Díaz & Morey, Inc. v. Báez

87 P.R. 452
CourtSupreme Court of Puerto Rico
DecidedFebruary 26, 1963
DocketNo. 87
StatusPublished

This text of 87 P.R. 452 (Díaz & Morey, Inc. v. Báez) is published on Counsel Stack Legal Research, covering Supreme Court of Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Díaz & Morey, Inc. v. Báez, 87 P.R. 452 (prsupreme 1963).

Opinion

Mr. Justice Ramírez Bages

delivered the opinion of the Court.

Appellants Enrique Báez and Juan Lube were awarded by the Housing Authority of Puerto Rico the execution of the project “La Playa” in Arecibo, Puerto Rico, identified with No. UR PR 5-5, by a bid of $94,857.65. Later appellants subcontracted to appellee Diaz & Morey, Inc., the electrical work of said project and to that effect the parties signed a letter-contract on August 12, 1955, in the following terms:

“Díaz & Morey, Inc. and Associates Contractors Electrical Engineers
August 12, 1955
Messrs. Báez & Lube
Engineers-Contractors
Hato Rey, Puerto Rico
[454]*454Gentlemen:
Confirming our conversation of today with Mr. Enrique Báez, we promise to carry out the electrical work of the project in Arecibo, of the Housing Authority of Puerto Rico pursuant to our quotation of July 14, 1955, for the sum of $12,500, excluding all concrete work that might be necessary.
Our work is subject to the drawings and specifications of the Housing Authority.
The conditions of payment shall be the same established in the contract for the project with the Authority.
Cordially yours,
Díaz & Morey, Inc.
(Sgd.) M. Morey
M. Morey-Treasurer.”

Appellee received $10,000 under said subcontract and, when it was denied the balance of $2,500 it filed a complaint against appellants and the Fireman’s Bond & Indemnity Co., the lirm which had furnished the payment bond in relation with the project. It alleged that they had finished the electrical work pursuant to the specifications, that the same has been accepted by the aforesaid Authority and by the Puerto Rico Water Resources Authority and requested that appellants be ordered to pay it $2,500 which they still owed, plus $500 for attorney’s fees. Appellants raised the defense that the subcontract in question required that the work be realized pursuant to the plans and specifications of the Housing Authority and that the conditions of payment would be the same established in the principal contract; that appellee failed to execute work worth $2,100, which amount the aforementioned Authority deducted from appellants and that, on the other hand, the latter carried out work for $900 which was supposed to be carried out by appellee, which makes a total of $3,000; and by virtue thereof, in case it were decided that appellee's work was agreed at the sum of $12,500, appellants counterclaimed the aforesaid amount of $3,000 and requested the dismissal of the complaint and the granting [455]*455of the counterclaim, ordering appellee to pay appellants the sum of $500,

The District Court, San Juan Part, on May 31, 1900 dismissed the complaint in this case and imposed costs and $150 attorney’s fees on appellee, refusing to provide anything whatsoever respecting the claim of $900 for the work carried out by appellants and which corresponded to appellee. The aforesaid court concluded that the conditions of payment in the main project of “La Playa” were on the basis of unit work executed, that is, that the final liquidation would be made on the basis of the work actually performed; that the subcontract of August 12, 1955 required that the electrical work of the project be executed for the sum of $12,500 . . subject to the plan» and specification» of the Authority. .. ” and that “the conditions of payment ... would be the same established, in its contract for the project with the Authority”; that the conditions of payment between the contracting parties were the same as those imposed by the Housing Authority on appellants; that the witness Osvaldo Hidal-go, chief engineer of the aforesaid Authority, showed that a reduction of work amounting to $2,153.48 had been made from the original estimate of the electrical part of the project and that appellee performed additional work not contemplated by the original estimate for the sum of $55; that the appellee did not show that it had performed work for $12,500; that the parties agreed that their manner and conditions of payment were based on the work actually done and that the parties were bound and subject to the final liquidation made by the aforesaid Authority without taking into consideration the partial advanced payments received by appellants, as well as by appellee, as provided by the specifications, citing to that effect § 108 concerning payments to contractors for the project “La Playa” of the general conditions of the main contract between appellants and the Authority in question.1

[456]*456Appellee appealed from that judgment to the Superior Court, San Juan Part, but appellants did not appeal from the decision of the District Court which refused to make any provision respecting their claim for work performed which corresponded to appellee. The Superior Court, by judgment of May 11, 1961 reversed the judgment appealed from and rendered another ordering appellants to pay appellee the sum claimed of $2,500, plus costs, and the sum of $200 for attorney’s fees. The aforesaid court decided that the District Court erred in dismissing the complaint in this case, pursuant to the interpretation given to the subcontract by appellants, because that interpretation is manifestly untenable; that “there can be no doubt that the parties agreed to a lump sum, which was specific and determined by the subcontracted work. To give the last paragraph of the subcontract the interpretation sought by appellees and with which the District Court was in agreement would mean (1) to disregard the price expressly agreed upon, and (2) to set up in the subcontract, by way of interpretation, a different price—the unit price of the original contract—which could not have been the intention of the parties because both exclude each other. It is impossible to disregard what was expressly agreed upon and to interpolate in the subcontract what it does not state: that the unit price of the contract with the Housing Authority were incorporated therein. The only sensible interpretation which may be given the last paragraph of the subcontract [457]*457is that appellant would receive the advanced payments, for the account of the price agreed upon, in the same manner agreed by appellees in their contract with the Housing Authority.”

The reversal of the judgment of the District Court in this case is not based on the fact that it erred in its findings of fact but that it did not correctly interpret the provisions of the two contracts involved in this case.

The electrical part of the main contract respecting the project “La Playa” is described in the printed specifications which is part of the contract. The Authority pointed out in said form the different items of the work, the amount of material and equipment estimated, and provided therein several blanks for the bidder to fill out with his quotations for unit prices of equipment and material, including labor, materials, bonds, insurance, general expenses, and profit, pursuant to the aforesaid. Appellants’ proposal for the electrical work amounted to $14,673.50, on the basis of the amounts estimated for equipment and material.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guerini Stone Co. v. P. J. Carlin Construction Co.
240 U.S. 264 (Supreme Court, 1916)
Arrow Sheet Metal Works, Inc. v. Bryant & Detwiler Co.
61 N.W.2d 125 (Michigan Supreme Court, 1953)
Moses v. Edward H. Ellis, Inc.
72 A.2d 856 (Supreme Court of New Jersey, 1950)
Edward E. Morgan Co. v. United States
230 F.2d 896 (Fifth Circuit, 1956)
Noyes v. Butler Bros.
108 N.W. 839 (Supreme Court of Minnesota, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
87 P.R. 452, Counsel Stack Legal Research, https://law.counselstack.com/opinion/diaz-morey-inc-v-baez-prsupreme-1963.