Wilson v. County of Buchanan

298 S.W. 842, 318 Mo. 64, 1927 Mo. LEXIS 490
CourtSupreme Court of Missouri
DecidedOctober 10, 1927
StatusPublished
Cited by8 cases

This text of 298 S.W. 842 (Wilson v. County of Buchanan) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilson v. County of Buchanan, 298 S.W. 842, 318 Mo. 64, 1927 Mo. LEXIS 490 (Mo. 1927).

Opinions

This is a suit for a balance claimed by plaintiff for grading a road, under a contract with the defendant county. The petition alleges that plaintiff undertook to grade the Easton-Fisher road, in certain governmental sections, under a contract and *Page 68 bond given by him, in obedience to directions to be given from time to time by the county surveyor, and in accordance with written specifications made a part of the contract; and that the county agreed to pay therefor seventeen and one-half cents per cubic yard of earth moved. It is alleged that plaintiff performed and completed the work, according to the contract, and that in doing so, moved 82,000 yards of earth, which, at the price agreed, entitled him to payment in the sum of $14,350; that the representatives of the county measuring the work, made a gross and palpable mistake, and allowed plaintiff as for earth moved only 32,717.8 yards, or 49,282.2 yards less than the amount of earth actually moved. It is alleged that the work was accepted by the county, but that the measurements and estimates of the county's engineer were false, fraudulent and grossly incorrect and inadequate, and that there is owing to plaintiff for said work the sum of $8,624.35.

The answer, after a general denial, admitted the making of the contract; and next, pleaded that plaintiff "in performing said contract, moved not to exceed 48,130 yards of earth, and that he has been fully compensated therefor, and final payment made to him on said contract." The answer also pleaded the following provision of the contract. "The grading will be paid for by the cubic yard of excavation only, and the figures of the Highway Engineer on final estimate shall be taken as final." It was then alleged "that said final estimate was duly made, and payment made to plaintiff in accordance therewith, and that said final payment was accepted by the plaintiff."

The reply was a general denial.

There was a verdict for plaintiff in the sum of $4,312.18, which was one-half the amount sued for. Defendant appealed, and plaintiff also appealed. By mistake of the clerk, the appeals were allowed to the Kansas City Court of Appeals; and upon motion that court properly transferred the cause to this court. [Constitution, art. 7, sec. 12.] The plaintiff is not pressing the appeal taken by him, and the cause is to be considered upon the appeal of defendant.

The defendant insists that error was committed in the refusal of the court to give the peremptory instruction offered by defendant at the close of the plaintiff's case, and again at the close of the whole case. The contention of defendant is put upon two grounds: First, that the evidence for plaintiff as to the moving of any earth in excess of that allowed and paid for, is vague and indefinite, and insufficient to support the verdict, which, it is urged, was based upon conjecture; and second, that the evidence showed a final settlement with plaintiff, and final payment to him, made without fraud or gross error; and that plaintiff is bound thereby. Complaint is also made of the admission of certain testimony, and the giving and refusal of certain instructions. *Page 69

The contract was made in October, 1917, and the work done thereunder was completed in July, 1918. This suit was brought in February, 1923. In August, 1918, after the completion of the work, a warrant was issued to the plaintiff for $1,422.75 containing a recital that it was for final payment for grading the Easton-Fisher road. Plaintiff cashed this warrant. The contentions and the evidence as to the claim of mistake, then and thereafter made by the plaintiff, will be noticed later. The determinative question in the case is whether in measuring and estimating the number of yards of earth moved, a gross mistake was made.

At the time of the making of the contract, one Ray L. Cargill was County Highway Engineer. He continued to be such until about the time, or shortly after, the work was completed, when he resigned and moved to Kansas City. He was succeeded by H.L. Meyer, who had been his assistant. The final measurement or estimate was made by Meyer. Cargill testified that he was a civil engineer, and was engaged almost altogether in that sort of work from 1901 to 1918; that the profile, and an estimate of the amount of earth to be moved, were made by him or under his supervision. This was done before the surface of the road was disturbed. He said he had not seen the profile or estimate since he resigned, but his recollection was that it was approximately 80,000 cubic yards. He was asked what degree of accuracy, as to yardage, the profile should indicate. He answered: "The profiles are not attempted to be made accurate, consequently the estimate would not be accurate. We found in some instances they ran within five per cent and sometimes would go as high as twenty-five per cent, depending upon the amount of bank dirt to be moved. I should say an average of sixteen and two-thirds per cent would be about right. That would run both ways. I think I can safely say it would be more apt to run over. There would likely be more yardage than less." Farther on in his testimony he explained that the profile was of the center line of the road. The surface of the road throughout the width of the cut to be made would not always be of the same level as the center or profile. The estimate of the cut in the center of the road could be made with some accuracy, but it was necessary to add percentages to this, which were estimates, for what was spoken of as bank work. The profile was introduced in evidence, but it is not set out in the bill of exceptions as in the abstract; but the recital is made that the estimate of 82,000 yards was marked thereon.

Robert L. George was produced as a witness for plaintiff. He testified that he lived on the road in question; that he had been in the County Engineer's office for about nine years, but was not a civil engineer; that his position was that of road supervisor; that he helped to run the line. He testified that his only experience in estimating yardage in the grading of roads was that he would read *Page 70 whether they ran over or under; that he knew nothing about it except when, in the office, he would know whether the estimate went over or under. He was asked, by the court, if he knew anything about estimating the amount of dirt to be moved from a given road or profile. He replied that he did, from observation; that he could go over a given road and estimate about what the dirt would be. He testified that the profile of this road was "around 80,000, or something like that." He described the width of the road at certain places, and depth of the cuts, and he was asked whether in his judgment the profile was correct. He answered: "The profile was on the center line of the road and the boys always added something extra for the cuts. I would think the profile was small enough for the road at that time, anyhow." He also said that the plaintiff "in order to grade out his fills, in places, had to go below his grade stakes. It might have been three or four plowings."

W.B. Hazen testified for plaintiff. He had been working as civil engineer since 1888, with the exception of about two years. He said that he was County Engineer from 1901 to 1907, and had experience in estimating the quantities of earth to be moved for highways and ditches; that in 1921 he undertook to survey and verify the final levels run by H.L. Meyer, upon the road in question, but could not verify them. He said: "While he ran in his cuts, his fills were raised about the profile. His cuts were lower, and west of Easton it was impossible to check on his bench mark at the bridge. He was off, I think, thirteen feet at the bridge. You could not put very much dependence in that kind of levels. . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Highway Department v. W. L. Cobb Construction Co.
143 S.E.2d 500 (Court of Appeals of Georgia, 1965)
State Highway Dept. v. Cobb &C. Co.
143 S.E.2d 509 (Court of Appeals of Georgia, 1965)
State Ex Rel. State Highway Commission v. Warner
361 S.W.2d 159 (Missouri Court of Appeals, 1962)
Giudicy v. Giudicy Marble, Terrazzo & Tile Co.
329 S.W.2d 664 (Supreme Court of Missouri, 1959)
Denney v. Spot Martin, Inc.
328 S.W.2d 399 (Missouri Court of Appeals, 1959)
Olsen v. Bernie's, Inc.
296 S.W.2d 3 (Supreme Court of Missouri, 1956)
Baker v. Estate of Brown
294 S.W.2d 22 (Supreme Court of Missouri, 1956)
Randol v. Kline's Incorporated
18 S.W.2d 500 (Supreme Court of Missouri, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
298 S.W. 842, 318 Mo. 64, 1927 Mo. LEXIS 490, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilson-v-county-of-buchanan-mo-1927.