Smith 4-Lot Subdivision

CourtVermont Superior Court
DecidedSeptember 27, 2011
Docket244-12-09 Vtec
StatusPublished

This text of Smith 4-Lot Subdivision (Smith 4-Lot Subdivision) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith 4-Lot Subdivision, (Vt. Ct. App. 2011).

Opinion

STATE OF VERMONT ENVIRONMENTAL COURT

{ { In re Smith 4-Lot Subdivision Final Plat { (Appeal of Pauze) { Docket No. 244-12-09 Vtec { {

Decision on Motion to Approve and Enforce Settlement Agreement E. Francis Pauze, Jr. (“Appellant”) has filed a motion to approve and enforce a settlement agreement executed after court-ordered mediation in July 2010. The motion followed an appeal of municipal permits granted to Howard Smith (“Applicant”) for a four-lot subdivision in Poultney, Vermont. Applicant opposes the motion to approve and enforce, claiming that the Court lacks jurisdiction to enforce the settlement agreement and that the agreement is not binding. In this proceeding, Appellant is represented by John C. Thrasher, Esq. and Applicant is represented by Phyllis R. McCoy-Jacien, Esq.

Factual Background For the sole purpose of putting the pending motion in context, we recite the following facts, which we understand to be undisputed unless otherwise noted: 1. By his appeal to this Court, Appellant alleges that the Town of Poultney Design Review Board (“DRB”), in a decision issued November 18, 2009, failed to properly apply the Town of Poultney Subdivision Regulations (“Regulations”) to Applicant’s subdivision application and that this Court, in its de novo review, should deny the pending application. 2. Applicant’s proposed four-lot subdivision is of a 4.63± acre parcel located at 122 On the Green in Poultney, in the Rural Residential 1-Acre Zoning District. The parcel contains one existing house. 3. On July 29, 2010, as a result of court-ordered mediation, the parties reached an agreement resolving “all issues raised or that could have been raised” in this appeal. With the assistance of a mediator, the parties reduced their agreement to writing in a document entitled “Settlement Agreement.” The mediator filed a copy of this Settlement Agreement with the Court as an exhibit to the parties’ Alternative Dispute Resolution Report which is dated July 30, 2010 and was filed August 2, 2010.

1 4. Both parties and their respective attorneys signed the Settlement Agreement. 5. The Settlement Agreement states that the parties will file a stipulation so that the Court may enter an order affirming the DRB’s November 18, 2009 decision. See Settlement Agreement at 1. 6. The Settlement Agreement contains an “Acknowledgement of Arbitration” term, whereby the parties relinquish their rights to further litigate this dispute and commit to resolve any further disputes through arbitration. See id. at 2. 7. Paragraph 8 of the Settlement Agreement states that the parties will cooperate and sign all documents necessary to implement their Agreement. Id. 8. Paragraph 9 of the Settlement Agreement represents that the parties intend their Agreement “to resolve all issues raised or that could have been raised in” this pending appeal. Id. 9. The parties left the mediation session, after having signed the Settlement Agreement, with the understanding that further documents, incorporating the terms of the Agreement, would be completed by each party and filed with this Court, so that the Court could then sign an order disposing of this appeal based on those documents. 10. Within a matter of days after the parties signed the Settlement Agreement, Appellant contacted Applicant with suggested proposals to resolve outstanding landscaping and septic siting issues. See id. at 1.1 11. By December 7, 2010, Appellant made efforts to file the anticipated documents with the Court. 12. At a telephonic conference with the Court on March 31, 2011, Applicant first expressed his unwillingness to file the anticipated documents. Appellant thereafter filed the pending motion to have the parties’ Settlement Agreement enforced by this Court.

1 While it is not explicitly stated, these provisions make clear that the parties agreed to “negotiate in good faith the location and type of [additional landscaping] plantings,” Settlement Agreement at 1, ¶ 2, and would “jointly agree” on whether the “state approved replacement leach field for Lot 1 may remain where it is.” Id. at 1, ¶ 5. After the parties signed the Settlement Agreement, the Court inquired as to the status of these outstanding items. By letter dated August 26, 2010 and filed with the Court on August 30, 2010 (with a copy provided to Applicant’s attorney), Appellant’s attorney represented that the parties were working to resolve these final items, but that they might need until October 15 to complete the engineering and other preparatory work. During a status conference with the Court on October 18, 2010, both attorneys represented that the settlement was still moving forward.

2 Discussion Pending before the Court is Appellant’s motion to approve and enforce the Settlement Agreement that Appellant and Applicant executed after court-ordered mediation in July 2010. Appellant argues that the Agreement is enforceable by the Court because it was fully executed by both parties and their attorneys while the matter was part of the Environmental Division’s exclusive jurisdiction and because Appellant is now simply requesting the Court’s approval of that Agreement. Applicant argues, in opposition, that this Court lacks jurisdiction to enforce the parties’ Settlement Agreement. Applicant also asserts that the Agreement was not intended to be binding on the parties and that the Court cannot consider it so because the settlement has not yet been approved by the Court and incorporated into a judgment order. Applicant’s final argument is that Appellant delayed in complying with the terms of the Agreement, thereby breaching the Agreement. For the reasons detailed below, we reject Applicant’s three arguments and agree with Appellant. We conclude that this Court does have the authority to recognize and enforce the Settlement Agreement, which was reached by the parties in the course of court-ordered mediation; that the Agreement reached by the parties is binding upon them; and that the complained-of delays were not so significant as to constitute a breach of the parties’ Agreement.

I. Whether the Environmental Division has jurisdiction over the Settlement Agreement A trial court has jurisdiction to enforce a settlement agreement in an action still pending and active on the court’s docket, even when the terms of the agreement are not yet incorporated into an order. See Petition of Telesystems Corp., 148 Vt. 411, 412–13 (1987). However, the Telesystems Court established that when asked to enforce such an agreement, a trial court retaining jurisdiction must review the terms of the settlement agreement prior to enforcement, so as to “minimize the possibility that unconscionable terms of settlement are accorded the force and effect of a judgment order.” Id. at 413. We regard Telesystems as both confirming that this Court is an appropriate forum to enforce the challenged Settlement Agreement and requiring that the Court first review whether the Agreement’s terms are conscionable before enforcing it. The fact that this Agreement was a result of court-ordered mediation lends additional

3 support to our conclusion that we have jurisdiction to enforce this Agreement.2 We also note that this Court has jurisdiction to conduct any necessary evidentiary hearings to resolve disagreements related to an agreement’s formation or consummation. Turning to the Agreement itself, we note that it was entered into specifically to resolve the disputed issues that arose in this Environmental Division docket. The Settlement Agreement explicitly memorializes that the parties agreed to resolve the disputes in this appeal. The Settlement Agreement was included in a mediation report submitted on a form that is routinely used by this Court as part of mediation proceedings. See 12 V.S.A. § 5717(a)(1) (a signed mediation agreement is not privileged); 12 V.S.A. § 5718(a) (mediators may disclose a mediation report and signed mediation agreement).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Manosh v. Manosh
648 A.2d 833 (Supreme Court of Vermont, 1993)
Malladi v. Brown
987 F. Supp. 893 (M.D. Alabama, 1997)
Catamount Slate Products, Inc. v. Sheldon
2003 VT 112 (Supreme Court of Vermont, 2003)
Northern Aircraft, Inc. v. Reed
572 A.2d 1382 (Supreme Court of Vermont, 1990)
Webb v. LeClair
2007 VT 65 (Supreme Court of Vermont, 2007)
Bixler v. Bullard
769 A.2d 690 (Supreme Court of Vermont, 2001)
McGee Construction Co. v. Neshobe Development, Inc.
594 A.2d 415 (Supreme Court of Vermont, 1991)
In re Telesystems Corp.
535 A.2d 1277 (Supreme Court of Vermont, 1987)
Camara v. Camara
2010 VT 53 (Supreme Court of Vermont, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Smith 4-Lot Subdivision, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-4-lot-subdivision-vtsuperct-2011.