Second Nat. Bank of Cincinnati v. Pan-American Bridge Co.

183 F. 391, 105 C.C.A. 611, 1910 U.S. App. LEXIS 5059
Court of Appeals for the Sixth Circuit·Decided December 6, 1910·No. No. 2,045·Published·Cited by 5 cases

Opinion

KNAPPEN, Circuit Judge.

The defendant in error (plaintiff below, and hereafter called the plaintiff) recovered verdict and judgment against plaintiff in error (hereafter called the defendant) for $2,723.49, being the balance of the contract price for certain structural steel work furnished by plaintiff, under written contract with defendant, for the construction of the latter’s bank building, together with the value of certain extras furnished. The questions presented on this review lie within a comparatively narrow compass. The facts material to their understanding are these:

The contract provides that plaintiff shall furnish and erect the work “agreeably to the drawings and plans prepared by” the architects for the owner, and that the work shall be performed “under the direction, and to the satisfaction of” the architects or the authorized representative of the owner; also that payments under the contract should be made “upon a certificate of the architect or other authorized representative of the owner,” 15 per cent, being retained from the amount of each certificate and to be paid within 30 days after the final completion of the work “and the acceptance of the same by the architects of the owner, or its duly authorized agent.” Payments were made from time to time by the defendant as the work progressed, aggregating full payment of the contract price except the sum of $2,062.89. Plaintiff furnished extras amounting to $660.60. It is for the sum of these' two items that recovery was permitted. There is no dispute over the extras. The only dispute over the merits of the other item arises upon the claim of defendant that it should be allowed $2,370.84, as the expense of making certain changes in the work claimed to have been made necessary by plaintiff’s failure to comply with the specifications in one respect only, which is this: The specifications provide that “the connection of beams and columns will be standard.” They also pi-ovide that the contractor shall furnish to the architect, for his approval, triplicate copies of detail drawings, and that the wox’k shall be executed “in strict accordaxice with such approved drawings,” there being the further provision that:

“The architect, ixx approving these dx'awings, approves them in a general manner as being in or out of conformance with the general reqxiirements of his drawings and specifications and does not relieve the coxitractor of responsibility for the correctness of the work shown by them.”

The contractor made detail drawings of the connections of beams and columns, plainly showing 8 holes for each connection; that is to say, in splice-plates, angle irons, columns’, and beams. These drawings were approved in writing by the architect. Construction in accordance therewith proceeded to at least the sixth story, without ob[393] jection by the owner or the architect to the manner of these connections. Objection was then made that good workma 'hip and standard connection required 10 rivets instead of 8 for each connection. The record indicates that this objection was first made by the public building inspector. There is testimony tending to show that the architect, after construction had progressed to at least the height before stated, insisted that new 10-rivet connections be furnished in place of the 8-rivet connections. Upon plaintiff’s refusal or failure to make the changes, they were made by defendant at a cost of $2,-370.84. The architect was satisfied with and accepted the material and workmanship furnished by plaintiff with the single exception of the connections in question, lie refused to finally accept plaintiff’s work as a performance of the contract and to give a certificate of such performance, basing his refusal upon the failure of plaintiff to make the proper connections or to allow defendant for the cost of the changes made therein. The plaintiff’s work has not been accepted by defendant, or by any one on its behalf, as a complete performance of the contract, the defendant, however, being in the occupancy and use of the building. By its plea it offered to confess judgment for 8332.69, as the difference between the plaintiff’s claim and the amount paid by defendant for making the new connections.

Upon the trial there was a conflict of testimony as to whether 8-rivet connections were standard or whether 10-rivets were required. The defendant, both by objection to testimony and by motion for a directed verdict at the close of the testimony, insisted that plaintiff was precluded from recovery by the architect’s refusal to accept performance of the contract and to give his certificate thereof, and that plaintiff could have relief against such refusal only in a court of equity. The court instructed the jury that if plaintiff’s work and material conformed to the contract recovery could be had, notwithstanding the lack of acceptance or certificate by the architect, provided the jury should find that such certificate was withheld “unreasonably and unfairly” or (as expressed at another time) “capriciously or arbitrarily.” An instruction requested by defendant at the close of the general charge that “it is not sufficient to show that the architect is unreasonable and unfair,” was refused. No exception was taken to the charge of the court as given, exception being, however, reserved to the refusal to give the request just referred to as well as to the refusal to direct verdict for defendant.

In our opinion the exception to the refusal of defendant’s request just mentioned sufficiently raises for review the correctness of the charge in the respect mentioned. Indeed, no question of such sufficiency is raised in plaintiff’s brief.

Free access — add to your briefcase to read the full text and ask questions with AI

Second Nat. Bank of Cincinnati v. Pan-American Bridge Co., 183 F. 391, 105 C.C.A. 611, 1910 U.S. App. LEXIS 5059 (6th Cir. 1910).

183 F. 391 (Second Nat. Bank of Cincinnati v. Pan-American Bridge Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

F. J. Lewis Mfg. Co v. Snyder
37 F.2d 299 (Sixth Circuit, 1930)
Reaugh Construction Co. v. Corlett
23 Ohio N.P. (n.s.) 336 (Cuyahoga County Common Pleas Court, 1920)
Stark Electric R. v. McGinty Contracting Co.
238 F. 657 (Sixth Circuit, 1917)
American Sign Co. v. Electro-Lens Sign Co.
211 F. 196 (N.D. California, 1913)