Avery v. Board of Supervisors

39 N.W. 742, 71 Mich. 538, 1888 Mich. LEXIS 649
CourtMichigan Supreme Court
DecidedOctober 12, 1888
StatusPublished
Cited by25 cases

This text of 39 N.W. 742 (Avery v. Board of Supervisors) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Avery v. Board of Supervisors, 39 N.W. 742, 71 Mich. 538, 1888 Mich. LEXIS 649 (Mich. 1888).

Opinion

Long, J.

At a session of the board of supervisors of Ionia county, in 1882, a committee was appointed to present a resolution at the January session of said board, in 1883, submitting to the voters of the county the proposition to build a court-house. On January 11, 1883, this committee made a report to the board of supervisors, and on the same day a resolution was passed by the board appointing a committee of three as a building committee. This committee are the three defendants in this case. These defendants at once caused plans and specifications to be prepared, and advertised for proposals to build the court-house; requiring the party who was the successful bidder to give bonds, according to the terms of the resolution of the board, in the sum of $30,000, for the faithful performance of the contract. The specifications provided, among other things, as follows:

Sealed bids will be received up till 12 o’clock noon on the 1st day of October, 1883, at the office of the probate judge of Ionia county. They must be upon blanks furnished by the committee, and accompanied by a guaranty, which must be signed by the bidder and acceptable surety or sureties. The successful bidder will be required to furnish an acceptable bond in the sum of $30,000 for the faithful performance of the same.”

The bids were received and opened, and Claire Allen was the successful bidder. On November 1, 1883, the committee entered into a contract with Claire Allen for the building of the court-house. Annexed to this contract, and executed at the same time, was the bond as [540]*540provided . in the notice. Plans and specifications were made a part of the contract, and were signed by the contracting parties.

Shortly after the execution of this contract, and sometime in December, 1883, the plaintiff, William E. Avery, made an oral contract with Claire Allen, the contractor, to furnish cut stone for the court-house according to the plans and specifications, which were a part of the original contract between Claire Allen and the building committee. On December 8, $1,000 was paid to Avery on the order of Claire Allen, on this contract. On February 11, 1884, Avery and Allen reduced their contract to writing. Avery was paid according to the terms of this contract between him and Allen, in estimates from time to time, until the last payment of $1,165.55. This was June 15, 1885. He received an order from Claire Allen directed to O. Waterbury, Superintendent of the Building Committee of the Ionia County Court-house, Ionia, Mich.,” for the above amount. This order was not accepted in writing by Waterbury, and, after retaining it for some time, Waterbury returned it to Avery. This claim of Avery was presented to the board of supervisors at the January session, 1887, and the board absolutely refused to pay it.

At the same session the board of supervisors passed the following resolution :

“Resolved, that the county of Ionia, and the board of supervisors thereof, shall and do hereby agree to save harmless the building committee heretofore appointed, to wit, Ohauncey Waterbury, Levi Shotwell, and Edson P. Gifford, and the members thereof aforesaid, from all suits and proceedings, claims and demands, growing out of the erection of the court-house, or in any way relating thereto.”

On March 29, 1887, this action was brought against the board of supervisors of Ionia county and the committee. [541]*541The plaintiff seeks to recover against the committee, because they neglected to require a bond to protect labor and material-men, and joins the county as defendant, because the board of supervisors passed the resolution above set forth.

The declaration in this cause alleges:

1. The adoption of a resolution, fpr submission to the voters of Ionia county a proposition to raise $45,000, with which to build a county court-house.

2. That in case the resolution was carried, it was provided that Ohauncey Waterbury, Edson P. Gifford, and Levi Shotwell should act as building committee, to secure and adopt plans and specifications, and enter into a contract with the lowest responsible bidder or bidders giving proper security for the .performance of the contract.

3. By inference it charges that the resolution was adopted by the people.

4. That on November 1, 1883, the committee entered into a contract with Claire Allen for the construction of the court-house; that Allen entered upon the performance of the contract; that by virtue thereof it became the duty of the defendants, and each of them, as a board of officers and agents, contracting for and in behalf of said county of Ionia, who so hold themselves out to the public as a properly constituted board of officers and agents for said county for the purpose of contracting in behalf thereof, to require security, as required by section 1 of Act No. 94 of the. Public Acts of 1883.

5. That afterwards, on February 11, 1884, relying upon the bond provided for by said section, and believing a bond had been required of Claire Allen, plaintiff made a contract with Claire Allen to furnish him the stone to be used in constructing said court-house, to the value of $8,425, which said stone were built into the court-house.

6. That the court-house was never finished by Allen, but he failed to do so, and was financially unable to finish the same; and that afterwards, on July 29, 1885, after the material had been furnished, the court-house was taken off the hands' of the contractor by the committee, and finished by them.

7. That, at the time said court-house was taken off the hands of Claire Allen by the committee, Allen was indebted [542]*542to tbe plaintiff in the sum of $1,165.55, which sum said Claire Allen had hitherto wholly neglected and refused to pay.

8. That at the time said debt became due, to wrt, June 15, 1885, Claire Allen was, and still is, financially irresponsible, so that the debt, or no part thereof, could be collected of him.

9. That at the January session, 1887, the board of supervisors adopted a resolution, and in other ways did ratify and confirm the acts of said building committee, and assumed the responsibility and liability incurred by them, and agreed to save harmless said building committee from all suits, proceedings, claims, and demands growing out of the erection of said court-house, or in any manner relating thereto; and that, by reason of the neglect of said committee and board of supervisors to require said bond, an action had accrued to the plaintiff to demand and recover the sum of $1,165.55, and interest thereon.

The declaration in the case nowhere alleges or attempts to rely upon any misconduct of the defendants, excepting the one fact of the omission to take the statutory bond. It does not allege fraud or deceit, or that the committee intentionally or purposely committed any wrong against the plaintiff. On the trial, so far as the county was concerned, the circuit judge held the resolution offered in evidence, and above quoted, did not bind the .county of Ionia so far as to give the plaintiff an action on the case against the county.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O'Neal Steel Company v. Leon C. Miles, Inc.
187 So. 2d 19 (Mississippi Supreme Court, 1966)
Arrow Sheet Metal Works, Inc. v. Bryant & Detwiler Co.
61 N.W.2d 125 (Michigan Supreme Court, 1953)
People Ex Rel. Youngs v. United States Fidelity & Guaranty Co.
249 N.W. 20 (Michigan Supreme Court, 1933)
Christman v. Southern Surety Co.
43 F.2d 452 (W.D. Michigan, 1929)
Granette Products Co. v. Arthur H. Neumann & Co.
221 N.W. 197 (Supreme Court of Iowa, 1928)
People Ex Rel. Towner Hardware Co. v. Morrison
199 N.W. 689 (Michigan Supreme Court, 1924)
Producers Stone & Gravel Co. v. Chicago Bonding & Surety Co.
185 N.W. 703 (Michigan Supreme Court, 1921)
Stricker v. Industrial Commission
188 P. 849 (Utah Supreme Court, 1920)
People ex rel. Westover-Kamm Co. v. Valley Mantel & Tile Co.
166 N.W. 839 (Michigan Supreme Court, 1918)
Tipton Realty & Abstract Co. v. Kokomo Stone Co.
110 N.E. 688 (Indiana Court of Appeals, 1915)
People ex rel. Buhl Sons Co. v. Finn
127 N.W. 704 (Michigan Supreme Court, 1910)
Friedman v. County of Hampden
90 N.E. 851 (Massachusetts Supreme Judicial Court, 1910)
People ex rel. Kuenzel v. National Construction Co.
123 N.W. 801 (Michigan Supreme Court, 1909)
Horton v. Crowley Electric Co.
122 N.W. 312 (Supreme Court of Minnesota, 1909)
People ex rel. Davis v. Campfield
114 N.W. 659 (Michigan Supreme Court, 1908)
Farmer v. St. Croix Power Co.
93 N.W. 830 (Wisconsin Supreme Court, 1903)
United States ex rel. Croll v. Jack
82 N.W. 1049 (Michigan Supreme Court, 1900)
People ex rel. Emack v. Thompson
77 N.W. 314 (Michigan Supreme Court, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
39 N.W. 742, 71 Mich. 538, 1888 Mich. LEXIS 649, Counsel Stack Legal Research, https://law.counselstack.com/opinion/avery-v-board-of-supervisors-mich-1888.