Christman v. Southern Surety Co.

43 F.2d 452, 1929 U.S. Dist. LEXIS 1125
CourtDistrict Court, W.D. Michigan
DecidedJanuary 11, 1929
StatusPublished
Cited by2 cases

This text of 43 F.2d 452 (Christman v. Southern Surety Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Christman v. Southern Surety Co., 43 F.2d 452, 1929 U.S. Dist. LEXIS 1125 (W.D. Mich. 1929).

Opinion

RAYMOND, District Judge.

This is an action brought to recover from the surety on a public contractor’s bond the amount claimed to be due plaintiff for materials furnished for the construction of a sewer in the village of Spring Lake.

Motions for directed verdict made by both parties at the close of the proofs recognize that the determination of this ease depends substantially upon the construction to be given that portion of section 2, of Act No. 384, of the Public Acts of Michigan of 1925, which relates to the notice of indebtedness or of furnishing materials to be given to- officers or agents of municipalities by materialmen. A copy of section 2 is appended, the amendments made by this act being in italics.1

[453]*453The clear weight of authority is that such statutes are to be liberally interpreted in favor of the materialman and laborer with a view to effecting their purpose to require payment to those who have contributed by their labor and material to the erection of ■ buildings, or the making of publie improvements. Guaranty Co. v. Pressed Brick Co., 191 U. S. 416, 24 S. Ct. 142, 48 L. Ed. 242; U. S. for Use of Hill v. American Surety Co., 200 U. S. 197, 26 S. Ct. 168, 50 L. Ed. 437; McQuillin Municipal Corp. (2d Ed.) § 2108, and cases cited. Interpretation should be with a view to effectuating the legislative purpose manifested by such enactments (St. Louis v. Construction Co., 175 Mo. App. 555, 158 S. W. 98; U. S. for Use of Hill v. American Surety Co., supra; Clow & Sons v. A. W. Scott CO., 162 Minn. 501, 203 N. W. 410; 25 R. C. L. 1012, 1013), which is not solely for the benefit of the materialman. In the case of Equitable Surety Co. v. McMillan, 234 U. S. 448, 456, 34 S. Ct. 803, 805, 58 L. Ed. 1394, it is said: “The public is concerned not merely because laborers and material-men (being without the benefit of a mechanic’s lien in the case of publie buildings) would otherwise be subject to great losses at the hands of insolvent or dishonest contractors, but also because the security afforded by the bond has a substantial tendency to lower the prices at which labor and material will be furnished, because of the assurance that the claims will he paid.”

The history of this class of legislation in Michigan is important. Act No. 94, Pub. Acts 1883 (3 Comp. Laws 1897 § 10743 et seq.), entitled “An act to insure payment of wages earned, and for materials used in eon-strueting, repairing or ornamenting publie buildings and public works,” offered no protection to subcontractors, and in a number of cases arising thereunder and the amendment of 1905 the distinction between mate-rialmen and subcontractors was made. See Avery v. Board of Supervisors, 71 Mich. 538, 39 N. W. 742; Hirth v. Powers, 108 Mich. 339, 66 N. W. 215; People v. Cotteral, 119 Mich. 27, 77 N. W. 312; People v. National Construction Co., 159 Mich. 133, 123 N. W. 801; People v. Finn, 162 Mich. 481, 127 N. W. 704. No notice of reliance upon or acceptance of benefits of the bond was required by that act as a condition precedent to action.

Act No. 187 of Pub. Acts 1905 (3 Comp. Laws 1915, § 14827 et seq.), included subcontractors among those entitled to the protection of the bond, but required as an express condition precedent to benefits thereunder that, “in the ease of a subcontractor, he shall give notice in writing before payment is made for the work or materials furnished by him to the said hoard of officers or agents, that he is a subcontractor for the doing of some part of such work which he shall specify in his notice and that he relies upon the security of the bond by this act required to he given by the principal contractor, and that in the ease of the giving of such notice to the said board of officers or agents said subcontractor shall also notify the principal contractor that he has done so, and whenever this shall have been done, the said subcontractor shall he entitled, subject to the rights of the persons with whom he has contracted for labor and materials, to the benefit of the security given by the principal contractor,” etc. Section 2 (Comp. Laws 1915, § 14828).

[454]*454Act No. 384, Pub. Aets 1925, imposed, additional duties upon tbe subcontractor, and provided for notice of claim of reliance upon tbe bond to be given by subcontractors relying on tbe bond, to the sureties of the contractor, and, in the case of materialmen, provided for notice as appears by the amendment.

The controlling question here presented is whether the notice required to be given by a materialman is a condition precedent to a right of action upon the bond. The-statutes of some jurisdictions clearly make the right to maintain action upon the bond depend upon giving the notice provided for therein. See Huggins v. Sutherland, 39 Wash. 552, 82 P. 112; Grant v. Berrisford, 94 Minn. 45, 101 N. W. 940,1133; San Dimas Quarry Co. v. American Surety Co., 30 Cal. App. 3, 157 P. 548; Otis Elevator Co. v. Long, 238 Mass. 257, 130 N. E. 265; Tower v. Miller, 211 Mass. 113, 97 N. E. 748; Power Regulator Co. v. Taylor, 225 Mass. 292, 114 N. E. 356; Shea v. City of Springfield, 252 Mass. 571, 147 N. E. 829; Greene County v. Southern Surety Co., 292 Pa. 304, 141 A. 27.

No case has been found in which such a notice has been held to be a condition precedent to action where no't clearly made so by statute. It is noted that title 40, § 270, U. S. Code (40 USCA § 270), which provides for furnishing of an affidavit and the obtaining of a certified copy- of bond by material-men and laborers on United States government contracts, has been uniformly construed in such manner as not to make compliance a prerequisite to the right to maintain an action. See Title Guaranty & Trust Co. v. Crane Co., 219 U. S. 24, 31 S. Ct. 140, 55 L. Ed. 72; United States v. Massachusetts Bonding & Insurance Co. (D. C.) 198 F. 923; American Surety Co. v. United States, 77 Ill. App. 106, Purington v. United States, 126 Ill. App. 323.

The amendments of 1925 were apparently made with discrimination and care. See House Journal 1925’, pp. 176, 507, 1246. Giving due weight to the careful consideration section 2 must have received, and to the fact that the Legislature must have had in mind the distinctions between the rights and remedies theretofore afforded subcontractors and materialmen, not only suggested by the repeated decisions of the courts, but clearly indicated in section 2, the conclusion is ir-resistable that the Legislature, by failing to provide in the ease of the notice to be given by materialmen that, “whenever this shall have been done,” they “shall be entitled to the benefit of the security,” unmistakably indicated its intent to preserve a substantial distinction between the two classes of creditors. Had the purpose been to make the filing of notice a condition precedent to a cause of action on the bond, it should have been under the existing state of judicial opinion and legislation, clearly expressed. Failure so to do, in the opinion of the court, indicates clearly the opposite intent.

Section 5 was added to the act by the 1925 amendment to include obligations for certain material and supplies within the benefits of the bonds.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Holmes v. Insurance Co. of North America
288 F. Supp. 325 (W.D. Michigan, 1968)
Southern Surety Co. v. Christman
43 F.2d 455 (Sixth Circuit, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
43 F.2d 452, 1929 U.S. Dist. LEXIS 1125, Counsel Stack Legal Research, https://law.counselstack.com/opinion/christman-v-southern-surety-co-miwd-1929.