Cranford Co. v. City of New York

150 A.D. 195, 134 N.Y.S. 839, 1912 N.Y. App. Div. LEXIS 7083

This text of 150 A.D. 195 (Cranford Co. v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cranford Co. v. City of New York, 150 A.D. 195, 134 N.Y.S. 839, 1912 N.Y. App. Div. LEXIS 7083 (N.Y. Ct. App. 1912).

Opinion

Scott, J.:

In February, 1907, the city of New York, by the board of water supply j entered into a contract with plaintiff for the sink[197]*197ing of two test or exploration shafts on either side of the Hudson river for the purpose of determining the elevation at which solid rock might be found, and the suitability of this rock for containing the Catskill aqueduct tunnel. The work to be done and the rate of payment for each item of work was specifically defined by the contract. Inasmuch as speed in completion was deemed to be of great importance, each bidder was requested to name in his proposal the speed which he was willing to guarantee, and a bonus of $400 per day was agreed to be paid to the contractor in case the work should be completed earlier than the bid time, and in case guaranteed progress was not made, $100 per day, not including the first twenty-five days, it was stipulated should be exacted as liquidated damages.

As to payments, the contract provided that the engineer should, from time to time, as .the work progressed, but not oftener than once in each month, make in writing an estimate of the work done and the materials furnished since the last preceding estimate, and that the city should pay to the contractor ninety-five per cent of each estimate, a final adjustment of accounts and a final estimate to be made when the work should be completed. No time was specified in the contract within which the city should pay the ninety-five per cent of each monthly estimate after the same should have been made and signed by the engineer.

The plaintiff entered upon the performance of the contract and received seven monthly estimates from the engineer, the first being dated May 18, 1907, and the last November 13,1907. In each month the engineer made and signed the estimate within a few days after the tenth of the month, and no complaint is made of any delay on this score. The estimates for May and June were paid on September 17, 1907, and those for July and August were paid on September 26, 1907. The evidence recalls the fact, which has passed into history, that the autumn of 1907 was a period of severe financial stringency, when money was scarce and difficult to be had even by the most solvent, and it is, perhaps* for this reason that the city was dilatory in paying the September, October and November estimates. At all events it had not paid them by December 4, 1907, on which date plaintiff, by letter, notified the board of water supply that [198]*198unless the three last-mentioned estimates, aggregating about $25,000, were paid within three days from date, that is to say on or before December 7, 1907, it would discontinue the work. The amount of the estimates was not paid within the time specified, and on December 9, 1907, plaintiff did discontinue work, and so notified the board of water supply on December twelfth.

It appears in evidence that plaintiff had made serious mistakes in estimating upon the work to be done, and the rate of progress which it could make, so that, as was testified by one of its officers, they were glad to get out of the contract.

The plaintiff now sues, as upon a quantum, meruit, for the fair value of all the work done by it, including the cost of its plant, less the sums which it was paid, at contract rates, under the first four monthly estimates. In consequence of its erroneous estimate of the cost of doing the work, it now claims upwards of $200,000, • although the unpaid estimates barely exceeded $25,000.

The theory of the action is that the defendant committed a breach of the contract in having failed to promptly pay the September, October and November estimates; that this breach justified the plaintiff in rescinding the contract, and that having so rescinded it for just cause, it is entitled to recover the . fair value of the work performed and the cost of plant, without regard to the contract prices.

There is ample- authority for the proposition that the failure of one party to a contract to pay an installment when due, is such a breach of the contract as will absolve the other party from all obligations to perform on his part while the default continues. (Wharton & Co. v. Winch, 140 N. Y. 287, 293.) The first question to be considered, therefore, is whether there was such a breach by the city in the present case. As has already been said the contract does not provide within what time after a monthly estimate has been made the city must pay the ninety-five per cent thereof. The obligation, therefore, is to pay it within a reasonable time. What constitutes a reasonable time under a city contract has been the subject of consideration on more than one occasion. In Jones v. City of New York (47 App. Div. 39) this court said: What would be inex[199]*199cusable or unreasonable delay, however, on the part of an individual or a partnership, or even a business corporation, might not be such in the case of a municipal corporation, with its complete system operated through independent official agencies. The contractor who deals with such a public corporation should not look for the same promptitude of payment as though he were dealing with private, parties. He must expect occasional delay and inconvenience as the natural result of the necessary formalities prescribed by law, and also from unforeseen contingencies such as the exhaustion of the fund applicable to the' work.” In Williams v. City of New York (130 App. Div. 182), which arose under a contract executed by the board of aqueduct commissioners, the plaintiffs claimed a breach of the contract by the city in consequence of its neglect to promptly pay a monthly estimate. The estimate had been made on January 12, 1904, but at that time a lien against the contractor was on file in the comptroller’s office, which was not removed until February 8, 1904. On February twenty-fourth the contractor served notice of rescission of the contract. “The defendant had a reasonable time within which to pay to the plaintiffs the amount due, and a mere delay in payment for a reasonable time to enable it to make the necessary arrangements for that purpose was not upon any possible construction of the contract a breach thereof. The comptroller of the city of New York cannot be expected to have the money ready or warrants drawn for the payment of claims against the city immediately upon presentation. The fiscal officer of a large municipal corporation is entitled to a reasonable time after the claim is presented to make • payments. There is nothing to show that the liability of the city to pay this amount was ever repudiated by the comptroller; there was a simple delay in making the payments. The necessity of time to make payment is recognized by the charter, which requires a claim to be presented for payment to the comptroller "of the city of New York, and that he has neglected to pay it for thirty days before an action can be maintained upon it against the city. (Greater N. Y. Charter [Laws of 1901, chap. 466], § 261, as since amd. by Laws of 1906, chap. 550, and Laws of 1907, chap. 677.) This is to give the comptroller [200]*200the necessary time to make the proper investigation and provide for the payment of the claim, and the charter fixes thirty days as a reasonable time for that purpose.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

William Wharton, Jr., & Co. v. Winch
35 N.E. 589 (New York Court of Appeals, 1893)
Nason Manufacturing Co. v. Stephens
28 N.E. 411 (New York Court of Appeals, 1891)
Jones v. City of New York
47 A.D. 39 (Appellate Division of the Supreme Court of New York, 1900)
Williams v. City of New York
130 A.D. 182 (Appellate Division of the Supreme Court of New York, 1909)
Koon v. Greenman
7 Wend. 121 (New York Supreme Court, 1831)
Galloway v. Barr
12 Ohio St. 354 (Ohio Supreme Court, 1843)

Cite This Page — Counsel Stack

Bluebook (online)
150 A.D. 195, 134 N.Y.S. 839, 1912 N.Y. App. Div. LEXIS 7083, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cranford-co-v-city-of-new-york-nyappdiv-1912.