McDowell-Purcell, Inc. v. Manhattan Construction Co.

383 F. Supp. 802, 1974 U.S. Dist. LEXIS 9330
CourtDistrict Court, N.D. Alabama
DecidedMarch 25, 1974
DocketCiv. A. 72-G-823-J
StatusPublished
Cited by3 cases

This text of 383 F. Supp. 802 (McDowell-Purcell, Inc. v. Manhattan Construction Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDowell-Purcell, Inc. v. Manhattan Construction Co., 383 F. Supp. 802, 1974 U.S. Dist. LEXIS 9330 (N.D. Ala. 1974).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

GUIN, District Judge.

This cause coming on for trial and the court having heard the evidence of the witnesses ore tenus and considered the exhibits introduced herein, the court enters the following findings of fact and conclusions of law:

(1) On to-wit the 9th day of May, 1969, the parties hereto entered into the subcontract agreement identified during the trial of this cause as Plaintiff’s Exhibit 1, by virtue of which the plaintiff, McDowell-Purcell, Inc., (sometimes hereinafter referred to as “McDowell” and also as “subcontractor”) stipulated as follows:

“To furnish all materials (except reinforcing steel materials) labor, equipment and supplies including all applicable taxes and insurance required for the concrete caissons at the following unit prices; also the furnishing and setting of a 24" pipe casing all in accordance with Plans and Specifications prepared by Southern Services, Inc. for the Alabama Power Company, Substructure Construction, Gorgas Steam Plant — Unit No. 10, Inquiry No. AP-7923 — ”

The plans and specifications relating to substructure construction at Gorgas Steam Plant hereinbefore mentioned were identified as Plaintiff’s Exhibit 2, and the court concludes in determining the rights of the parties herein that due consideration and substantial significance must be given to the obligation of the defendant, Manhattan Construction Company (hereinafter sometimes referred to as “Manhattan” and also as “prime contractor”) to the Alabama Power Company thereunder, including but not limited to the following excerpts therefrom :

A. “SECTION I
GENERAL
SCOPE
These specifications are intended to cover the following items of work in connection with the construction of the Purchaser’s Gorgas Steam Plant —Unit No. 10. The Contractor shall perform all operations of work required and shall furnish all supervision, labor, equipment, tools, plant, and all materials (* * * * * *) *804 required to satisfactorily complete the specified work.
* * * * * *
Removal of ground water and surface water as required to keep the excavations sufficiently dry to allow construction to progress as scheduled.
****** »
B. “SECTION II
EARTHWORK, ROCK WORK AND UNWATERING
SCOPE
The Contractor shall perform the items of work specified below:
******
Removal of surface and ground water, and keeping working areas sufficiently dry to allow construction to progress as scheduled.
* * * * * *
UNWATERING OF GROUND WATER
In order to perform the excavation for the powerhouse, the water passages, intake-discharge structure and chimney foundation, the removal of ground water will be required.
* * *
The unwatering system for removal of ground water will have to be installed during excavation operation.
******
The Contractor will be responsible for pumping out the existing pond and shall also be responsible for keeping the excavated areas workably dry and he shall furnish, install, operate, maintain, and remove all unwatering equipment required to perform his work.
* *****
SURFACE DRAINAGE
The Contractor shall be responsible for surface drainage water in the areas in which he is working, and all pumping required shall be done by the Contractor at the Contractor’s expense. Cuts and fills shall be made in such a manner as to avoid pockets and to allow water to run off without ponding. All temporary drainage facilities for surface water shall be furnished by the Contractor at the Contractor’s expense. *****.
******
UNWATERING OF GROUND WATER
Each Bidder shall quote a total price for furnishing all equipment and performing all operations of work required for pumping out the existing pond after the earth dike is placed and for installing, maintaining, operating and removing the unwatering system. * * *
(See Plaintiff's Exhibit 2, Pages 2-1, 2-4, 2-5, and 2-9.)

In respect to the last quoted requirement, the specifications further show that Manhattan quoted the lump sum price of $26,609.00 “For pumping out pond and unwatering as specified.” Plaintiff’s Exhibit 2 further shows that the prime contractor quoted unit prices for caissons and other pipe casings approximately twenty per cent (20%) in excess of the prices for said work which it obtained from the plaintiff. (See Page 3 of the specifications.) In other words, defendant contracted with the owner for a profit of twenty per cent (20%) on the work which it had subcontracted to McDowell. According to the evidence, Manhattan was paid by the Alabama Power Company, with whom it had contracted for “unwatering” and the caisson work which was performed by McDowell. In further connection with its “unwatering” obligation, it is shown on page 14 of the specifications that the defendant proposed to subcontract this phase of the work to John W. Stang Corp. of St. Petersburg, Florida, but under the evidence the same was not performed by Stang, being undertaken by Manhattan itself.

*805 C. “SECTION III
ROCK SUPPORTED FOUNDATIONS FOR POWERHOUSE
SCOPE
This section of the Specifications is intended to cover the furnishing of all materials, equipment, labor and supervision required for drilled piers (concrete caissons) and fill concrete as required to support the Unit No. 10 powerhouse building for Gorgas Steam Plant; * -x- * * *
CAISSONS
* -» -X. Foundations under the powerhouse shall be drilled piers (concrete filled caissons) down to-sound rock to permit inspection of the bearing surface. These shall be of various sizes from 3' to 10' in diameter as indicated in the proposal form and as will be shown on the Purchaser’s approved drawings. It is estimated that approximately 300 caissons will be required. * * *.
* * *. Each caisson shall have a protective casing, the bottom of which shall be seated in rock and sealed to prevent seepage of water and then thoroughly cleaned.
* * -X -X- * -X-
Prior to placing concrete for caissons, the caisson excavation shall be clean and free of any foreign matter and water. No concrete shall be placed for caissons until after each is approved by the Purchaser’s Superintendent.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McKinney Drilling Co. v. Collins Co., Inc.
517 F. Supp. 320 (N.D. Alabama, 1981)
McDowell Inc. v. Manhattan Construction Company
515 F.2d 1181 (Fifth Circuit, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
383 F. Supp. 802, 1974 U.S. Dist. LEXIS 9330, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdowell-purcell-inc-v-manhattan-construction-co-alnd-1974.