United States ex rel. Hudson River Stone Supply Co. v. Venable Const. Co.

124 F. 267, 1903 U.S. App. LEXIS 4983
CourtU.S. Circuit Court for the Northern District of Georgia
DecidedJune 8, 1903
DocketNo. 1,488
StatusPublished
Cited by6 cases

This text of 124 F. 267 (United States ex rel. Hudson River Stone Supply Co. v. Venable Const. Co.) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the Northern District of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Hudson River Stone Supply Co. v. Venable Const. Co., 124 F. 267, 1903 U.S. App. LEXIS 4983 (circtndga 1903).

Opinion

NEWMAN, District Judge.

This case is now before the court ort exceptions to the report of the auditor to whom reference was made under an order, which, so far as is material here, was as follows:

“In this case it appearing to the court that the controversy in the case-involves among other things the ascertainment of the actual quantity of stone-delivered hy the Hudson River Stone Supply Company to the Venable Construction Company, and it appearing to the court that the ascertainment of the facts in this regard in advance of the trial by jury will be of great aid to the court and jury in the hearing of the case:
“Counsel consenting, it is ordered that for the purpose of ascertaining the-amount of stone so delivered, this matter is referred to Shepard Bryan, Esq., as auditor, to find and report the facts in this regard. Let the auditor’s report show when and in what quantities deliveries of stone were made.. * * *»

The Venable Construction Company had a contract with the government for the construction of certain gun and mortar batteries at Key West, Fla. It was necessary for the Venable Construction Company to have considerable stone in carrying on this work, and it entered into a contract with the Hudson River Stone Supply Company,, on March 25, 1897, for approximately 36,000 cubic yards of stone — _ 2,600 cubic yards being stone crushed and screened to pass through a" three-eighths inch ring, and the balance through a one and one-half' inch ring — and this stone was to be used to make concrete in constructing the gun and mortar batteries.

A provision in the contract between the Venable Construction Company and the Hudson River Stone Supply Company was as follows:

“It is mutually agreed between both parties hereto, that all measurements, of stone shall be taken by U. S. government engineer on arrival of the vessel at Key West, and his certificate of the cubical contents shall be accepted to-the number of cubic yards contained therein, in settlements between them. All freight to be paid according to said measurements, twenty per cent. (20%)-in cash, and balance in New York or Baltimore Exchange, and the balance-for stone thus delivered, on the 15th of each month, for all stone delivered: the month previous, less 10% retained until completion of the contract.
“Einal settlement to be made on final estimates rendered for said work by the engineer officer in charge, detailed measurements to be rendered parties-of the second part, as each boat is measured and discharged.”

The auditor in his report, after discussing the contentions of the-parties, and of the evidence and facts of the case at some length, reaches a conclusion, which will be shown by extracts from his report, as follows:

“I have been very much puzzled in getting at the real truth in this case.. The evidence of the experiments made has not been satisfying. The measurements made by both parties have been unsatisfactory. The theories presented by the plaintiff and defendant are so radically and extremely different, the-plaintiff contending that the srmount of broken stone in 32,440 cubic yards of concrete is about 10 per cent, more than the yardage of concrete, and the defendant contending that the cubic yardage of broken stone in the same amount of concrete is about 10 per cent, less than said yardage.
“After reading and considering all the testimony which has been offered, and after much reflection, I have reached the conclusion that, when broken-. 1%-inch stone is used to make concrete, there is no increase in the cubic yardage of the resulting mass. I am satisfied as to this point. I believe that there is no considerable decrease. It is true that the defendant’s testimony tends to show that in one instance 100 cubic feet of broken stone made 108--[269]*269■cubic feet of concrete, and in another instance 100 cubic feet of stone made 111 cubic feet of concrete. This difference was accounted for by the difference in tamping. * * *
“I have reached the conclusion that the amount of broken 1%-inch stone contained in 32,440 cubic yards of concrete in place in the fortifications at Key West, Florida, was 32,440 cubic yards. In my opinion, not enough sand .and cement was added to entirely fill the voids; indeed, I consider this fact as thoroughly demonstrated by the testimony.
“As I have said before in this report, I do not believe that there was any increase in the mass over the number of cubic yards of stone used.
“I therefore find that the Hudson Itiver Stone Supply Company furnished to the Venable Construction Company 32,440 cubic yards of broken inch and a half stone, and 382.5 yards of granolithic stone.”

The real question in this case is as to how much of the broken stone went into a cubic yard of concrete, as contained in the gun and mortar batteries. The plaintiff contends that there was more stone than concrete, and the defendant contends that there was less stone than concrete. The materials used in preparing the concrete, and the proportions of the same, were as follows: One cubic yard of cement, two cubic yards of sand, and five cubic yards of stone. The plaintiff contends that when the stone, sand, and cement are thus placed together in a solid mass, and “tamped,” as it is called, the sand and cement fill what are called “voids,” that is, the space between the broken stone, and cause the stones to adhere more closely together, thereby making the cubical contents of the mass less than the stone would be if measured before such mixture. The defendant takes the contrary view, and claims that the mass is increased. The special master found, as has been shown from the extracts from his report given above, that a cubic yard of concrete contained a cubic yard of stone. The engineer officer in charge of the work at Key West, on behalf of the United States government, was J. M. Braxton. The testimony of Mr. Braxton was twice taken in this case, and the same was offered in evidence before the auditor. It is a little difficult to get at the exact ruling of the auditor about this testimony. Objection was made on behalf'of the plaintiff to its admissibility in parts and as a whole, and special objection was made to the admissibility of certain tables attached to the last set of interrogatories. These tables were referred to by Mr. Braxton in his evidence as containing various measurements and quantities necessary to arrive at the amount of stone which went into the concrete. There seems to have been a difference in the character of the concrete; that is, what is called “concrete No. i,” “concrete No. 2,” and “concrete No. 3.” The tables attached to Mr. Braxton’s interrogatories show the amount of concrete of each kind, and it also shows the number of what are called “skips,” and the contents of the skips. These skips were used to convey the material to the batteries. The result of the whole testimony of Mr. Braxton, taking his answers to the interrogatories and the tables together, is that he fixed the total amount of stone which went into the 32,440 cubic yards of concrete at 29,147 cubic yards. The stress of the argument by counsel in this case has been directed to the question of the admissibility of this testimony of Mr. Braxton’s, and the effect to be given it, if admitted.

[270]*270• Counsel for the defendant insist that the papers attached to Mr. Braxton’s testimony are admissible as public records.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Radov
44 F.2d 155 (Third Circuit, 1930)
Globe Indemnity Co. v. Reinhart
137 A. 43 (Court of Appeals of Maryland, 1927)
E. I. Du Pont De Nemours & Co. v. Tomlinson
296 F. 634 (Fourth Circuit, 1924)
French v. Virginian Railway Co.
93 S.E. 585 (Court of Appeals of Virginia, 1917)
Navarre Et Ux. v. Honea
1914 OK 96 (Supreme Court of Oklahoma, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
124 F. 267, 1903 U.S. App. LEXIS 4983, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-hudson-river-stone-supply-co-v-venable-const-co-circtndga-1903.