Williams v. City of New York

130 A.D. 182, 114 N.Y.S. 652, 1909 N.Y. App. Div. LEXIS 167
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJanuary 15, 1909
StatusPublished
Cited by4 cases

This text of 130 A.D. 182 (Williams v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams v. City of New York, 130 A.D. 182, 114 N.Y.S. 652, 1909 N.Y. App. Div. LEXIS 167 (N.Y. Ct. App. 1909).

Opinion

Ingraham, J.:

In the year 1901 the aqueduct commissioners, acting under the authority conferred upon them by chapter 490 of the Laws of 1883 (and acts amendatory thereto), in connection with the water supply of the city of New York, determined to construct a dam on the Croton river which was known as the Muscoot Dam.” They issued proposals for bids to do the work required by certain specifications which were annexed to the proposals for bids; the plaintiffs submitted a bid which was accepted, and a formal contract was executed on the 10th day of May, 1901. The contract in form is between The City of New York, acting by and through the Aqueduct Commissioners, by virtue of the power vested in them by Chapter 490 of the Laws of 1883, of the State of New York, and the amendments thereto, parties of the first part, and John Williams and Robert J. Gerstle, composing the firm of Williams & Gerstle, of 347 East 44th St., New York City, parties of the second part.” By the contract the plaintiffs agreed that they would commence the work within twenty days from the date of the contract; “ that the rate of progress of their work shall be such, in the opinion of . the engineer, and that they will so conduct the said work that on or before July 1, 1902, the whole work covered by this contract and specification shall be entirely completed,” with a penalty of $250 for each day that the contractors should be behind in the performance and completion of the work, and with a further provision that “ neither an extension of time for any reason beyond that fixed herein for the completion of the work, nor for the doing and acceptance of any part of the work called for by this contract, shall be deemed to be a waiver by the said aqueduct commissioners of the right to abrogate ■ this contract for ábandonment or delay, in the manner provided for in the .paragraph marked ‘ p ’ in this agreement.” Paragraph “ p ” of the contract provided that the contractors “ agree that if the work to be done under this agreement [184]*184shall be. abandoned, or if the conditions as to the rate of progress hereinbefore specified are not fulfilled, or if this contract shall be. assigned by the parties of the second part otherwise than as is herein-before specified, or if at any time the engineer shall be of opinion and shall so certify, in writing,, to the said aqueduct commissioners that the said work or any part thereof is unnecessarily or unreasonably 'delayed, or that the said contractor is violating any of the conditions or covenants of this contract, or executing said contract in bad faith, or if the work to, be done under this contract be hot fully and entirely completed within the time herein stipulated for its completion, the said aqueduct commissioners shall have the power to notify the aforesaid contractor to discontinue all work, Or any part thereof under his contract, by a written notice to be served upon the contractor either personally or by leaving said notice at his residence or with his agent in charge of the work; and thereupon- the said contractor shall discontinue said work, or such part thereof as sejfid aqueduct commissioners may designate, and the said aqueduct commissioners shall- thereupon have the power to place such and. so many persons, and obtain by purchase or hire such materials, * * * by contract or otherwise, as said aqueduct commissioners deem. necessary to complete the work herein described, * * * and the expense so charged shall be deducted and paid by the "parties of the first part out of such moneys as either may be due, or may at any time, thereafter become due to the said contractor under and by virtue of this agreement, or any part thereof.” And it was further agreed that “ if the work under this contract is not, in the opinion of the aqueduct commissioners, practically completed as hereinbefore provided (Clause L) on or before the first day of July, 190.2, that "one-half of the moneys retained by The City of Mew York under Clause T shall be and is hereby forfeited by the said parties of the second ■part to the said The City of Mew York, and the aqueduct commissioners shall have the. right to take possession of the work.” The contract "also contains the further provision that -in order to enable the said contractor to. prosecute the work, advantageously the engineer shall once a month make an estimate in writing of the amount of work done and materials delivered to be used in the work, and the value thereof, according to the terms of the contract; that the [185]*185' first such estimate shall be of the amount or quantity and value of the work done since the parties of the second part commenced the performance of this contract on their. part, and every subsequent estimate (except the final one) shall be of the amount or quantity and value of the work done since the last preceding estimate was made; that such estimates of amount and quantity shall not be required to be made by strict measurement or exactness, but they may at the option of said engineer be approximate only, and that upon each such estimate being made the parties of the first part will pay to the parties of the second "part ninety per cent of such estimated value.

The plaintiffs commenced work under this contract and proceeded thereunder until January, 1901. The work was not then completed, although according to the terms of the contract it was to have been completed on or before July 1, 1902, but the time for the completion of the work appears to have been extended from time 'to time by the aqueduct commissioners. On February 18, 1901, the engineers of the aqueduct commissioners certified that the contract between the city of Mew York, acting by and through the aqueduct commissioners, and John Williams and Robert J. Gerstle, dated May 10, 1901, for the building of the “Muscoot Dam” on the Croton river at Muscoot mountain and the work thereunder “is unnecessarily and unreasonably delayed, and the contractors are violating the conditions or covenants of the contract and executing the same in bad faith, and the work done under the contract is not fully and entirely completed within the time therein specified in the said contract for its completion; ” whereupon, and on February 29, 1901, the aqueduct commissioners served a notice on the plaintiffs .to discontinue all work under their contract, stating that the notice was served pursuant to the terms and conditions of the contract'and because of their failure to comply therewith; that the aqueduct commissioners would proceed to complete the work under the provisions of the contract, and to charge the cost thereof as therein provided, and take such other steps as might be legal and proper under the provisions of chapter 190- of the Laws of 1883 and the amendments thereto. Subsequently, and in May, 1901, the plaintiffs commenced this action, alleging the making of the contract; that" as soon as permitted the plaintiffs proceeded to [186]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rapid Transit Subway Construction Co. v. City of New York
129 Misc. 714 (New York Supreme Court, 1927)
Caldwell v. Board of Education
127 Misc. 492 (Appellate Terms of the Supreme Court of New York, 1926)
Gerber v. Kalmar, Puck & Abrahams Consolidated, Inc.
104 Misc. 85 (Appellate Terms of the Supreme Court of New York, 1918)
Cranford Co. v. City of New York
150 A.D. 195 (Appellate Division of the Supreme Court of New York, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
130 A.D. 182, 114 N.Y.S. 652, 1909 N.Y. App. Div. LEXIS 167, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-v-city-of-new-york-nyappdiv-1909.