O'Brien v. Sexton

30 N.E. 461, 140 Ill. 517
CourtIllinois Supreme Court
DecidedMarch 24, 1892
StatusPublished
Cited by10 cases

This text of 30 N.E. 461 (O'Brien v. Sexton) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Brien v. Sexton, 30 N.E. 461, 140 Ill. 517 (Ill. 1892).

Opinion

Mr. Chief Justice Magruder

delivered the opinion of the ■Court:

This is ah action of assumpsit begun on April 20, 1888, by the appellant for the use of Bich and Stone against the appellee. Judgment in the trial court was in favor of the defendant below, the appellee here, and this judgment has been affirmed by the Appellate Court, whence the cause is brought before us by appeal.

The declaration contains the common counts only, to which the defendant filed the plea of the general issue. The record shows a written stipulation, signed by the attorneys of both parties, by which it is agreed “that either of the parties may introduce evidence under the pleadings as they stand, the ■same as if an appropriate special count or special plea had been filed in the case, and the said defendant may introduce-any evidence which would be a defense under the statute of limitations, or by way of set-off, or recoupment, which would be admissible if the subject matter were properly pleaded.”

On December 31, 1882, appellant, O’Brien, and appellee, Sexton, entered into a written contract under seal, by which O’Brien agreed, that he would provide all labor, workmanship and materials and execute to completion all the plastering work required in the erection of a block of niné buildings, containing 36 flats, known as Hotel St. Benedict, and located at the corner of Chicago Avenue and Gass Street in Chicago, in accordance with the plans and specifications prepared by J. J. Egan, architect, and annexed to the contract, the work and materials to be subject to the direction and acceptance of Egan and of Sexton, who was to act as superintendent; and' by which Sexton agreed to pay O’Brien $9990.00 as follows: $3000.00 when the work is lathed and browned; $2000.00 'when the work is second coated;, balance, less 15 per cent, 'when completed; the 15 per cent reserved to be paid when work is accepted. Under the specifications, O’Brien was to do lathing, plastering, calcimining, patching, repairing, finishing, •cleaning and drying, and to commence the plastering within •six days after one house was roofed and enclosed, and to continue the work so as to have the entire block plastered within six weeks from the commencement of the plastering. The ■owner, Sexton, was to have the building suitably enclosed with temporary doors and window sashes, etc.

O’Brien or the men under him worked at the lathing and ■plastering until the close of Saturday, April 21,1883, or until sometime in the forenoon of Monday, April 23, 1883, at which time the work, which O’Brien was to do under the contract, liad not yet been finished. After April 23, 1883, O’Brien did no more work. Before that day Sexton had paid him $6225.00 ■upon the contract, and thereafter paid some of his workmen $943.00, making $7168.00 in all, and leaving $2822.00 unpaid. Appellant claims that the cost of completing the contract should not have been more than about $400.00, and that there is due to him the difference between $2822.00 and $400.00, ¡tówit: $2422.00, besides interest and the value of certain materials and utensils alleged to have been appropriated by appellee. On the other hand, appellee claims that he was-obliged to pay out more than $5000.00, in addition to said1 sum of $'7168.00, in order to complete the work left unfinished' by the appellant, and that, in addition to all this, he lost more-than $5000.00 in rents by reason of the delay in the completion of the work.

The pivotal fact in the case is the cause of the failure of appellant to do anything more towards the fulfillment of the; contract after April 21 or April 23. The testimony is clear,1 that O’Brien’s men worked until the close of April 21. The-; testimony is not clear as to whether any work was done on; April 23, though appellant claims that some work was done-, on the morning of that day. Was the failure of O’Brien to. finish the work due to his fault, or to the fault of appellee Did appellant abandon the work and neglect and refuse to pro- - ceed with it, or did appellee refuse to allow the appellant to-, proceed and prevent him from fulfilling his contract ? These, were questions for the jury to decide. Appellee claimed, that appellant abandoned the work without good cause; and there-, was testimony tending to support this view. Appellant claimed,, that appellee refused to furnish him with money to pay the-workmen what was due to them on the evening of April 21,, and forcibly prevented him from entering the building, and employed outside parties to complete the contract without the-, consent of the appellant and without notice to him. There-| was evidence tending to support this contention.

No instructions were given for the plaintiff below, and none-seem to have been asked on his behalf. The court gave some-fourteen instructions for the defendant, and, among others,, the following:

“Tenth—If the jury believe, from the evidence, that there was a written contract between O’Brien and Sexton for the; ‘doing of the plastering in question, and that O’Brien failed and refused to perform his part of said contract, and abandoned said plastering work in an unfinished state, and that Sexton did not release O’Brien from said contract, nor waive the performance of it by him, nor prevent O’Brien from completing his contract, then the jury are instructed, as matter of law, that O’Brien cannot recover anything under said written contract. And even though the jury may believe, from the evidence and under the instructions of the court, that O’Brien is entitled to recover-under an implied contract for some plastering done by him, yet the jury are instructed, as matter of ■ ' law, that he cannot, under such implied contract, recover for any work done or materials furnished before April 20, A. D. 1883, but only for work done and materials furnished on or after April 20, A. D. 1883, if done and finished under a contract not in writing, or an implied contract.

“Eleventh—If the jury believe, from the evidence and under the instructions of the court, that O’Brien is not entitled to ■recover under a written contract for the plastering in question, ; but is entitled to recover under an implied verbal contract for plastering done by him, then the jury are instructed that the' Statute of Limitations precludes a recovery by O’Brien for! any plastering done by him more than five years before the. commencement of this suit. This suit was commenced April ' 20, A. D. 1888.”

These were the only instructions given which related to the statute of limitations, and we think that, under the facts of this case, they were erroneous and calculated to mislead the jury.

Under the stipulation of the parties the declaration is to be .regarded as containing not only the common counts, but a .special" count founded upon a breach of the contract. If the defendant, Sexton, forced the plaintiff, O’Brien, to abandon ,the work at the close of Saturday, April 21, he was guilty of-.a breach of the contract at that time, and, if the plaintiff was entitled to recover by reason of such breach, the cause of action accrued at that time. This suit, having been begun on April 20, 1888, was commenced one day less than five years after the plaintiff did the last work upon the defendant’s building.

If the action be regarded as a suit upon the express contract in writing brought to recover damages for a breach thereof, the cause of action was not barred on April 20,1888.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Berg & Associates, Inc. v. Nelsen Steel & Wire Co.
580 N.E.2d 1198 (Appellate Court of Illinois, 1991)
Santucci Construction Co. v. City of Danville
471 N.E.2d 1000 (Appellate Court of Illinois, 1984)
Brown v. Forest Park Foundation
308 N.E.2d 310 (Appellate Court of Illinois, 1974)
Strom v. Lipschultz
282 N.E.2d 257 (Appellate Court of Illinois, 1972)
Burns v. Mitchell
191 S.E. 870 (Court of Appeals of Georgia, 1937)
Sibley v. Stetson & Post Lumber Co.
188 P. 389 (Washington Supreme Court, 1920)
Rudy v. Rudy
23 Ohio C.C. Dec. 359 (Stark Circuit Court, 1912)
Quackenboss v. Devine
167 Ill. App. 5 (Appellate Court of Illinois, 1912)
Crampton v. Logan
63 N.E. 51 (Indiana Court of Appeals, 1902)
Crane Elevator Co. v. Clark
80 F. 705 (Seventh Circuit, 1897)

Cite This Page — Counsel Stack

Bluebook (online)
30 N.E. 461, 140 Ill. 517, Counsel Stack Legal Research, https://law.counselstack.com/opinion/obrien-v-sexton-ill-1892.