Sun Shipbuilding & Dry Dock Co. v. United States Lines, Inc.

439 F. Supp. 671, 1977 U.S. Dist. LEXIS 13214
CourtDistrict Court, E.D. Pennsylvania
DecidedOctober 31, 1977
DocketCiv. A. 75-2275
StatusPublished
Cited by19 cases

This text of 439 F. Supp. 671 (Sun Shipbuilding & Dry Dock Co. v. United States Lines, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sun Shipbuilding & Dry Dock Co. v. United States Lines, Inc., 439 F. Supp. 671, 1977 U.S. Dist. LEXIS 13214 (E.D. Pa. 1977).

Opinion

MEMORANDUM AND ORDER

CAHN, District Judge.

I. INTRODUCTION

Plaintiff Sun Shipbuilding and Dry Dock Company (“Sun”) and defendant United States Lines, Inc. (“USL”) have filed cross-motions for summary judgment. Plaintiff alleges that it is entitled to $926,617.17 1 in contract damages as well as substantial interest charges dating from January 1, 1966. Defendant contends that as a matter of law it has no further contract liability and that in any event plaintiff is not entitled to recover interest for any period prior to this court’s final decision. I have concluded that plaintiff’s motion should be granted and defendant’s denied.

II. FACTS

Plaintiff is a shipbuilding company. In late 1962, plaintiff entered into a tripartite agreement with defendant and the United States Maritime Administration pursuant to the Ship Construction Subsidy Program, 46 U.S.C. § 1101 et seq., to construct five cargo vessels. Under the contract, the Maritime Administration obligated the United States Government to pay 48.6 percent of the contract price, and defendant agreed to pay the remaining 51.4 percent. Following a series of legal battles, the Government fully satisfied its obligation; only defendant’s share is at issue in this case.

Under the terms of the contract, USL and the Government were entitled to order changes unilaterally in the construction of the vessels. The contract provided arbitration procedures for determining plaintiff’s compensation for increased costs due to such modifications. 2

Pursuant to these contract terms, USL ordered Sun to undertake two substantial changes in the construction of the ships. Sun diligently performed the necessary work. On November 24, 1965, two months after its delivery of the final vessel, Sun submitted a $5,000,000 claim for additional compensation. On November 13, 1967, the Division of Estimates found plaintiff’s actual costs to be $1,700,000. On appeal, the Office of Ship Construction redetermined the costs and found them to be $2,200,000. An appeal by both parties to the Maritime Subsidy Board resulted in an increase of the plaintiff’s compensation to $2,798,882.35 on September 24, 1971. Finally, on January 20, 1972, the Secretary of Commerce, upon consideration of another set of challenges by USL and Sun, again modified the award by increasing it to $3,070,547.95. Plaintiff appealed this award to the Court of Claims with respect to the Government’s share. The Court of Claims affirmed the Secretary’s decision on May 28, 1976.

During this entire period, Sun still had recovered no compensation from the defendant for the costs of the changes defendant had unilaterally ordered. Furthermore, USL has, to date, not paid its full share of the change costs which it concedes are *675 owed. Upon plaintiff’s demand for payment in 1972, USL did offer to pay its share of the administrative award if plaintiff would waive its right to appeal the award of the Maritime Subsidy Board. But at no time after the Secretary of Commerce increased the award did defendant offer to satisfy plaintiff’s full claim, along with the interest plaintiff alleged was due.

III. ISSUES

Plaintiff’s alternative claims raise several issues:

1. Is Sun entitled to prejudgment interest from January 1, 1966 — a reasonable time after it submitted its final estimate of costs — on the full amount awarded?
2. If not, is Sun entitled to prejudgment interest from September 24, 1971— the date of the Maritime Subsidy Board’s final award — on the full amount awarded?
3. Is Sun at least entitled to prejudgment interest from January 1, 1966, on the amount USL conceded was due?

Defendant’s lengthy reply claims that no interest is recoverable because Sun’s claim was not liquidated prior to the Secretary’s decision and no prejudgment interest can be recovered on an unliquidated debt. USL also contends that the contract imposes no liability whatsoever on it until all “disputes” with respect to the contract are settled, and thus no interest can be charged prior to this court’s final decision.

USL’s cross-motion raises the following procedural issues:

1. Did a Court of Claims ruling concerning plaintiff’s claims against the United States determine plaintiff’s interest claim and thus estop the similar claim in this case? Alternatively, does Sun’s presentation of its case to the Court of Claims operate as a waiver of Sun’s interest claim in this action?
2. Is the United States an indispensable party to this action, such that this court cannot decide the issues before it unless the United States is joined?
3. Does Sun’s failure to accept USL’s payment offer in 1972 preclude any claim for interest?

USL also raises a number of substantive challenges to the award of the Secretary itself:

1. Did the Secretary err as a matter of law in awarding Sun compensation for delay costs?
2. Did the Secretary err as a matter of law in awarding Sun compensation for delay costs relating to delay occurring before the final contract due date?
3. Did the Secretary err as a matter of law in awarding in excess of three million dollars in view of the fact that USL relied on Sun’s lower original estimate of costs?

IV. INTEREST 3

A. Should Prejudgment Interest Be Awarded ?

Ordinarily the issue of whether prejudgment interest should be awarded to a claimant under a contract depends on whether the claim was liquidated or unliquidated at the time it was brought. The time when USL’s debt became liquidated in this case — that is, when it was “finally” ascertained or capable of ascertainment with mathematical precision — is a matter which the parties have vigorously disputed.

The two rules for prejudgment interest are similar under Pennsylvania and federal law. If a claim is liquidated, the party whose payment or money has been withheld is entitled to prejudgment interest as a matter of right from the time the money became due or payable. Eazor Express, Inc. v. Int’l Brotherhood of Teamsters, 520 F.2d 951, 973 (3d Cir. 1975), cert. *676 denied, 424 U.S. 935, 96 S.Ct. 1149, 47 L.Ed.2d 342 (1976); Oxford Manufacturing Co. v. Cliff House Building Corp., 224 Pa. Super. 387, 307 A.2d 343 (1973). If, on the other hand, the claim is not mathematically ascertainable, prejudgment interest is ordinarily not allowed. However, the court, in its discretion, may in a particular case find that the equities of the circumstances demand an award of interest and may grant such an award as it deems proper. Miller v. Robertson,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gil Enterprises, Inc. v. Delvy
79 F.3d 241 (Second Circuit, 1996)
Brantley v. Weeks (In Re Brantley)
116 B.R. 443 (D. Maryland, 1990)
Lexington Insurance v. Abington Co.
621 F. Supp. 18 (E.D. Pennsylvania, 1985)
Stewart v. Harris Structural Steel Co., Inc.
486 A.2d 1265 (New Jersey Superior Court App Division, 1984)
Delta Steamship Lines, Inc. v. United States
31 Cont. Cas. Fed. 71,587 (Court of Claims, 1983)
EC Ernst, Inc. v. Koppers Co., Inc.
520 F. Supp. 830 (W.D. Pennsylvania, 1981)
Silver v. Gene K. Kolber Advertising, Inc.
518 F. Supp. 939 (E.D. Pennsylvania, 1981)
Peterson v. Crown Financial Corp.
498 F. Supp. 1177 (E.D. Pennsylvania, 1980)
Gold & Co. v. Northeast Theater Corp.
421 A.2d 1151 (Superior Court of Pennsylvania, 1980)
Sharp v. Coopers & Lybrand
491 F. Supp. 55 (E.D. Pennsylvania, 1980)
Fidelity & Deposit Co. v. Calesnick
482 F. Supp. 72 (E.D. Pennsylvania, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
439 F. Supp. 671, 1977 U.S. Dist. LEXIS 13214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sun-shipbuilding-dry-dock-co-v-united-states-lines-inc-paed-1977.