McGillivray Construction Co. v. Hoskins

202 P. 677, 54 Cal. App. 636, 1921 Cal. App. LEXIS 502
CourtCalifornia Court of Appeal
DecidedOctober 24, 1921
DocketCiv. No. 2299.
StatusPublished
Cited by4 cases

This text of 202 P. 677 (McGillivray Construction Co. v. Hoskins) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McGillivray Construction Co. v. Hoskins, 202 P. 677, 54 Cal. App. 636, 1921 Cal. App. LEXIS 502 (Cal. Ct. App. 1921).

Opinion

FINCH, P. J.

This appeal is from a judgment directing the issuance of a writ of mandate requiring the defendant to make a true and correct final estimate of excavations made by the plaintiff under a contract for the construction of a concrete highway for Stanislaus County.

[1] Appellant assigns as error that the court failed to file findings of fact and conclusions of law. The appeal is taken upon the judgment-roll alone and therefore, in support of the judgment, it is presumed that findings were *638 waived. (Mulcahy v. Glazier, 51 Cal. 627; Baker v. Baker, 139 Cal. 626 [73 Pac. 469]; Ladd v. Myers, 4 Cal. App. 352 [87 Pac. 1110]; Hutton v. Newhouse, 41 Cal. App. 689 [183 Pac. 276].)

[2] It is contended that the complaint is insufficient in that it does not allege that prior to the commencement of the action a demand was made upon the defendant to make the required estimate. The complaint alleges that the defendant refused to include in his estimate the work upon which the action is based. The answer denies that the plaintiff was entitled to have such work so included and this appeal is founded on the same contention. Under such circumstances a demand would have been futile and this court would not be justified in holding that there has been a miscarriage of justice because of failure to make a futile demand. (Moreing v. Shields, 28 Cal. App. 513 [152 Pac. 964]; Moore v. Superior Court, 20 Cal. App. 299 [128 Pac. 946]; Chicago, K. W. R. Co. v. Chase County Commrs., 49 Kan. 399 [30 Pac. 456]; Gamble v. First Judicial Dist. Court, 27 Nev. 233 [74 Pac. 530]; State v. Pacific Brewing & M. Co., 21 Wash. 451 [47 L. R. A. 208, 58 Pac. 584] ; State v. Baushausen, 49 Neb. 558 [68 N. W. 950]; City of Austin v. Cahill, 99 Tex. 172 [88 S. W. 542, 89 S. W. 552].)

The contract provides, in so far as pertinent to the issues tried, that plaintiff shall be paid for the work as follows:

“Proposition ‘B.’ Approximately 7.483 miles of portland cement concrete road not including the grading for a lump sum of $66,935.
“Proposition ‘C. ’ All excavation of every description without classification including all incidental work for the unit price of 60c per cubic yard.”

Among the specifications, under the head “Grading,” are the following:

“ (a) Grading shall include the removing of all material, filling, re-filling, trimming and shaping, or such other work as may be necessary to bring the surface of the roadway to conform with the adopted sub-grade and cross-section.
“(b) All brush, roots, trees or vegetation lying between the gutters must be grubbed out and removed as directed by the county engineer.
*639 “(d) All soft and unsuitable material shall be removed and the space refilled with suitable material.
“(e) Ditches shall be excavated by the contractor in such places and of such dimensions as the engineer may direct, and he shall be paid for such work at the contract price for excavation.
“(f) The entire roadway shall be ploughed or broken up as directed by the engineer to secure a bond between new and old material.
‘1 (i) Computation of quantities shall be made by the method of average end areas and all measurements of work to be paid for shall be made in excavation.
“ (j) The contract price per cubic yard of excavation shall include the excavation, loading, transportation, and deposit of material in accordance with these specifications, and also all grubbing and clearing, ditching and all other work incidental to the grading.
“ (o) "Wherever oil is encountered during the grading, all lumps must be neatly piled by the side of the right-of-way and must not be placed in the grade.”

The complaint alleges that “oil was encountered and excavated below the finished subgrade in a considerable portion of the roadway for said highway, and the excavating done by applicant in the removal of said oil, and necessary in order to remove the same, amounted to 28,204.6 cubic yards. . . . that all of the work under said contract was completed by the applicant on March 20, 1918, and said work was done to the satisfaction of said Hoskins.”

The judgment recites that under and by the terms of the contract “petitioner was required to excavate and remove oil cake encountered below the subgrade” to the amount of 10,319 cubic yards and “was entitled to be paid therefor at the rate of 60c per cubic yard.”

[3] Appellant contends that “the removal of the oil cakes was work incidental to the grading,” and that therefore the plaintiff is entitled to no compensation for the excavation necessary to its removal. It is not claimed that such work was unnecessary in the preparation of a proper subgrade on which to lay the concrete. Proposition “B” provides for the payment of a lump sum for the construction of the “concrete road not including the grading.” The implication necessarily follows that compensation is to be *640 received for the grading. Proposition “C” provides the measure of such compensation, sixty cents per cubic yard for “all excavation of every description without classification including all incidental work.” No language could be clearer. It does not appear why excavations below the sub grade are any more incidental to the grading than those above.

[4] It is next argued that since the specifications provide specially for payment to the contractor at the agreed price per yard for excavating ditches “the idea that payment was to be made for any of the other incidentals mentioned under the heading of ‘grading’ ” is thereby excluded under “the rule expressio u-nius est exclusio alterkis.” The specifications, however, do not purport to fix the compensation to be received and the reference therein to payment for excavating ditches cannot reasonably be held to limit the express provision of the contract that payment shall be made for “all excavation of every description.” It is more probable that the provision was inserted in the specifications to guard against any controversy as to whether the term “excavation” included the construction of ditches.

[5]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Terminal Const. Corp. v. Bergen, Etc., Authority
112 A.2d 762 (New Jersey Superior Court App Division, 1954)
State Highway Department v. MacDougald Construction Co.
6 S.E.2d 570 (Supreme Court of Georgia, 1939)
State Ex Rel. Malott v. Cascade County
22 P.2d 811 (Montana Supreme Court, 1933)
Bates v. Hoskins
202 P. 679 (California Court of Appeal, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
202 P. 677, 54 Cal. App. 636, 1921 Cal. App. LEXIS 502, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcgillivray-construction-co-v-hoskins-calctapp-1921.