Lewis v. Chicago, S. F. & C. Ry. Co.

49 F. 708, 1891 U.S. App. LEXIS 1656
CourtU.S. Circuit Court for the District of Eastern Missouri
DecidedDecember 7, 1891
StatusPublished
Cited by16 cases

This text of 49 F. 708 (Lewis v. Chicago, S. F. & C. Ry. Co.) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Eastern Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lewis v. Chicago, S. F. & C. Ry. Co., 49 F. 708, 1891 U.S. App. LEXIS 1656 (circtedmo 1891).

Opinion

Thayer, District Judge,

(after stating the facts as above.) For the information of counsel the court states the conclusions it has reached concerning the various questions of law and fact that have arisen in this case as follows:

First. The second clause in the contract, declaring that the engineer’s measurements and calculations of the quantity and amount of the several kinds of work, and also that his classification of the material contained in excavations, shall be “final and conclusive,” is a valid provision, and is binding upon the parties to the agreement. Therefore there can be no recovery in excess of the engineer’s final estimate, unless such estimate is successfully assailed lor fraud, gross errors, or mistake. Railroad Co. v. March, 114 U. S. 549, 5 Sup. Ct. Rep. 1035; Wood v. Railroad Co., 39 Fed. Rep. 52, and citations; Sweet v. Morrison, 116 N. Y. 19, 22 N. E. Rep. 276; Brush v. Fisher, 70 Mich. 469, 38 N. W. Rep. 446.

[710]*710’Second. The estimate may be impeached .for fraud; that is to say. it may be shown that the engineers in charge intentionally underestimated or overestimated the work. It may also be impeached by proof of gross errors in the measurements and calculations. If the evidence shows such errors, it either creates the presumption of fraud, or warrants the conclusion that the engineers did not exercise that degree of care, skill, and good faith in the discharge of their duty which the law exacts; and in either event the court wall disregard the estimate so far as is necessary to do substantial justice. The meaning of the word “mistake,” as above employed, must be carefully defined.

(а) The court will relieve against mistakes in measurements and calculations that are apparent on the face'of the estimate, or that' are clearly proven, though not so apparent.

(б) If it is satisfactorily shown that the engineers failed, through oversight, to measure or estimate any particular part of the work, the court wall grant relief as to such mistakes.

■ (c) If it appears that the engineer in charge put a wrong construction on any provision of the contract, the court will correct any substantial errors resulting from such mistake, for the reason that the parties did not make the decision of the engineer as to the proper interpretation of the contract final,and conclusive. It is the province of the court to construe the agreement. Bridge Co. v. City of St. Louis, 43 Fed. Rep. 768.

(d) But in determining the kind of material found in the several cuts, the engineers were called upon to exercise their judgment. That was a matter, as the contract in substance recites, which involved the exercise of special skill and attention as the work progressed, and for that reason-the parties selected an umpire, by wrhose judgment they agreed to be bound. Ranger v. Railway Co., 1 Eng. Ry. Cas. 1; 13 Sim. 368. The court will not undertake to revise the decision of the engineer on questions of that character if it appears that he acted in good faith. The utmost it can do is to correct errors of classification that may have resulted from an erroneous interpretation of the contract.

(e) Slight discrepancies in measurements made by the respective parties must also be disregarded; and even when there are discrepancies of some magnitude the court must accept measurements made by the engineers of the railway company, unless the proof clearly shows that they are erroneous. The presumption is that all measurements made by such engineers are correct, and the burden is on the plaintiffs to overcome that presumption. Torrance v. Amsden, 3 McLean, 509; Bumpass v. Webb, 4 Port. (Ala.) 65; Pleasants v. Ross, 1 Wash. (Va.) 156.

Third. After an attentive consideration of the question, the court concludes that the engineers put a wrong construction on the second clause of the specifications, in so far as they construed the “plowing test ” to be applicable to shale, soapstone, cemented gravel, and hardpan, as well as to other hard, earthy substances. The right interpretation of the clause is as follows: Shale, soapstone, cemented gravel, and hardpan were known substances, and were known to be hard to handle. Therefore it was declared that they should be classified as loose rock. And, inas[711]*711much as it was thought probable or possible that other hard earths might be encountered in the progress of tlie woik, it was agreed that any other material requiring the use of pick and bar, or that could not be plowed “with a strong, ten-ineh grading plow, * * * behind a good six horse or mule team,” should likewise be classified as loose rock. This is the correct exposition, and truly expresses the thought in the mind of the draughtsman.

But the court is of the opinion that the practice pursued by the engineers of estimating loose rock by percentages was justifiable and proper. Under all the circumstances of tlie case, that seems to have been the only fair and practicable method of classifying much of the material when the plowing test was applied. The evidence satisfies me that the material handled varied much in consistency and hardness, and lay in irregular strata. By far the largest portion of all the material found in the various cuts, except the rock cuts, was broken up, I think, by the use of a team of not more than six horses. Probably that was the most practicable and economical method of working the cuts, as an eight-horse team is usually cumbersome. Nevertheless, if the engineers had classified every cubic yard of earth that was so broken up with six horses “'as earth excavation,” it would not have accorded with the spirit of the contract. The application of that rule to the work of those contractors who had much hard material to handle, and very little easy plowing, would have been manifestly unjust. On the other hand, it would have been contrary to the spirit of the agreement, and equally unfair to the railway company, io have classified all of such material as loose rock. In short, the contract must he interpreted in a reasonable manner, with a due regard for the rights of both parties, and with a proper appreciation of tlie nature and magnitude of the undertaking, and the difficulties encountered in applying the plowing test to the subject-matter. In the light of such considerations as these, the specifications will not admit of the construction that it was tlie duty of the engineers to draw a rigid line, under all circumstances, between earth and loose rock, and to classify a given material as all loose rock, unless a six-horse team was able to plow therein continuously, from day to day, and to turn a full ten-inch furrow. As the contract did not define what should be esteemed plowing, or describe to what extent it should be impossible to plow with six horses, to entitle the contractor to loose rock classification, there was a grave difficulty in applying the force test to much of the material, and upon the whole I am satisfied that the engineers properly solved that difficulty in accordance with the spirit of the agreement by allowing a given percentage of loose rock, basing the percentage upon their observation of bow the material was handled, and the difficulties actually encountered in moving it. This conclusion is fortified by the fact that these plaintiffs did not object to the method of classification by percentages while the work was in progress.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wunderlich v. United States
117 Ct. Cl. 92 (Court of Claims, 1950)
State Highway Department v. MacDougald Construction Co.
6 S.E.2d 570 (Supreme Court of Georgia, 1939)
Mayer v. East Side Logging Co.
280 P. 343 (Oregon Supreme Court, 1929)
Clifton, Applegate & Toole v. Big Lake Drain District No. 1
267 P. 207 (Montana Supreme Court, 1928)
Baker v. Multnomah County
246 P. 352 (Oregon Supreme Court, 1926)
Dock Contractor Co. v. City of New York
296 F. 377 (Second Circuit, 1924)
McGillivray Construction Co. v. Hoskins
202 P. 677 (California Court of Appeal, 1921)
Sweeney v. Jackson County
178 P. 365 (Oregon Supreme Court, 1919)
Indianapolis Northern Traction Co. v. Brennan
87 N.E. 215 (Indiana Supreme Court, 1909)
City of Atchison v. Rackliffe
96 P. 477 (Supreme Court of Kansas, 1908)
Fruin-Bambrick Const. Co. v. Ft. Smith & W. R. Co.
140 F. 465 (U.S. Circuit Court for the District of Western Arkansas, 1905)
United States v. Bonness
125 F. 485 (Eighth Circuit, 1903)
United States ex rel. Hudson River Stone Supply Co. v. Venable Const. Co.
124 F. 267 (U.S. Circuit Court for the Northern District of Georgia, 1903)
Elliott v. Missouri, K. & T. Ry. Co.
74 F. 707 (Eighth Circuit, 1896)
Mundy v. Louisville & N. R.
67 F. 633 (Sixth Circuit, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
49 F. 708, 1891 U.S. App. LEXIS 1656, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lewis-v-chicago-s-f-c-ry-co-circtedmo-1891.