive authority to determine what provisions should be embodied in said contract, in order, so far as.might be possible, to save the city from loss, embarrassment and litigation by reason of any work done or supplies furnished thereunder, which approval should be evidenced by their certificate indorsed thereon, signed by a majority of them; and .the approval of the counsel to the corporation was to be evidenced by his certificate to that effect, indorsed in like manner.
“ By section 26 it was provided that when the form of the contract with its specifications and the form of the bond for the faithful performance thereof should have been approved as above provided, the said commissioners should advertise for sealed bids or proposals for the doing of the work or the furnishing of the material called for in such approved form of contract; and after the receipt of such bids or proposals, by section 28 it was provided that they should be publicly opened by said aqueduct commissioners, who were empowered to accept that bid or proposal, the acceptance of which would, in their judgment, best secure the performance of the contract; or they might reject any and all such bids. Section 30 provided that the contracts when so awarded were to be executed in triplicate by the contractors on the one part and the aqueduct commissioners, acting for the city of New York, on the other part; and that the work and materials, called for by such contract should be done and furnished under the direction and supervision and subject to the inspection of said aqueduct commissioners, their engineer, supervisors and inspectors, but such direction, supervision and inspection might be intrusted to the engineers and other subordinates of the department of public works so far as said commissioners should so direct; but in no event should the city of New York be held in any action or proceeding brought or had under any contract so made to any other or greater liability than that expressed therein, nor be required to pay out or . otherwise dispose of any sum of money for the doing of such *557 work or the furnishing of such material greater than is stipulated in said contract) nor otherwise than in strict conformity to the terms thereof.
Section 33 provided that all work thereby authorized to be done and all materials to be furnished involving an expenditure of over §1,000 should be procured by contract made in the manner required by and pursuant to the provisions of the act. The said commissioners were, however, empowered without contract to cause such surveys to be made and such maps and plans prepared as should, in their opinion, be necessary to carry out the provisions of the act'; and might appoint and fix the compensation of suitable engineers and other persons to supervise and inspect all the work by said act authorized to be done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BOARD OF WATER & SEWER COM'RS v. Bill Harbert Const. Co.
870 So. 2d 699 (Supreme Court of Alabama, 2003)
Roy C. Knapp & Sons, Inc. v. County of Putnam
212 A.D.2d 770 (Appellate Division of the Supreme Court of New York, 1995)
Thomas Crimmins Contracting Co. v. City of New York
542 N.E.2d 1097 (New York Court of Appeals, 1989)
Thomas Crimmins Contracting Co. v. City of New York
138 A.D.2d 138 (Appellate Division of the Supreme Court of New York, 1988)
Joseph F. Egan, Inc. v. City of New York
18 A.D.2d 357 (Appellate Division of the Supreme Court of New York, 1963)
Claim of Schmidt v. Wolf Contracting Co.
269 A.D. 201 (Appellate Division of the Supreme Court of New York, 1945)
City of New York v. National Dredging Co.
254 A.D. 530 (Appellate Division of the Supreme Court of New York, 1938)
JA La Porte Corporation v. Mayor and City Council
13 F. Supp. 795 (D. Maryland, 1936)
Provo v. City of Syracuse
186 N.E. 417 (New York Court of Appeals, 1933)
Marshall Construction Co. v. State
133 Misc. 131 (New York State Court of Claims, 1928)
Litchfield Construction Co. v. City of New York
216 A.D. 517 (Appellate Division of the Supreme Court of New York, 1926)
James Stewart & Co. v. State
121 Misc. 827 (New York State Court of Claims, 1923)
People ex rel. New York Dock Co. v. Delaney
192 A.D. 734 (Appellate Division of the Supreme Court of New York, 1920)
S. Pearson & Son, Inc. v. State
112 Misc. 29 (New York State Court of Claims, 1920)
Rosenwasser v. Ogoglia
172 A.D. 107 (Appellate Division of the Supreme Court of New York, 1916)
L. F. Bannon Plumbing, Heating & Contracting Co. v. City of Kingston
166 A.D. 397 (Appellate Division of the Supreme Court of New York, 1915)
Emporia Concrete & Construction Co. v. Board of Commissioners
76 S.E. 14 (Supreme Court of North Carolina, 1912)
Peterson v. . City of New York
98 N.E. 501 (New York Court of Appeals, 1912)
Peterson v. City of New York
146 A.D. 879 (Appellate Division of the Supreme Court of New York, 1911)
Williams v. City of New York
130 A.D. 182 (Appellate Division of the Supreme Court of New York, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
35 N.E. 323, 139 N.Y. 543, 55 N.Y. St. Rep. 596, 94 Sickels 543, 1893 N.Y. LEXIS 1036, Counsel Stack Legal Research, https://law.counselstack.com/opinion/obrien-v-mayor-etc-of-new-york-ny-1893.