Patten v. Tapogna

CourtVermont Superior Court
DecidedSeptember 23, 2024
Docket23-cv-1857
StatusPublished

This text of Patten v. Tapogna (Patten v. Tapogna) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Patten v. Tapogna, (Vt. Ct. App. 2024).

Opinion

7ermont Superior Court Filed 08/21/24 Orleans UUnit

VERMONT SUPERIOR COURT eo CIVIL DIVISION Orleans Unit Case No. 23-CV-01857 247 Main Street Newport VT 05855 802-334-3305 www.vermontjudiciary.org

Adam Patten v. Mary Tapogna

FINDINGS, CONCLUSIONS, AND JUDGMENT

The present matter came before the Court for a bench trial on August 14, 2024. Both Plaintiff Patten's claims and Defendant Tapogna's counterclaims arise from a roofing job that Tapogna hired

Patten to perform in the winter of 2023 on her Lyndonville house. Patten seeks payment for $17,700,

which represents the outstanding balance on the remainder of the $35,200 that he claims is due and

owning on the roofing job that he performed in February and March of 2023. Tapogna has counterclaimed seeking damages for what she alleges is shoddy workmanship and consequential damages.

Based on the findings of the Court and the law of contract governing the parties' relationship, the

Court finds that Plaintiff Patten breached the agreement through his failure to properly install the roof, and Defendant Tapogna as the non-breaching party is entitled to damages that will put her in the position

that she would have been in if the contract had been fulfilled. Defendant Tapogna is also entitled to

damages for Patten's negligence arising from an unsecured ladder falling on Defendant's fence and causing

damages to screens and windows. Collectively, Defendant Tapogna 1s entitled to damages in the amount of $11,921.39. All other claims and requests for damages in the matter are denied as a matter of fact and law.

Findings of Fact

On July 5, 2022, Plaintiff Adam Patten delivered an estimate to Defendant Mary Tapogna that outlined a proposed scope of work. Patten, working under the business name A.C.T. Roofing, would

replace Tapogna's asphalt shingle roof with a corrugated metal roof. The estimate had one single cost item for the expected roof demolition and replacement of $33,600 and a second cost for the roll off dumpster

that would have to be rented of $1,600. In the notes, Patten indicated that he would be taking the roof

down to the decking and removing all shingles, underlayment, and drip edges. He indicated that he would

Ordet Page 1 of 8 23-CV-01857 Adam Patten v. Mary Tapogna inspect the decking for rot. He indicated that decking replacement, if necessary, would be an extra charge. He also stated that he would put a synthetic layer on the entire roof and install new drip edges.

Tapogna agreed to this scope of work and hired Patten to perform the work. Nothing in the estimate indicates that Patten would not perform work on certain areas, and the estimate is silent on flashing or counterflashing. It also does not make reference to a widow’s walk section of the roof. Patten admits that he did not climb onto the roof at the time that he generated the estimate and that his scope of work was based solely on his visual observations from the ground. The parties did not reduce their agreement to a written contract. The estimate itself does not include space for Tapogna to accept the estimate or any language indicating that parties intended to be bound by any further specific terms or conditions beyond the estimate. Based on the evidence and testimony of the parties, the Court finds that the estimate loosely describes the scope of work that Patten was offering to perform and the price that he was offering. This price is consistent with the amount that Patten seeks in this litigation minus the initial payment made by Tapogna at the start of Patten’s work.

In February of 2023, Patten began work at Tapogna’s Lyndonville house. Tapogna paid Patten an initial deposit of $17,500, which was 50% of the amount agreed upon for the work. Patten removed and took off all the existing asphalt shingles and disposed of them in a roll off dumpster that was delivered to the site and removed at the end of the project. Patten then installed corrugated metal roof on the house. Patten did not replace any of the subroof’s decking board but simply laid the synthetic material over the existing decking and screwed the metal into the existing decking. Patten put the corrugated panels on the entire roof, except for a porch, which he claims Tapogna did not want him to finish, and on the widow’s walk at the top of the house, which would require a rubber roof due to its shape and location. Patten claims that he informed Tapogna that he did not install rubber roofs and that she would have to find a separate contractor to deal with this section. Tapogna states that this was not her understanding. The Court finds Patten’s testimony credible, but it also finds that the original estimate and scope of work did not include provisions to install a rubber roof, and even if Patten would have installed it, it would have been a change to the contract and required additional consideration as it went beyond the parties’ agreed upon scope.

In March of 2023, Patten had largely completed his work and had removed his equipment and tools. While Patten claims there were a few follow-up items to complete, he agreed that his work was done. Around this time, Tapogna informed him of her dissatisfaction, and she informed him that he was not allowed back onto the property. Shortly thereafter, she hired John Calamaio to do an inspection of the property. Calamaio did the inspection and produced a report detailing his findings. While Calamaio is not Order Page 2 of 8 23-CV-01857 Adam Patten v. Mary Tapogna a roofer or contractor, he is a licensed property inspector, and his report is derived from his actual observations and training. The Court finds the report to be credible and accurate in detailing the issues with the roof that Tapogna has incorporated into her answer and counterclaims.

Tapogna also hired Bob Barnes, a concrete contractor to inspect the roof. His findings mirrored Calamaio’s, but he did not produce a report or do work on the property.

After Calamaio’s and Barnes’ inspections, Tapogna contracted with Justin Ouellette, doing business as North Ridge Renovations. Ouellette conducted a more extensive review of the roof. His findings and observations are consistent with Calamaio’s and Barnes’. Tapogna contracted with Ouellette to have him repair the roof, but Ouellette came to the conclusion that the entire roof needed to be removed as it needed a base of plywood underneath to support any roofing structure and to address the dimpling and unanchored screws that he found on the Patten-installed roofing panels.

Ouellette performed this work in early 2024. The total for this work came to $57,500, and it included removal of the old roof ($6,500), installation of plywood on all surfaces of the sub-roof repair ($15,000), purchase and installation of a new roof ($27,500), replacement of flashing around chimneys and brick work ($5,500), and installation of a rubber roof on the widow’s walk area ($3,000). Following Ouellette’s work, the leaking issue ceased at Tapogna’s house, and Tapogna reports that she is satisfied with the new roof.

Based on the testimony of Defendant’s experts and as shown in the photographic exhibits, there were several issues with Patten’s installation.

First, the existing decking was insufficient to support the metal panels. The decking, originally installed in the 19th century had gaps and missing segments that left a number of screws, used to secure the metal panels, unanchored. The evidence indicates that Patten attempted to fix this issue with caulking, but both Justin Ouellette and John Calamaio, who examined Patten’s work, credibly opined that it was insufficient, that many screws lifted out at the slightest tug, and they would eventually give way leading to leaking and failure on these roof panels.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Evarts v. Forte
376 A.2d 766 (Supreme Court of Vermont, 1977)
Isbrandtsen v. North Branch Corp.
556 A.2d 81 (Supreme Court of Vermont, 1988)
Tour Costa Rica v. Country Walkers, Inc.
758 A.2d 795 (Supreme Court of Vermont, 2000)
McGee Construction Co. v. Neshobe Development, Inc.
594 A.2d 415 (Supreme Court of Vermont, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Patten v. Tapogna, Counsel Stack Legal Research, https://law.counselstack.com/opinion/patten-v-tapogna-vtsuperct-2024.