Newman v. United States

81 F. 122, 1897 U.S. App. LEXIS 2625
CourtU.S. Circuit Court for the District of Western Virginia
DecidedFebruary 10, 1897
StatusPublished
Cited by2 cases

This text of 81 F. 122 (Newman v. United States) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Western Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Newman v. United States, 81 F. 122, 1897 U.S. App. LEXIS 2625 (circtwdva 1897).

Opinion

PAUL, District Judge.

This is a petition filed by the plaintiffs against the United States under the provisions of the act -of congress passed March 3, 1887, entitled “An act to provide for the bringing of suits against the government of the United States” (24 Stat. 505)'. The petitioners claim that the government owes them the sum of $7,846.61, as an unpaid balance on a contract made on the 29th day of December, 1890, between the United States and the petitioners for the construction of a road from the city of Staunton, Va., to the National Cemetery, near that city. The contract made for said road was authorized by an act of congress passed April 9, 1890, appropriating $11,000 for that purpose.

The petition alleges:

“That, as provided in tlieir said contract, they entered upon the building of the said roadway according to the plans and specifications set forth in the contract, they furnishing the material, labor, and all other things necessary for the carrying out of their said contract; that the United States furnished a [123]*123superintendent to supervise the work, and to see tlint it was done according to contract; that this superintendent dealt so harshly and unjustly with your petitioners, depriving them by his repons of compensation for work which they did according to contract, and refusing to recommend for them compensation for extra work done, and for work done in a different way from that specified in the «contract, so that before the completion of the work it broke up your petitioners financially, and they were compelled to abandon the work, and let other contractors finish it, much to their damage and injury.”

The petition makes an exhibit of the statement of settlement made by the war department of the work done, and prices of the same. The petition further alleges that:

“This statement of settlement did very gross injustice to your petitioners, depriving them of nearly one-half of what was justly due them. The following is a statement of the account which should have been rendered, and by which they*, should have had a settlement for this work. This statement shows that the superintendent in charge of the work on the part of the United States .did not properly classify the work done, lie classifying liard-pan excavation as earth excavation, not allowing sufficient solid-rock and loose-rock excavation; not allowing for The construction of valley guttering when the contract called for lateral guttering; not allowing for curbing at all; not allowing sufficient macadam for foundation, both from material obtained in excavation of the road and for material brought from the outside; and for other errors, misstatements, and disallowances as shown by this statement of the account.”

Then follows a statement of the account between the parties as the petitioners claim it should be.

Upon the evidence the court finds the following facts: (1) That the petitioners, William W. Newman: and D. Newton Wilson, citizens of Augusta county, Virginia, as partners under the firm name of Newman & Wilson, ou the 29th day of December, 1890, entered into a contract with the United States for the construction of a roadway leading from the city of Staunton, Virginia, to the National Cemetery, near that city. (2) That preliminary to the signing of said contract by the parties thereto, G. B. Dandy, deputy quartermaster general, U. S. army, advertised for proposals for the said roadway. (3) That the curbing mentioned in the advertisement for proposals for the construction of the roadway, and in the proposal of the claimants, is not embraced in the contract, and that the curbing was done independently of the contract; that the price of the curbing was fifteen cents per lineal foot; and that the same was included in the engineer’s report of solid rock removed, and paid for in the amount allowed the claimants for solid rock in the final statement made by the war department. (4) That the gutter called for in the contract was a lateral gutter, and that the one constructed by claimants is what is known as a valley gutter; that the latter was adopted and constructed with the tacit, if not expressed, consent of the claimants; that there was no agreement between the engineer in charge of the work and the claimants that the price to be paid for this kind of gutter was to be other than that named in the agreement for the lateral gutter; that no authority was given by the United States to the engineer to make any other contract for the gutter than that stated in the contract, nor did. the United States sanction any other; that the guttering was reported by the engineer in his final estimate at the price named in the agreement, and the same was paid to the claimants without objection on their part. (5) That the item in the claimants’ demand [124]*124designated “100 cubic yards water excavation in culvert at $1.00 per yard” was embraced in tbe contract in tbe work to be done designated under the head of “Culvert”; that the same was..included in the engineer’s final estimate and report, and has been paid for. (G) That the item in claimants’ demand designated “Regrading hill west of cemetery, $100,” is embraced in the contract under the head of “Grading,” as stated in the specifications; that it was included in the final, estimate and report of the engineer, and the same has been paid for. (7) That the engineer in charge and supervising- the work, as provided in the contract, was W. L. Whitmore; that it is not alleged in the petition, nor shown by the evidence, that there was any fraud or gross mistake on his part, such as would imply bad faith toward the claimants in the discharge of his duties in making measurements and classifications of the material excavated, nor that there was any failure on his part to exercise an honest judgment in the discharge of his duties. (8) That on October 31,1890, W. L. Whitmore, tbe engineer in charge of the construction of the roadway, made his report to the war department that the roadway was completed, accompanying said report with a statement of the work done and the amount due thereon to the claimants, Newman & Wilson; that the amount was paid to Newman & Wilson and receipted for in full.

The following are the report and receipt, which are made part of this finding:

“Staunton, Va., National Cemetery, Staunton, Va., October 31st, 1890.
“I hereby certify that I have this day inspected the work performed and material furnished by Newman & Wilson, contractors, on the construction of roadway at the Staunton, Va., National Cemetery, as j)er statement attached. I further certify that the work done and material used are satisfactory, and in accordance with the requirements of the contract, and I estimate that there is due therefor to the said Newman & Wilson, contractors, the sum of nine thousand three hundred and sixty-nine and ^Vioo dollars, less previous payments, work completed and accepted.
“William L. Whitmore, Civil Engineer & Inspector, Q. M. Dept.”
“I certify that the above account is correct and just; that the services were rendered as stated; that they were necessary for the public service, anil are borne on my report of persons, etc., for the month of October, 1891.
“G. B. Dandy, Deputy Qr. Mr. General, U. S. Army.”
“Received at Washington, D. C., the 9th day of November, 1891, of Dieut. Col. Geo. I-I.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joice v. United States
51 Ct. Cl. 439 (Court of Claims, 1916)
United States ex rel. Hudson River Stone Supply Co. v. Venable Const. Co.
124 F. 267 (U.S. Circuit Court for the Northern District of Georgia, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
81 F. 122, 1897 U.S. App. LEXIS 2625, Counsel Stack Legal Research, https://law.counselstack.com/opinion/newman-v-united-states-circtwdva-1897.