Edward E. Morgan Co. v. United States

230 F.2d 896, 60 A.L.R. 2d 455
CourtCourt of Appeals for the Fifth Circuit
DecidedFebruary 23, 1956
DocketNo. 15650
StatusPublished
Cited by16 cases

This text of 230 F.2d 896 (Edward E. Morgan Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edward E. Morgan Co. v. United States, 230 F.2d 896, 60 A.L.R. 2d 455 (5th Cir. 1956).

Opinions

JONES, Circuit Judge.

The appellants, Edward E. Morgan Company, Inc., and Jones & Gillis, Incorporated, herein referred to as the prime contractors, entered into a contract with the United States of America for the construction of runway, taxiway and parking apron extensions at the Gray Air Force Base near Killeen, Texas. A construction bond was given by the prime contractors with the appellant, United States Fidelity and Guaranty Company, as surety. The contract was on a unit price basis. A schedule of designations and unit prices was annexed to and made a part of the contract. In this schedule there was included as Item No. 4, Crushed Stone Base Course of an estimated quantity of 30,500 cubic yards at a price of $2.17 per cubic yard. Included as paragraph 7-14 of the specifications of the contract was the provision:

“The unit of measurement for base course shall be the cubic yard, measured in place and computed by the average end-area method, for the quantity of completed and accepted base course as determined by the contracting officer.”

Following the above we find this provision:

“The quantities of base course, determined as specified in paragraph 7-14, will be paid for at the contract unit price for ‘Crushed Stone Base Course’, which payment shall constitute full compensation for the construction and completion of the base course, including the preparation of the subgrade, the furnishing of all materials, supplies, equipment, and tools; the handling, manipulating, placing, shaping, compacting, rolling, finishing, and correcting unsatisfactory areas; the furnishing and applying of water; and the furnish[899]*899ing of all other labor and incidentals necessary to complete the work required by this section of the specifications.”

The use plaintiff, W. 0. Pelphrey, whom we will call the subcontractor, submitted a letter offer dated April 7, 1953, to the prime contractors in which he proposed:

“ * * * to furnish all equipment, tools, labor, and incidentals necessary to excavate and crush a minimum of 40,000 C. Y. [cubic yards] of Edwards Limestone * * * ^ y0Ur option, the material will be stockpiled or delivered to your handling units from our bins, provided the hauling units you choose can clear our bins without alteration thereto. * * * This work to be performed in accordance with specifications and to meet the screen analysis of the specifications. * * *
“For the above work we quote 1.01 per C. Y. Partial payment to be made by the 10th of each month. Final payment 15 days after completion of job.”

By a letter dated April 13, 1953, from the prime contractors to the subcontractor, the offer was accepted. The pertinent portions of the acceptance are:

“We herewith accept your proposal of April 7, 1953, to crush the rock for the extension of the Gray Air Force Base Runway and Taxiways.
******
“You will also be governed by the same regulations, as to wages, etc., that we are under the terms of our contract.”

Although not mentioned in either of the letters comprising the contract between the prime contractors and the subcontractor, some of the rock crushed by the subcontractor was used in the construction of a perimeter road for which the prime contractors were paid on a square yard basis. Some of the rock was used in construction of or at a fire station but there is no evidence showing how much was so used nor the manner of computing the prime contractors’ compensation. The rock for the perimeter road was an extra under the prime contract and probably the same was true of that used at the fire station.

The prime contractors employed D. E. Goetes (sometimes in the record spelled “Goates” and as “Goetz”) to haul the rock crushed by the subcontractor to the site of the work in dump trucks, each of which, the evidence showed, held five cubic yards. Goetes was paid for hauling 3090 cubic yards to the perimeter road and fire station, and 44,890 cubic yards to the Gray Air Force Base Project. By dump truck measurement the subcontractor crushed and delivered 47,980 cubic yards of stone.

On June 26, 1953, the subcontractor submitted to the prime contractors an estimate for the period through June 25, 1953, based upon the crushing of 30,730 cubic yards of stone. On July 1, 1953, the prime contractors sent to the subcontractor an estimate showing 14,863 cubic yards of stone for runways and taxiways and 2,000 cubic yards of stone for the perimeter road, which estimate was only for the period ending June 15, 1953. This estimate was transmitted to the subcontractor by a letter from the prime contractors advising that the figures were taken from the estimate of the U. S. Engineers and were approximate only. The letter stated that the work for the period June 15th through the 25th would come through on the July 25th estimate. The records of Goetes show that he hauled 15,310 cubic yards through June 13, 1953. If to this we add the 1,655 cubic yards which the subcontractor’s books show were delivered on June 15, 1953, we have 16,965 cubic yards, a figure not greatly in excess of the 16,863 cubic yards of the U. S. Engineers’ approximate figures. With the letter was a check for $17,031.63 in payment for crushing 16,863 cubic yards of stone at $1.01 per cubic yard.

The work of the subcontractor was completed on July 11, 1953. On July 24, [900]*9001953, he billed the prime contractors with mining and crushing 47,980 cubic yards of stone at the contract price of $1.01, or $48,459.80, upon which he credited the payment of $17,031.63, leaving a balance, as shown by his invoice, of $31,-428.17. The army engineers estimated that there were 31,187 cubic yards of crushed stone in the runways, taxiways and parking aprons, and 2,415 cubic yards of crushed stone in the perimeter road, or a total of 33,602 cubic yards, measured in place as required by the contract between the United States and the prime contractors. The prime contractors, using the “in place” measurement, determined the total amount payable under the subcontract to be $33,938. Payment was tendered on this basis. Subsequently the prime contractors offered payment based on 40,000 cubic yards of crushed stone, the minimum quantity as specified in the letter agreement. The tender was refused. For the amount claimed by the subcontractor credit being given for the interim payment, action was brought under the Miller Act, 40 U. S.C.A. § 270a et seq.

The subcontractor had a check of the prime contractors for $22,374.44 which bore a notation that it was in full settlement. He asked the prime contractors for authority to use the check without prejudice. The request was refused. The check was tendered into the registry of the court. During the trial and while the subcontractor was on the stand as a witness in his own behalf he endorsed the check so as to make it payable to the clerk.

Considerable evidence was introduced, including testimony that there was a custom or usage in Texas that crushed stone was bought and sold by loose truck measurement. Instructions were requested by the prime contractors that doubts as to the meaning of the term “C. Y.” or “cubic yard” should be resolved against the subcontractor, and that the jury should find for the prime contractors unless the subcontractor proved that both parties intended that the subcontractor should be paid by loose truck measurement and not by U. S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
230 F.2d 896, 60 A.L.R. 2d 455, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edward-e-morgan-co-v-united-states-ca5-1956.