Crane Elevator Co. v. Clark

80 F. 705, 26 C.C.A. 100, 1897 U.S. App. LEXIS 2248
CourtCourt of Appeals for the Seventh Circuit
DecidedMay 22, 1897
DocketNo. 346
StatusPublished
Cited by16 cases

This text of 80 F. 705 (Crane Elevator Co. v. Clark) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crane Elevator Co. v. Clark, 80 F. 705, 26 C.C.A. 100, 1897 U.S. App. LEXIS 2248 (7th Cir. 1897).

Opinion

JENKINS, Circuit Judge

(after stating the facts as above). The contract between the parties provided that one-half part of the contract price should be paid “when the plant is running to the satisfaction of the architect, and has been accepted by him.” This clearly constituted him the arbiter of disputes between the parties to the contract with respect to its performance. The general doctrine is not disputed, that, when the payment of the contract price is conditioned upon the obtaining of the umpire’s certificate, such certificate is a condition precedent to the right of the contractor to recover the contract price. The question arises, however, in regard to the right of the contractor when he has specifically and in good faith performed his contract, and the umpire refuses to accept the work or to give the required certificate. The English and early American cases held to the doctrine that the completion of the work to the satisfaction and acceptance of the umpire, or the obtaining of his certificate, is a necessary affirmative act of performance, and that the decision of the umpire can be refuted only for fraud, collusion, or bad faith. The later decisions of the courts of some of the states, of which Thomas v. Fleury, 26 N. Y. 26; Nolan v. Whitney, 88 N. Y. 648; Weeks v. O’Brien, 141 N. Y. 199, 36 N. E. 185; Chism v. Schipper, 51 N. J. Law, 1, 16 Atl. 316,—are examples, hold to the doctrine that the architect, in his relation as umpire, is the agent of the party for whom the work is to be done and for whose benefit the stipulation is made; that, when the work has been specifically and in good faith performed, a refusal to accept or to issue a certificate is unreasonable; and that a recovery may be had upon evidence other than the architect’s certificate of performance. It is not necessary that we should consider the numerous cases to which we have been referred, and which are, perhaps, somewhat in antagonism, because [708]*708we are bound and precluded from independent judgment by the decisions of the supreme court. The earliest case upon the subject in that court is U. S. v. Robeson, 9 Pet. 319. There the government stipulated to pay under a charter party upon the certificate of the officer commanding the men transported thereunder. A certificate-was given, and payment made for the sum covered by the certificate,, but recovery was sought for other service than that certified to. It was ruled that the obtaining of the certificate was a condition precedent, the court observing with respect to the right of the contractor (page 327):

“He cannot compel the payment of the amount claimed, unless he shall procure the kind of evidence required by the contract, or show that, by time or accident, he is unable to do so; and, as this was not done by the defendant in the district court, no evidence to prove the service, other than the certificates,, should have been admitted by the court. * * * Had the defendant proved that application had been made to the commanding officer for the proper certificates, and that he refused to give them, it would have been proper to-receive other evidence to establish the claim.”

Tbe court treats tbe certificate as evidence of performance, which could be otherwise proven if time or accident prevented tbe obtaining of tbe certificate, or it bad been refused upon application. The-force of this decision is possibly somewhat impaired by tbe rulings in subsequent cases. Kihlberg v. U. S., 97 U. S. 398; Sweeney v. U. S., 109 U. S. 618, 3 Sup. Ct. 314; Railroad Co. v. March, 114 U. S. 549, 5 Sup. Ct. 1035; Railroad Co. v. Price, 138 U. S. 185,11 Sup. Ct. 290;. Railway Co. v. Gordon, 151 U. S. 285, 14 Sup. Ct. 343. Tbe doctrine-established by these cases is this: That, with respect to tbe subject-matter submitted to tbe umpire, bis determination is final and conclusive; that it may be impeached only for fraud, collusion, or such gross mistake as would necessarily imply bad faith, or for a failure-to exercise an honest judgment. This is also tbe rule of tbe state-of Illinois, where this contract was made. Canal Trustees v. Lynch,. 5 Gilman, 521; McAuley v. Carter, 22 Ill. 53; Coey v. Lehman, 79 Ill. 173; Fowler v. Deakman, 84 Ill. 130; Barney v. Giles, 120 Ill. 154,. 11 27. E. 206; Micbaelis v. Wolf, 136 Ill. 68, 26 27. E. 384; Arnold v. Bournique, 144 Ill. 132, 33 N. E. 530; Gilmore v. Courtney, 158 Ill. 432, 41 N. E. 1023. The parties have, however, a right to demand' that the umpire shall, with respect to every matter submitted to- his determination, exercise an independent and honest judgment, and that he shall not arbitrarily refuse to accept performance or to give-a certificate. If the work has been in good faith performed, it is-his duty to accept; the fact of performance to be determined by him in the exercise of an independent, honest judgment. But arbitrary refusal to determine the fact, or arbitrary refusal to accept performance, constitutes a fraud in the law, availing to dispense with the necessity of his judgment as a condition precedent to the right of recovery by the contractor.

We come then to the question whether there was evidence hereof such action by the umpire that the question of the right of the plaintiff to recover the unpaid balance upon the contract should have-been submitted to the jury. In the consideration of this question, we must take that view of the testimony which is most favorable to-[709]*709the contention of the plaintiff in error, resolving all inferences and doubts in its favor. The testimony of the plaintiff below tended to prove the substantial performance of the work contemplated by the contractor, and that, upon a test made, the representative of the umpire had declared his full satisfaction with the work, and that every •condition of the contract had been fulfilled. The only objections which the umpire stated upon the trial he had found to the work prior to the test were that the elevators did not start and stop properly, .and were too noisy. Whether the imperfect starting or stoppage was owing to a defect in the construction, or to ignorant or unskillful operation of them, is not stated. Nor does it appear that such objection existed at and after the test. In regard to the objection of noise, it is to be observed that the original specification provided for a duplicate steam pump, and that the owner required the substitution of an electric pump and motor; that as early as the month of January, 1893, the Crane Elevator Company notified the owner that it had ascertained that the electrical pumping plant was practicable ■only for small powers and for small plants, i. e. that an electric pumping plant for one or two elevators can be constructed with belt connection between the pump and the motor, but with larger plants, to pump against higher pressure, it is necessary to use gearing, which was liable to be noisy; and, if noise be objectionable, they recommended the use of the steam pump, and because, also, it was less expensive to operate, and would occupv less room. No answer being obtained to this communication, the defendant directed the plaintiff to put in the electric pump, which was done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reaugh Construction Co. v. Corlett
23 Ohio N.P. (n.s.) 336 (Cuyahoga County Common Pleas Court, 1920)
Howard County v. Pesha
172 N.W. 55 (Nebraska Supreme Court, 1919)
N. S. Sherman MacH. Co. v. Dun
1911 OK 101 (Supreme Court of Oklahoma, 1911)
City of Atchison v. Rackliffe
96 P. 477 (Supreme Court of Kansas, 1908)
Bush v. Jones
144 F. 942 (Third Circuit, 1906)
Mercantile Trust Co. v. Hensey
27 App. D.C. 210 (D.C. Circuit, 1906)
J. J. Moore & Co. v. Cornwall
144 F. 22 (Ninth Circuit, 1906)
Consumers Gas Trust Co. v. Littler
70 N.E. 363 (Indiana Supreme Court, 1904)
United States ex rel. Hudson River Stone Supply Co. v. Venable Const. Co.
124 F. 267 (U.S. Circuit Court for the Northern District of Georgia, 1903)
City of Elizabeth v. Fitzgerald
114 F. 547 (Third Circuit, 1902)
Columbus Safe-Deposit Co. v. Burke
88 F. 630 (Seventh Circuit, 1898)
Moline Malleable Iron Co. v. York Iron Co.
83 F. 66 (Seventh Circuit, 1897)

Cite This Page — Counsel Stack

Bluebook (online)
80 F. 705, 26 C.C.A. 100, 1897 U.S. App. LEXIS 2248, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crane-elevator-co-v-clark-ca7-1897.