ANTRIM LUMBER COMPANY v. Bowline

1969 OK 161, 460 P.2d 914
CourtSupreme Court of Oklahoma
DecidedOctober 14, 1969
Docket41677
StatusPublished
Cited by6 cases

This text of 1969 OK 161 (ANTRIM LUMBER COMPANY v. Bowline) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ANTRIM LUMBER COMPANY v. Bowline, 1969 OK 161, 460 P.2d 914 (Okla. 1969).

Opinion

LAVENDER, Justice.

This appeal involves judgments recovered by the defendant in error, Ray Bowline, doing business as Bowline Construction Company (hereinafter called the plaintiff), in an action for judgment for the balance claimed to be due him as the contractor under a construction contract, and to have the same declared to, and foreclosed as, a valid mechanic’s and material-man’s lien, and for judgment on a bond for attorney fee, interest and court costs.

His action arose out of a written contract (hereinafter called the “base contract”) that was entered into, as of August 1, 1962, *916 between the plaintiff and Antrim Lumber Company, a corporation, for the construction, by the plaintiff, of a two-cell sanitary sewage lagoon and an outfall sewer line connecting the lagoon to the sanitary sewage gathering lines within a platted area then being developed by the lumber company, and two supplemental oral agreements between the same parties under which the plaintiff constructed one section of a storm sewer to serve the platted area and one section of a sanitary sewage gathering line to serve a portion of the platted area.

The plaintiff in error, Insurance Company of North America, was named as a defendant in the district court only because it is the surety on a bond for the payment of any reasonable attorney’s fee and all court costs and interest that might be adjudged against the lumber company, filed by the lumber company in connection with a cash deposit with the court clerk to secure the discharge, as provided in 42 O.S.1961 § 147, of the property in the platted .area from a lien claimed by the plaintiff for the payment of an amount which the plaintiff claimed was unpaid under those contracts. Unless otherwise indicated, the term “defendant,” when used in the singular, will refer only to Antrim Lumber Company.

The base contract between the defendant, as “Owner,” and the plaintiff, as “Contractor,” provides, in paragraph numbered “1” thereof, that the contractor agrees to furnish all labor and materials necessary to construct, and to construct, the sanitary sewer lateral lines serving the described “addition” from the southwest corner of said addition to the lagoon site, and the lagoon, and that “All such construction shall conform to the plans previously approved by the Oklahoma State Health Department, relating to the aforedescribed property, and all construction shall conform to the standard specifications adopted by the City of Tulsa for the construction of sanitary sewers.”

The base contract also provides, in paragraph numbered “2” thereof:

“The estimated quantities of work to be performed and the unit price to be paid to Contractor for each item of work are as follows:
“Excavation Rock 600 cu. yds. at $5.00 $3,000.00
“Excavation Dirt 1,251 cu. yds. at 1.50 1,867.50
“Lagoon Exc. and Embankment (earth only) 16,000 cu. yds. at 0.20 3,200.00
“ * * * *****
“Total $22,783.00
“The above quantities are estimated only and Contractor shall be paid on the basis of actual quantities of work performed. The parties hereby designate Shibley-Lane Engineering Co. as agent of each of the parties for the purpose of determining actual quantities of work performed pursuant to the contract. The actual quantities shall be measured by the Engineer during the performance of the work and his determination of quantities shall be binding on both parties hereto. * * * »

During the progress of the work on the lagoon and outfall-sewer project and prior to approval of that project by the State Health Department and the acceptance of that project by the defendant, the work on the gathering-line project and storm sewer project was completed and separate estimates covering the work on each of those projects, as well as three “partial” estimates of work done on the lagoon and *917 outfall-sewer project, all prepared and signed by the project engineer, A. E. Lane, and all providing for retainage of ten per cent of the amount shown thereon, were submitted to the plaintiff and were endorsed “approved” by him, and, after being okehed by Charles Pratt (who, according to the testimony of a vice president of the defendant, was the agent of the defendant concerning the development of the subdivision served by these projects as well as concerning the work on these projects), were paid by the defendant. After approval of the project by the State Health Department, a “final” estimate, prepared by the project engineer and purporting to reflect all of the work done on the lagoon and outfall-sewer project, all payments theretofore made thereon, the amounts retained on all three projects, and the amount due the plaintiff on all three of the projects ($13,433.38), was submitted to the plaintiff for his approval, but he refused to endorse his approval thereon and filed a statement of lien claimed against the property being developed as a subdivision and served by the project, in the principal amount of $23,291.74.

Attached to the lien statement as an exhibit thereto was an itemized statement (which treats the items concerning the gathering-line and storm-sewer projects as “extras”), showing the number of units of various “items” of labor and materials which the plaintiff claimed to have furnished on the lagoon and outfall-sewer project, on the gathering-line project, and on the storm-sewer project, and as “extras” in connection with the outfall-sewer project itself, the price claimed by him for each unit, the resulting amount claimed by him for each such “item,” and the total amount claimed to have been earned by him as to each group of “items” (lagoon and outfall-sewer project $45,266.70, gathering-line project $1,073.93 storm-sewer project $4,226.25, and $4,917.40 as “extras” in connection with the lagoon and outfall-sewer project), for a gross amount of $55,424.03, and also showing payments on the lagoon and outfall-sewer project in the sum of $26,362.64 (which is the sum of the payments shown on the project engineer’s “final” estimate with respect to that project, and showing that the plaintiff claimed to be unpaid $513.41 retained by the defendant on the gathering-line and storm-sewer projects (the same amount shown therefor on the project engineer’s “final” estimate, $3,874.27 for unpaid items claimed by him on the gathering-line and storm-sewer projects and as “extras” in connection with the lagoon and outfall-sewer project, as well as an unpaid balance of $18,904.06 on the lagoon and outfall-sewer project, and a total of $23,291.74 claimed to be due him from the defendant.

That Itemized statement also shows (on the same lines with the number of units of each item and the prices and extensions thereof, as claimed by the plaintiff) the number of units of each item, the unit prices and extensions thereof, which the plaintiff contended had been approved by the project engineer for payment, and the differences, if any, between the number of units, unit prices and extensions thereof, as claimed by the plaintiff and as approved by the project engineer for payment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PUMMILL v. HANCOCK EXPLORATION LLC
419 P.3d 1268 (Court of Civil Appeals of Oklahoma, 2018)
Morgan v. Galilean Health Enterprises, Inc.
1998 OK 130 (Supreme Court of Oklahoma, 1998)
Cook v. Oklahoma Board of Public Affairs
1987 OK 22 (Supreme Court of Oklahoma, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
1969 OK 161, 460 P.2d 914, Counsel Stack Legal Research, https://law.counselstack.com/opinion/antrim-lumber-company-v-bowline-okla-1969.