McGee Construction Co. v. Neshobe Development, Inc.

594 A.2d 415, 156 Vt. 550, 1991 Vt. LEXIS 104
CourtSupreme Court of Vermont
DecidedMay 24, 1991
Docket89-551
StatusPublished
Cited by25 cases

This text of 594 A.2d 415 (McGee Construction Co. v. Neshobe Development, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McGee Construction Co. v. Neshobe Development, Inc., 594 A.2d 415, 156 Vt. 550, 1991 Vt. LEXIS 104 (Vt. 1991).

Opinion

Allen, C.J.

This action arises out of a contract dispute between Hugh McGee Construction Co. (McGee) and Neshobe Development, Inc. (Neshobe). Neshobe appeals from a jury verdict finding it to be the breaching party and awarding McGee damages in the amount of $20,000. McGee cross-appeals from the trial court’s denial of its V.R.C.P. 65.1 motion for enforcement of a separate judgment on stipulation against the security provided by Neshobe. On Neshobe’s appeal we affirm Neshobe’s liability and reverse and remand on damages. On McGee’s cross-appeal we reverse.

*552 In 1987, Neshobe undertook a condominium development project in Brandon, Vermont. The project was to proceed in three phases. McGee was hired to do the excavation, trenching, roadwork, and other sitework on Phase I on a cost-plus basis. The work on Phase I was completed in the summer of 1987. A balance of $15,000 remained outstanding on the Phase I contract after its completion.

On August 30,1988, McGee and Neshobe entered into a contract for Phase II of the project, under which McGee was to do work similar to that performed on Phase I. Phase II was split into part 1 and part 2, each consisting of six units. The work on part 1 was to commence on September 1,1988, and be substantially completed by October 1,1988. Work on part 2 would begin when sales of the units dictated, and be completed within four weeks. The Phase II contract between McGee and Neshobe was for a fixed sum of $76,000, $38,000 being allocated to each part.

McGee began its work on part 1, consisting of a duplex and a quad, on or about September 1. Soon thereafter it ran into unscheduled delays occasioned by Birch Hill Construction Co. (Birch Hill), the contractor responsible for the concrete work on Phase II. Birch Hill delayed work while waiting for the delivery of some additional concrete forms that it had ordered. There was also trouble with the setting of some footings, and one of the walls set by Birch Hill had to be torn down because it was defective. McGee was not able to backfill the duplex until October 3, and at that point it had not yet been able to begin its work on the quad’s walls because Birch Hill was still working on the footings. While it was a subject of dispute at trial, McGee testified through its principal, Hugh McGee, that it had been unable to do much of the roadwork, utility trenching, and other sitework because of the disruption in its schedule caused by the concrete delays.

On or about October 7, Hugh McGee went to the office of Rick Kaminski, president of Birch Hill and vice president of Neshobe, to express his concerns about the delay. Kaminski told him that a meeting with the principals of Neshobe would be scheduled for the 10th, and that if McGee had requests, to make them specific. The substance of the October 10 meeting is captured in the minutes of the meeting prepared by Neshobe, which both parties agree are accurate.

*553 At 7:25 am H. McGee enters the meeting and was asked by R. Kaminski to state his case and his reasons for calling the meeting in his own words. He states, he had stated that he cannot operate under the existing contract and will no longer proceed under the terms and conditions of that contract. R. Kaminski from Neshobe indicated that he is bound legally and morally by that contract and a new contract will not be allowed. Although, Change Orders will be allowed in reference to time extensions. H. McGee insisted that he will not continue under the terms of that contract and R. Kaminski stated, if he will not honor the terms and conditions of the contract (suggested) that H. McGee remove his equipment from the site and (suggested) that perhaps we will be better off having another contractor finish the project. H. McGee indicated that was acceptable to him and that would be exactly what he would do, remove his equipment from the site.

Neshobe sent a letter to McGee later in the day, containing these minutes and notifying McGee that if it was not on site on October 17, the contract would be terminated. A second letter to the same effect was sent on the 12th. McGee was not on site on October 17, and Neshobe hired a replacement. McGee received no payments under the Phase II contract.

McGee subsequently brought suit, alléging breach of the Phase II contract by delays attributable to Neshobe. McGee also sought recovery of the balance owed it on the Phase I contract. Neshobe counterclaimed, alleging that McGee’s failure to be on site on October 17 and its failure to abide by the contractual provisions for resolution of the dispute made McGee the party in material breach of the contract. During trial by jury, the parties entered into a stipulation in favor of McGee on the Phase I contract claim in the amount of $16,669.71. At the close of trial the jury found against Neshobe on its counterclaim, and returned a verdict in favor of McGee in the amount of $20,000. The court entered judgment on the jury verdict and judgment on the stipulation separately.

Following entry of judgment on the stipulation, McGee moved under V.R.C.P. 65.1 to enforce that judgment against an irrevocable letter of credit that Neshobe had used to provide security. The court denied the motion, holding that judgment on *554 the stipulation had not yet become final because of Neshobe’s pending post-trial motions in opposition to the judgment on the jury verdict.

Neshobe has appealed from the judgment on the jury verdict, and McGee has cross-appealed from the denial of its Rule 65.1 motion. We will address these appeals in turn.

I.

Neshobe contends that, by the terms of the contract, it was McGee’s cessation of work, not delays attributable to Neshobe, that materially breached the contract. Neshobe admits that it was responsible for many of the delays which interfered with McGee’s ability to perform the contract in a timely fashion. Neshobe also concedes in its brief that “[h]ad the contract not addressed delay, McGee could present a tenable argument that the delays occasioned by Neshobe were a substantial breach of contract, thereby justifying ... a termination of the contract.” Neshobe points, however, to provisions within the contract specifically addressing owner delay and resolution of claims arising from such delay, and argues that McGee’s failure to comply with these provisions left McGee in material breach of the contract.

It is axiomatic that parties can define their contractual relationship by the provisions employed in their contract. Contracting parties can define what will constitute a material breach of their contract. See Carter v. Sherburne Corp., 132 Vt. 88, 92, 315 A.2d 870, 873-74 (1974) (inclusion of “time is of the essence” clause magnifies the significance of delay); see also Burgess Construction Co. v. M. Morrin & Son Co., 526 F.2d 108,114 (10th Cir. 1975) (“unreasonable delay is a breach of an implied obligation not to hinder or delay the other party’s performance, in the absence of a contract clause contemplating and excusing the delay”), cert. denied, 429 U.S. 866 (1976). They can determine the damages that are recoverable in the event of a breach.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Op24-174_0.pdf
2025 VT 31 (Supreme Court of Vermont, 2025)
Stowe Aviation v. Agency of Commerce
Vermont Superior Court, 2024
Patten v. Tapogna
Vermont Superior Court, 2024
Gary Margolis v. Daily Direct LLC
2023 VT 20 (Supreme Court of Vermont, 2023)
Post and Beam Equity Group, LLC and Post and Beam of Mt. Snow, LLC
199 Vt. 313 (Supreme Court of Vermont, 2015)
Foti Fuels, Inc. v. Kurrle Corp.
90 A.3d 885 (Supreme Court of Vermont, 2013)
King v. Bishop
Vermont Superior Court, 2013
5860 Chicago Ridge, LLC v. United States
104 Fed. Cl. 740 (Federal Claims, 2012)
Smith 4-Lot Subdivision
Vermont Superior Court, 2011
Record v. Kempe
2007 VT 39 (Supreme Court of Vermont, 2007)
Chesery v. Zeno
Vermont Superior Court, 2004
Canton v. Graniteville Fire District No. 4
762 A.2d 808 (Supreme Court of Vermont, 2000)
Murphy v. Stowe Club Highlands
761 A.2d 688 (Supreme Court of Vermont, 2000)
Webb v. Navistar International Transportation Corp.
692 A.2d 343 (Supreme Court of Vermont, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
594 A.2d 415, 156 Vt. 550, 1991 Vt. LEXIS 104, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcgee-construction-co-v-neshobe-development-inc-vt-1991.