Rothwell v. Dean

60 Mo. App. 428, 1895 Mo. App. LEXIS 309
CourtMissouri Court of Appeals
DecidedJanuary 15, 1895
StatusPublished
Cited by4 cases

This text of 60 Mo. App. 428 (Rothwell v. Dean) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rothwell v. Dean, 60 Mo. App. 428, 1895 Mo. App. LEXIS 309 (Mo. Ct. App. 1895).

Opinion

Bond, J.

This action is for a balance claimed to be due under a contract to finish a levee at Cairo, Illinois. The contract sued on is to wit:

“St. Louis, July 14,1890.
“This agreement made and entered into between the firm of Dean, Berry & McKinney and J. F. Roth-well & Bro., by which the firm of Dean, Berry & McKinney, now holding subcontract from the 'firm of Greenlee & Little, general contractors on Cache Levee in Alexander county, Illinois, and with their consent, do hereby sublet to J. F. Rothwell & Bro. "all unfinished work on said Cache Levee between station numbers 83 and 117 and between station numbers 123 and and 129 of said levee. It is further agreed between the firm of Dean, Berry & McKinney and J. F. Roth-well & Bro. that the said J. F. Rothwell & Bro. shall complete the said work in accordance with the plans and specifications of the Cairo Board of Drainage Commissioners, and to their approval and acceptance of the said work, and, further, that the said firm of Dean, [430]*430Berry & McKinney shall pay to the said J. E. Rothwell & Brother fourteen cents per yard for embankment, which shall be payable after each monthly estimate, and be paid between the fifteenth and twentieth of each month, except, however, ten per cent. (10 per cent.) of all estimates, which is retained by said Cairo Board of Drainage Commissioners until the completion of said levee; and, further, the said J. E. Rothwell & Bro. shall prosecute the-work continuously until it is completed, and shall have all the work completed to the satisfaction of the said Cairo Board of Drainage Commissioners before October 1, 1890.
“Now, if the said J. E. Rothwell & Bro. shall have completed the said work to the satisfaction of the said Cairo Board of Drainage Commissioners, then the said firm of Dean, Berry & McKinney agree to pay to the said J. E. Rothwell & Bro. the sum of three hundred dollars ($300) extra, above all estimates.
“J. E. Rothwell,
“Dean, Berry & McKinney.”

The answer was a general denial, and contained a plea of payment. The case was tried before a jury, who found a verdict for the plaintiffs in the sum of $1,311, stating in their verdict that they allowed plaintiffs nothing for the work done by the Hakes force gang, hereinafter referred to. From a judgment entered upon this verdict the defendants prosecute the present appeal, and assign for error that the court in its instructions to the jury misconstrued the contract between themselves and the plaintiffs, and admitted illegal evidence against defendants’ objections, and that the verdict is excessive under the evidence.

In order to understand the substantial controversy between the parties, the following facts developed by the evidence become material. The levee work sublet to the plaintiffs consisted of several detached sections. [431]*431One of these sections lay east of the railroad embankment of the Illinois Central Railroad, and comprised stations from 83 to 108, each station being one hundred feet in length, the whole aggregating a length of two thousand, five hundred feet. It is in regard to this section that the controversy in the main arises. As this station was nearest the Ohio River, and near the confluence of the Ohio and Cashe Rivers, it was that part of the work which was most subject to overflow by a sudden rise of these rivers. The bulk of the work, which the defendants did prior to subletting the work to the plaintiffs, was done on this section. Besides this section, the defendants sublet to the plaintiffs work on sections west of the embankment of the Illinois Central Railroad, touching which, however, there is no substantial controversy.

Charles Throop, a witness for the plaintiffs, testified that he was the chief engineer of the Levee Company engaged in doing this work. According to his uncontradicted evidence he had been a civil engineer for a period of near forty years, and as such engaged in the supervision of large enterprises. Touching his thorough qualifications as an expert there can be no doubt. He testified that he made an estimate of the work done by the defendants prior to the time that they quit work, and found that the work done by them amounted to twenty-nine thousand and eighty-nine cubic yards of earth, east of the embankment of the Illinois Central Railroad. The defendants did some work after this measurement was made, but all the testimony seems to concede that this work was done on the four stations next to- the embankment of the Illinois Central Railroad.

In the early part of the year 1890, the waters rose to a great height in the Ohio and Cashe rivers, and flooded part of the work that had been done by the [432]*432defendants. The work at that time was in the following shape: There were about seven hundred feet of it between stations 92 and 99 raised to the established grade. This portion was above high water mark, and was not affected by the rise of the ■ waters. On both sides of this high fill, but mainly on the western side thereof, the bank was left by defendants much below grade, and was overflowed by the waters. The soil of which the embankment was made was in part sandy, and washed and floated off easily. After the waters had subsided, the chief engineer examined this bank, and he testified upon the trial that, in his opinion, from three thousand five hundred to five thousand yards had been thus washed off. What the loss thus caused amounted to, how it affected the final estimates, and whether it should fall upon plaintiffs or the defendants, were the main points controverted at the trial.

When the engineer, testified as to the amount of the loss caused by the overflow, the defendants objected to the testimony on two grounds: first, because, according to théir contention losses of that character had to be borne by the plaintiffs under the terms of their contract, and, next, because the evidence was vague and indefinite touching a subject which was capable of being ascertained by exact measurement. The first of these contentions is based on the theory that plaintiffs were bound by the terms of their contract to make good any injury to the work done before the subletting to them by floods or casualties of all kinds. This contention has for its only support section 9 of the plans and specifications referred to in the contract in suit. By this section the contractor was required to take all risks from floods and other sources which might occur before the final completion of the work. The section in question, however, does not by its terms, nor any sound principle of interpretation, operate [433]*433retrospectively. It only undertook to make provision, as between the parties to this suit, for losses or damages occasioned by the excepted causes after the beginning of the work. It was not intended to impose any liability on plaintiffs for losses or damages, which had fallen on defendants in their previous construction of the levee. There is, therefore, no merit in that assignment. The plaintiffs’ contract with the defendants bears date July 14, 1890, and there is no pretense that any losses were caused by the floods subsequent to said date.

Nor is, in our opinion, the second of these contentions tenable. It is not satisfactorily shown that the losses thus caused were ever measured by the engineer in any other manner, except by the estimate which he thus placed upon them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. State Highway Commission v. Warner
361 S.W.2d 159 (Missouri Court of Appeals, 1962)
Giudicy v. Giudicy Marble, Terrazzo & Tile Co.
329 S.W.2d 664 (Supreme Court of Missouri, 1959)
Denney v. Spot Martin, Inc.
328 S.W.2d 399 (Missouri Court of Appeals, 1959)
Wilson v. County of Buchanan
298 S.W. 842 (Supreme Court of Missouri, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
60 Mo. App. 428, 1895 Mo. App. LEXIS 309, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rothwell-v-dean-moctapp-1895.