Reaugh Construction Co. v. Corlett

23 Ohio N.P. (n.s.) 336, 1920 Ohio Misc. LEXIS 56
CourtCuyahoga County Common Pleas Court
DecidedApril 14, 1920
StatusPublished

This text of 23 Ohio N.P. (n.s.) 336 (Reaugh Construction Co. v. Corlett) is published on Counsel Stack Legal Research, covering Cuyahoga County Common Pleas Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reaugh Construction Co. v. Corlett, 23 Ohio N.P. (n.s.) 336, 1920 Ohio Misc. LEXIS 56 (Ohio Super. Ct. 1920).

Opinion

Kramef, J.

It is contended by counsel for defendants herein, in support of the defendant’s nmtion for a new trial:

First. That the jury erred in returning a verdict for plaintiff for the full contract price, when, at the most, substantial performance of the contract only, has been proved.

The claim that the evidence does not show strict performance is doubtlessly well taken. Certain minor variations, at least, from the plans and specifications, appear in the work, from which it must be said that the jury could have found substantial performance only. The fact that the architect tendered a certificate which made no deductions for these defects, would not, of course, foreclose defendant from pressing them upon the. trial, that certificate having been rejected.

The record, however, shows no evidence of damage accrueing to the defendant from plaintiff’" failure to perform strictly. Under these circumstances, the court instructed the jury:

‘ ‘ There being no evidence in this case, gentlemen, to show any damage to the owner, by reason of tne failure, if any there was, to build the building in strict compliance with the plans and specifications, the pláintiff is entitled to recover, if entitled to recover at all, upon his petition, the balance therein claimed, with interest from the date concerning which you have been heretofore instructed, namely, August 13. 191-1, which is thirty days after the last work was done on the premises.”

The finding of the jury upon the plaintiff’s petition, in this regard, was in accordance with this instruction, and, in the opin[338]*338ion of the court, there is no reason presented for disturbing the verdict, in this regard.

Second: That the verdict is not sustained by sufficient evidence, and is against the weight of the evidence.

The controversy in this case, as it appeared to be presented at the trial, was in respect to certain deductions made by the architect, under that clause of the contract which provides (Art. 6):

“The contractor shall complete the several portions, and the whole of the work comprehended in this agreement, by and at the time or times hereinafter stated, with the exception of the one-story portion, 100’ 0” north from the Euclid avenue building lines The party of the first part agrees to complete the reinforced concrete, and structural steel work herein described, within sixty-two working days after possession can be obtained of that portion occupying 102’ 3-4 of the Euclid avenue frontage by the depth to the extent of 100’ 0”, and to pay to the party of the second part the sum of $50 per day for each and every day the work remains unfinished, after the expiration of the time above specified. The party of the second part agrees to pay to the party of the first part the sum of $25 per day for every day the work is completed before that date. The portion north of 100 feet from Euclid avenue is to be completed without delay after possession is obtained.”

The deductions were for the number of days, at $50 per day, during which the architect claimed the building had been delayed by defective work of plaintiff, after the expiration of the time allowed in the contract for the plaintiff to complete its work.

The contention of the plaintiff is that the work was not defective in the respects claimed, and that, if there were any defect, there was no delay to the construction of the building by reason thereof.

The work of the plaintiff, by the prox isions of the contract and specifications, xvas to be done to the satisfaction of the architect, and payments were to be made only upon his certificate. No certificate for the amount claimed by the plaintiff and found due it by the jury having been issued, the plaintiff pleads that the architect “wrongfully, arbitrarily, capriciously and unreasonably and at defendant’s request, refused * * * to issue! a proper certificate.”

[339]*339At the request of the defendant, the court charged (No. 4) that there was no evidence to support the allegation that the certificate was withheld at the request of the owner, the defendant. The question then, is, whether the evidence supports the verdict that the certificate was arbitrarily, capriciously and un reasonably withheld?

The deductions made by tne architect were for delay, caused, as he claims, in the setting of the ierra cotta, due to the concrete walls erected by the plaintiff being out of plumb; delay caused to the plasterer by reason of tne faulty construction of the floors and ceilings, and delay caused to cite mason contractor in finishing the floors, due to their faulty construction, all of which delays the architect claims controlled the progress of the building.

The plaintiff, on the other hand, alleges that the difficulty in the setting of the terra cotta was caused by the fault of the mason contractor in starting his work inside the building line, and that this was known to the architect, and admitted by him to be, the fact; that the plasterer was not delayed in the prosecution of his work, due to any faulty work of Lhe plaintiff, and not at all during part of the time for which the deduction was made; that the controversy in relation to the finishing of the floors was due to the type of construction, which caused the heads of the pillars to project into the floors and not to any default of the plaintiff.

The record will show that -competent evidence was offered upon both sides, to substantiate the claims made by each side, respectively. The court can not attempt, here, to review the evidence. There appears to be nothing in the testimony of the variout witnesses, to require special comment, excepting this, that' the evidence of the architect, is surprisingly indefinite, in substantiation of his deductions. In the instance of the plasterer, Mr. Taylor, himself, testifies that he started his work, and was not delayed thereafter, upon May 28th, while the architect deducts to June 16th. For his second deduction, for the second periof of delay, caused by the interference of the terra cotta, charging the full amount to the plaintiff, he seems to offer practically no explanation.

There would seem to be no ground for the court to say that) [340]*340the jury could not reasonably find that the facts were as plaintiff claimed them to be.

If it is the law, that it is for the jury to say, whether the certificate was arbitrarily, capriciously or unreasonably withheld, it would seem to the court that a finding that this certificate waá so withheld, upon the facts, as alleged by the plaintiff, could not be negatived by the court.

Third: That the verdict is contrary to law.

The question as to the correctness of the law, as laid down by the court, is again raised in.the supplemental brief of defendant; and in oral argument, and in briefs, in which-both sides have exhaustively presented the question to the court.

The court has examined the authorities presented by both sides, and while it is not convinced that the interpretation of the law, as made by it at the trial, is not correct, the question is certainly not free from doubt.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martinsburg & Potomac Railroad v. March
114 U.S. 549 (Supreme Court, 1885)
Thomas v. Stewart
132 N.Y. 580 (New York Court of Appeals, 1892)
Pittsburg Terra-Cotta Lumber Co. v. Sharp
42 A. 685 (Supreme Court of Pennsylvania, 1899)
Hudson v. McCartney
33 Wis. 331 (Wisconsin Supreme Court, 1873)
Bird v. St. John's Episcopal Church of Elkhart
56 N.E. 129 (Indiana Supreme Court, 1900)
Lynn v. Baltimore & Ohio Railroad
60 Md. 404 (Court of Appeals of Maryland, 1883)
City of Elizabeth v. Fitzgerald
114 F. 547 (Third Circuit, 1902)
Scully v. United States
197 F. 327 (D. Nevada, 1912)
Penn Bridge Co. v. Kershaw County
226 F. 728 (Fourth Circuit, 1915)
Mundy v. Louisville & N. R.
67 F. 633 (Sixth Circuit, 1895)
Elliott v. Missouri, K. & T. Ry. Co.
74 F. 707 (Eighth Circuit, 1896)
Crane Elevator Co. v. Clark
80 F. 705 (Seventh Circuit, 1897)

Cite This Page — Counsel Stack

Bluebook (online)
23 Ohio N.P. (n.s.) 336, 1920 Ohio Misc. LEXIS 56, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reaugh-construction-co-v-corlett-ohctcomplcuyaho-1920.