Gammino v. Inhabitants of Dedham

164 F. 593, 90 C.C.A. 465, 1908 U.S. App. LEXIS 4658
CourtCourt of Appeals for the First Circuit
DecidedOctober 22, 1908
DocketNo. 751
StatusPublished
Cited by11 cases

This text of 164 F. 593 (Gammino v. Inhabitants of Dedham) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gammino v. Inhabitants of Dedham, 164 F. 593, 90 C.C.A. 465, 1908 U.S. App. LEXIS 4658 (1st Cir. 1908).

Opinion

BROWN, District Judge.

This is a writ of error for review of the rulings o.f the Circuit Court in an action of contract, in which a verdict was directed for the defendant town.

By the written contract between the town, by its commissioners, and the contractor, Gammino, it was agreed that the contractor should furnish all material and perform all labor required upon two sections, A and D, of a sewer.

The location, extent, and general character of the trenching and other work tp be done was shown upon plans attached to the contract. Approximate quantities of work to be done were set forth in the specifications, including, among other things, earth excavation and rock excavation at various depths. The contractor was to be paid different sums per cubic yard for earth and rock excavation, and different sums for excavation at different depths. Following the detailed- statement of approximate quantities was this language;

“The above quantities are not guaranteed, and the commissioners reserve the right to increase or diminish the same within 25 per cent. Upon the quantities above given bids will be compared. These quantities will be a part of any contract made for the prosecution of this work, and when referred to in such contract include each and every part of the same.”

We are of- the opinion that, upon a construction of the contract which gives due effect to this provision, the prices named are to prevail only to the extent of the quantities named, with a 25 per cent, margin of variation. The contract fails to fix a price for quantities in excess of this.

The amount of rock excavation necessary to complete the trenches was much more than 25 per cent, in excess of the approximate quantities. The brief of the plaintiff in error states that in section A the rock removed was 18 times the amount of the estimated rock, and in section D 43 times.

[595]*595It clearly appears from the contract that the work contemplated was the entire trenching and construction work of sections A and D. Therefore it cannot be said that an excess of rock excavation over that mentioned in the estimates was extra work, which required special orders from the engineer. It was work in excess of that for which prices were agreed upon, but not work in excess of wdiat was required for the completion of the sewer sections.

Looking at the contract with due regard to its principal object, as well as to the specific provisions, it seems reasonable to hold that it was the intention of the'parties, in case the quantities exceeded the estimates by more than 25 per cent., that the contractor might claim on quantum meruit for the excess, and might show that for this excess he was fairly entitled to more than the contract price. On the other hand, the town would he allowed to maintain that on quantum meruit for the excess the contractor was entitled to less than the contract prices.

The limitation to a 25 per cent, vaiiation was inserted for a purpose. Except for this provision, the prices named would prevail for all the work done, even if it should turn out that the actual proportions of earth and rock excavation were substantially different from what was contemplated. An attempt to hold the contractor strictly to the prices named for an 'amount of work substantially, different from what was contemplated might result in hardship so great as to show mutual mistake concerning the subject-matter of the contract, and thus endanger the entire contract.

A more reasonable view is that both parties expected that the proportions of earth and rock excavation would be substantially as set forth, but provided for a variation of 2f> per cent, and agreed on prices accordingly, leaving the matter of further possible variations to be adjusted upon the principles of quantum meruit. A clause of this character, read as a provision for future contingencies, should be regarded as inserted for the benefit of both parties.

We are of the opinion that there was error in confining the plaintiff to the prices named for the excess of rock excavation over and above that stated in the estimates of quantities plus 25 per cent.

The auditor found that the sum total of earth and rock excavation did not exceed by 25 per cent, the sum total of the number of cubic yards stated in the estimate for earth and rock excavation, and therefore that the prices named in the contract applied to all rock excavation. Counsel for defendant in error contends that this is in accordance with the proper construction of the contract.

We are of the opinion that this is erroneous, and that it not only violates the terms of the contract, but leads to an unreasonable result.

The different portions of the work are distributed into different classes or quantities because of differences in kind and of cost. These “quantities” embrace such different classes, as pipes of different sizes, figured by linear foot, manholes, larnpshafts, chimneys, concrete, foundations, timber cradles, etc., as well as earth and rock excavation.

It is manifest that the 25 per cent, was not intended to be figured upon the sum of all the quantities, because it is impossible to add [596]*596together linear feet of pipe, number of manholes and lampshafts, and cubic yards of earth and rock excavation.

The defendant’s contention that the right reserved to increase.or diminish the quantities within 25 per cent, applied to the quantities as a whole is unreasonable, because the parts or units are incapable of addition. An attempt to figure 25 per cent, of the sum of 10 pounds, 10 linear feet, and 10 cubic feet would present the same difficulty.

Nor did the auditor in fact follow the principle which he adopted; i. e., that the right to vary by 25 per cent, applied to the quantities as a whole. On the contrary, he picked' out but two of the quantities, the earth excavation and the rock excavation, and, while he arrived at a sum that could be expressed in cubic yards, the result has no reasonable significance, and involves the fallacious assumption that in the minds of the contracting parties a cubic yard is a cubic yard, whether it is earth, worth from 30 cents to $3 per yard to excavate, or rock, worth from $2 to $7 per yard to excavate.

When the contractor says, “In order to complete the trench I was obliged to excavate several hundred cubic yards of rock more than was estimated,” it is no reply to say, “But you were relieved from excavating a corresponding number of cubic yards of earth.” The number of yards may balance, but the labor and cost, which* .are the material things, do not balance.

In connection with the claim of the contractor for rock excavation in excess of the estimated quantity plus 25 per cent., we have to consider the clauses of the contract which provide for a forfeiture by the contractor of the sum of $10 per day for failure to complete the work within the specified time.

We are of the opinion 'that, upon a proper construction of the whole contract, the forfeiture or penalty does not apply to the period of delay caused to the contractor by rock excavation necessary for the completion of the trench, but in excess of the amount named in the “quantities” plus 25 per cent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J. D'Amico, Inc. v. Town of Saugus
401 N.E.2d 884 (Massachusetts Appeals Court, 1980)
Eickhof Construction Company v. City of Grafton
123 N.W.2d 580 (North Dakota Supreme Court, 1963)
Kyburz v. State
108 N.W.2d 645 (South Dakota Supreme Court, 1961)
Blair v. United States Ex Rel. Gregory-Hogan
147 F.2d 840 (Eighth Circuit, 1945)
Wunderlich v. National Surety Corp.
24 F. Supp. 640 (D. Minnesota, 1938)
Rae v. Luzerne County
58 F.2d 829 (M.D. Pennsylvania, 1932)
Rajotte-Winters, Inc. v. Whitney Co.
2 F.2d 801 (Ninth Circuit, 1924)
Dock Contractor Co. v. City of New York
296 F. 377 (Second Circuit, 1924)
McGillivray Construction Co. v. Hoskins
202 P. 677 (California Court of Appeal, 1921)
Tribble v. Yakima Valley Transportation Co.
171 P. 544 (Washington Supreme Court, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
164 F. 593, 90 C.C.A. 465, 1908 U.S. App. LEXIS 4658, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gammino-v-inhabitants-of-dedham-ca1-1908.