Arrow Sheet Metal Works, Inc. v. Bryant & Detwiler Co.

61 N.W.2d 125, 338 Mich. 68
CourtMichigan Supreme Court
DecidedNovember 27, 1953
DocketDocket 52, Calendar 45,949
StatusPublished
Cited by11 cases

This text of 61 N.W.2d 125 (Arrow Sheet Metal Works, Inc. v. Bryant & Detwiler Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arrow Sheet Metal Works, Inc. v. Bryant & Detwiler Co., 61 N.W.2d 125, 338 Mich. 68 (Mich. 1953).

Opinion

Carr, J.

The question at issue in this case concerns the right of the plaintiff to prosecute an action against defendant for damages for alleged breach of contract. The facts are not materially in dispute. In 1949 the Ford Motor Company entered into general contracts, 4 in number, for the construction of a stamping plant at or near Hamburg, New York. The first of said contracts covered the foundation work, the second the structural steel work, the third the furnishing and installation of boilers and materials and labor incident thereto, while the fourth contract was let to the defendant in this case and covered practically all of what was required to be done in the completion of the structure and not embraced within the terms of the first 3 contracts.

The contract between the Ford Motor Company, hereinafter referred to as the owner, and defendant, as one of the general contractors, was executed November 17, 1949. Thereafter defendant entered into negotiations with the plaintiff and on or about February 21, 1950, a written agreement in the form of an offer and acceptance thereof was finally executed, such subcontract covering roofing, sheetmetal work, and installation of metal siding on the stamping, plant. It was provided in the agreement that the work was to be done in accordance with plans, and specifications prepared by named architects and engineers. Copies of such plans and specifications *71 were incorporated in the general contract between the owner and the defendant. They indicated in detail the manner in which the construction work was to be performed.

Under the terms of the contract between the parties to this case plaintiff was to receive the sum of $380,000, payable in monthly installments, for the work that it undertook to do. It is not disputed that such sum was paid. Plaintiff claimed, however, that it had performed certain extras at the request and for the benefit of defendant, for which it was entitled to additional compensation. The parties were unable to agree with reference to the amount to which plaintiff was entitled because of such additional items. This case was thereupon instituted, the declaration seeking recovery for the doing of the extra work not covered by the written contract and also damages based on the theory of alleged breach of contract on defendant’s part. Plaintiff’s right to recover additional compensation for work done was submitted to the jury under 4 special questions, in answer to which the amount of recovery on each item in dispute was specified, and judgment in plaintiff’s favor was entered accordingly. Prom that portion of the final judgment neither party has appealed.

Plaintiff’s claim for damages on the theory of breach of contract was set forth in count 4 of its declaration, which alleged that by virtue of the contract between the owner and defendant and also the contract between plaintiff and defendant it was the duty of the latter “to organize the project, to provide proper supervision and coordinate the work of the various subcontractors, and to order and arrange delivery of materials” to the end that the plaintiff’s agreement might be performed within a reasonable time. It was further averred that it. was defendant’s duty to keep roadways leading to-the construction project free from snow, ice, and' *72 other obstructions, in order to permit delivery of materials and the movements of personnel, and that defendant was also required to provide electric current for temporary power and light so that plaintiff’s tools and equipment might be operated without interruption. It was alleged that defendant failed to perform the said duties, and that because-of delays resulting from such failure plaintiff’s costs were increased and it was deprived of a profit that otherwise it might have earned.

The contract between plaintiff and defendant did not set forth in specific terms the duties that plaintiff claims defendant owed to it and failed to perform. In support of its position plaintiff relies-on the reference in said contract to the plans and specifications as contained in the general contract between defendant and the owner. It is urged in this regard that such reference incorporated into the subcontract, for the benefit of plaintiff, certain obligations that defendant had assumed in connection with the performance of its work under the-general contract. The averments of count 4 of the-declaration have reference principally to the following provisions set forth in the “general conditions” contained in the general contract:

“The work shall be carried to completion with utmost speed.
“Immediately upon award of the contract, the-contractor shall prepare and submit a definite progress schedule and furnish same to the owner for approval. The contractor shall execute all portions of the work in accordance with the approved, schedule.
“If necessary, in order to complete the work within the time stated in the contract, or if, in the opinion of the owner, it becomes necessary, in order' to maintain the progress schedule, for the contractor to> work after regular hours, the contractor shall, .im *73 mediately upon request, work such overtime, additional shifts, Sundays or holidays, as may be required, without additional cost to the owner. * * *
“Should the progress or completion of the several portions or the whole of the work be delayed as the result of fire, lightning or other casualty for which the contractor is not responsible, or should the contractor be delayed in the prosecution of the work through the fault of any other contractor employed by the owner, or because of the owner, the time of completion of such portion or portions of the work directly affected by such delay shall, unless the owner elects to terminate the contract as provided under the heading ‘Termination by Owner’, be extended for a period equivalent to the time lost, which period shall be determined by the owner. No such extension shall be granted unless the contractor, within 48 hours of the occurrence of the cause of such delay, notifies the owner, in writing, that such cause has occurred and makes written application for the specific extension of time claimed to be necessitated by reason of such cause.
“The contractor shall have no claim against the ■owner for damage, loss, expense or other compensation on account of any such delays, except as specifically otherwise provided under the heading ‘Suspension of Operations.’ * * *
“The total electric service that the power company ■can make available to the project for construction purposes is 1900 KVA at 4160 volts. This service has now been installed for the foundation contractor to meet his requirements and those of the structural :steel contractor.
“Any portion of this present supply of current for power and light that may be required by the general contractor, over and above the needs of the foundation and structural steel contractors, shall he obtained by him through direct negotiations with the foundation contractor.
“It shall be understood that the general contractor shall furnish, install and maintain the electric serv *74

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dynamic Construction Co. v. Barton Malow Co.
543 N.W.2d 31 (Michigan Court of Appeals, 1995)
Berkel & Co. Contractors v. Christman Co.
533 N.W.2d 838 (Michigan Court of Appeals, 1995)
Omega Construction Co. v. Altman
382 N.W.2d 839 (Michigan Court of Appeals, 1985)
Hinshaw v. Blue Cross & Blue Shield
369 N.W.2d 221 (Michigan Court of Appeals, 1985)
SCHULL CONSTRUCTION COMPANY v. Koenig
121 N.W.2d 559 (South Dakota Supreme Court, 1963)
Díaz & Morey, Inc. v. Báez
87 P.R. 452 (Supreme Court of Puerto Rico, 1963)
Reed v. Long
204 F. Supp. 16 (E.D. Michigan, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
61 N.W.2d 125, 338 Mich. 68, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arrow-sheet-metal-works-inc-v-bryant-detwiler-co-mich-1953.