Vermont Marble Co. v. Baltimore Contractors, Inc.

520 F. Supp. 922, 29 Cont. Cas. Fed. 81,786, 1981 U.S. Dist. LEXIS 14044
CourtDistrict Court, District of Columbia
DecidedAugust 20, 1981
DocketCiv. A. 79-3079
StatusPublished
Cited by7 cases

This text of 520 F. Supp. 922 (Vermont Marble Co. v. Baltimore Contractors, Inc.) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vermont Marble Co. v. Baltimore Contractors, Inc., 520 F. Supp. 922, 29 Cont. Cas. Fed. 81,786, 1981 U.S. Dist. LEXIS 14044 (D.D.C. 1981).

Opinion

MEMORANDUM AND ORDER

CORCORAN, Senior District Judge.

This matter is before the Court on cross motions for summary judgment. Additionally the plaintiff, Vermont Marble Company, has moved for partial summary judgment on several underlying issues.

The action arises out of the construction of an extension to the Everett McKinley Dirksen Senate Office Building on Capitol Hill. The defendant, Baltimore Contractors Inc. (BCI), was the prime contractor with the Architect of the Capitol (AOC or Architect) to perform “Phase IV” in the construction.

The plaintiff, Vermont Marble Company (VMC) was a subcontractor to BCI. Its undertaking was to do the stonework facing on the building. Roughly 20 months after signing the subcontract, VMC abandoned the project asserting a right to rescind by reason of undue delays in the preparation of the site for the performance of its stonework.

Shortly before formally rescinding, VMC filed this action seeking a declaration of its rights under the subcontract and asking monetary relief in the nature of quantum meruit for the work it had performed thereunder.

A. Factual Background

1. The Prime Contract Between the Architect and BCI

In the summer of 1977 the Architect invited bids for “Phase IV” of the extension of the Dirksen Building. Phase IV involved the construction of the superstructure of the building. 1 BCI was awarded the contract and on October 28, 1977 was given “notice to proceed.”

Under its prime contract with the Architect, BCI agreed to certain “milestone” dates for completion of specified major steps of construction. The original milestones, measured from the October 28, 1977 notice to proceed, were as follows:

*924 1. Commencement of structural steel installation: 185 days (April 30, 1978).
2. All concrete and fireproofing through first six floors: 440 days (January 10, 1979).
3. All concrete and . . . through remaining floors and roof: 550 days (April 30, 1979).
4. Stone installation and masonry work through first six floors: 745 days (November 11, 1979).
5. Completion of all work: 900 days (April 14, 1980).

2. The Subcontract Between BCI and VMC

In August 1977, VMC sent a proposal to BCI for a subcontract to perform the stonework. BCI used the VMC bid in its bid for the prime contract. In December, 1977, BCI presented VMC with a counter proposal which consisted of BCI’s standard form subcontract with 11 pages of attached “riders.” Among the key elements of the Baltimore Contractors’ proposal were the following:

1. Article IV, stating in part, that “Subcontractor shall . .. prosecute the work . . . in prompt and diligent manner; and . . . where necessary to expedite the performance thereof, the authorized representative of subcontractor shall take orders directly from the Superintendent of Contractor. Subcontractor shall do the several parts of the work at such times and in such order as Contractor may direct and shall proceed with and wholly finish the work in such time as not to delay Contractor or other subcontractors, and to insure completion of the Prime Contract within the time fixed therein; ... it being understood that time is of the essence of this Agreement.”

2. Article XIV, included a “no-damage-for-delay” clause, providing, inter alia: “Contractor shall have the right at any time to delay or suspend the commencement or execution of the whole or any part of the work without compensation or obligation to subcontractor other than to extend the time for completing the work for a period equal to that of such delay or suspension.”

3. A rider directing subcontractor’s attention to the milestone and liquidated damages provisions of the prime contract.

4. A rider representing that Baltimore Contractors would “prepare an anticipated Construction Schedule” outlining the work to be accomplished by each subcontractor to insure completion of the project as outlined in the schedule.

In January and February, 1978, representatives of the contracting companies met and exchanged correspondence in an effort to reach an acceptable rewrite of those provisions of the BCI proposal which VMC found unacceptable.

Eventually, subcontract language acceptable to both sides was reached. Article IV remained essentially in the form BCI proposed. The most significant change was that Article XIV’s “no-damage-for-delay” clause was eliminated and replaced by carefully negotiated rider paragraph 32, which read as follows:

Should Subcontractor be obstructed or delayed in the commencement, prosecution or completion of the Work because of conditions attributable to Owner and which by the terms of the Prime Contract may be grounds for an extension of time or money damages, Subcontractor shall promptly make claim therefore in writing, and Contractor shall present said claim to the Owner. Contractor shall pay to Subcontractor whatever money damages or extensions of time allowed by Owner to Contractor * under the Prime Contract for said delay claim. [2] Contractor for just cause shall have the right at any time to delay or suspend the commencement or execution of the whole or any part of the Work without compensar tion or obligation to Subcontractor other than to extend the time for completing the Work for a period equal to that of such delay or suspension.
Nothing herein shall in any way preclude the right of Subcontractor to make claims against the Contractor for any un *925 reasonable length of delay of Subcontractor’s work within Contractor’s control or within the control of any other Subcontractor to Contractor.

The subcontract was executed on February 15,1978.' “Critical Path Method” schedules were prepared which appeared to accommodate all trades sufficiently to permit completion of the project within the limits of prime contract “Milestone 5.” But performance lagged. The delays prevented VMC from commencing stone installation at least until sometime in the fall of 1979— too late to meet the requirements of Milestone 5. Moreover, it is undisputed that the major portion of the work, known as the “extension building,” became ready for VMC’s stonework only in the spring (April or May) of 1980. 2

3. Status of the Job in November, 1979; Rescission

The parties agree that preparatory work on the major portion of the project, the extension building, was not sufficiently completed to allow commencement of stonework in the agreed-upon sequence until early-to mid-spring, 1980. BCI contends, however, that the lesser portion, the “central wing” 3 was ready for stonework in November, 1979.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ashcraft & Gerel v. Coady, Edward
244 F.3d 948 (D.C. Circuit, 2001)
Metric Systems Corp v. McDonnell Douglas Corp.
850 F. Supp. 1568 (N.D. Florida, 1994)
McGee Construction Co. v. Neshobe Development, Inc.
594 A.2d 415 (Supreme Court of Vermont, 1991)
Foundation Development Corp. v. Loehmann's, Inc.
788 P.2d 1189 (Arizona Supreme Court, 1990)
Granite Computer Leasing Corp. v. Travelers Indemnity Co.
702 F. Supp. 415 (S.D. New York, 1988)
State v. Silver
457 A.2d 463 (Supreme Court of New Jersey, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
520 F. Supp. 922, 29 Cont. Cas. Fed. 81,786, 1981 U.S. Dist. LEXIS 14044, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vermont-marble-co-v-baltimore-contractors-inc-dcd-1981.