Stein v. McCarthy

97 N.W. 912, 120 Wis. 288, 1904 Wisc. LEXIS 64
CourtWisconsin Supreme Court
DecidedJanuary 12, 1904
StatusPublished
Cited by6 cases

This text of 97 N.W. 912 (Stein v. McCarthy) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stein v. McCarthy, 97 N.W. 912, 120 Wis. 288, 1904 Wisc. LEXIS 64 (Wis. 1904).

Opinion

Oassoday, O. J.

The plaintiffs claim that the case was improperly taken from the jury. This seems to be based upon the theory that their contract made with the defendant through Findorff was separate from, independent of, and without reference to the plans, specifications, and contract which the defendant had previously made with the owners of the Kappa House in respect to the plastering. If the evidence on the part of the plaintiffs sustains such theory, then the verdict was improperly directed. The evidence is undisputed, and to the effect that March 11, 1901, the defendant entered into a written contract, including plans and specifications, with the owners of the Kappa House, to erect, construct, and complete the same on or before September 1, 1901, according to such plans and specifications, for $11,441; that, prior to that "time, Porter — named therein as local superintendent — notified different contractors in Madison, including the plaintiffs and the defendant, in' writing, that •such plans and specifications were at his 'office, and invited such contractors, respectively, to examine the same and send him sealed bids for the different parts of the work; that the plaintiffs, pursuant to such notice,, carefully examined such plans and specifications, which were identified by them in evidence, and thereafter sent to Porter their bid for the plastering work; that the defendant sent in a separate bid for the mason work, and also a separate bid for the whole work, and the defendant’s bid for the whole work was accepted, and accordingly the defendant made the contract with the owners March 11, 1901, as stated; that subsequently the defendant sent the plans and specifications to the plaintiffs to give him [292]*292a bid on tbe job; that the plaintiffs then, figured up and returned tbe plans and specifications, and about June 10, 1901, one of tbe plaintiffs met tbe defendant at tbe Pair Store block in tbe presence of Porter, and asked him wbo was going to do the plastering on tbe Kappa House and be replied tbat be did not consider tbe figures of tbe plaintiffs as any bid at all, and tbat be was sure tbat they would not get tbe job; tbat about June 15, 1901, one of tbe plaintiffs asked Pindorff (a subcontractor of a part of tbe woodwork at tbe Kappa House) wbo was going to do tbe plastering on tbat bouse; tbat Pindorff replied by asking wby tbe jilaintiffs did not go and see tbe defendant and do tbe plastering; tbat be then told Pindorff tbat tbe plaintiffs would not see tbe defendant because be bad said wbat be did at tbe Pair Store;, tbat tbe plaintiffs wanted Pindorff to belp tbem get tbe contract before receiving tbe plans and specifications from the defendant; tbat Pindorff then told Mm tbat be thought the plaintiffs were a little bit high on tbe work, and asked if tbe plaintiffs would not “dó tbat work for twenty-one and thirty-five a yard;” tbat be replied tbat tbat would depend on wbat was to be done; tbat Pindorff said, “A bard finish;” tbat be replied tbat tbe plaintiffs could not “do it for twenty-one and thirty-five;” tbat Pindorff then asked wbat tbe plaintiffs wanted “for back plastering,” and be replied, “Thirteen;”' and tbat in a couple of days afterwards Pindorff said, “Go-ahead and do tbe work.” Tbe plaintiff wbo bad such conversation with Findorff testified to tbe effect that be told Pin-dorff wbat tbe plaintiffs’ “bid would be for that job/’ tbat tbe plaintiffs bad previously looked it over “to determine wbat” their "bid would be for that job;” tbat they did tbat. after tbe contract was let to tbe defendant; that before putting in their bid, prior to that time, they “looked over the-plans and specifications carefully as to wbat was required in the plastering part of it;” tbat they “knew wbat tbe plans and specifications required as to plastering and lathing;” tbat [293]*293at that time they understood that if their bid should be accepted they would be controlled by such plans and specifications, but that at the time of the agreement with Eindorff they did not understand that they were bound by such plans and specifications; that they did understand that Mr. 'McCarthy had the contract for the entire work; that they knew that they were making the contract through Eindorff with the defendant, as the other party to the contract; that they Knew the plaintiffs were subcontractors; that they did not expect to do the work differently from what the defendant had •contracted to do it, and that they were bound by what they had agreed with Eindorff; that June 25, 1901, being the ■next day after the plaintiffs commenced work on the Kappa House they received notice in writing from Porter, as such superintendent, that their lathers were “not carrying out the requirements of the specifications where they call for all outside lathing to be narrow laths, nailed with six galvanized iron cut nails to each lath;” that he should expect the lath then “on to be renailed in order to be satisfactory;” that he -showed the letter to Eindorff, who said Porter was the superintendent, and that the plaintiffs better do as he had stated; that they understood from that time on that Porter was superintendent, and that the plaintiffs must “do the work under his directions, not to his satisfaction;” that the plaintiffs did not get any certificate from Porter, and never asked for any. ' August’4, 1901, Porter notified the defendant in writing that the plaintiffs were delaying the work on the Kappa House, and that there would certainly be trouble unless something was done. Two days afterwards the defendant notified the plaintiffs in writing that they would be held responsible for all cost or trouble by reason of such delay. As indicated in the statement of facts, the specifications mentioned required all work to be executed “to the satisfaction of the architects and person superintending the work.” The defendant’s contract with the owners required all work to be executed in a [294]*294thorough, complete, and .most workmanlike mánner, and agreeably to snch directions as should be given from time to time by the architects or Porter, as such local superintendent,, and to such superintendent’s full and entire satisfaction,, without reference thereon to any other person; and it required payment to the defendant by the owners only “on the certificate of the superintendent.” It is undisputed that the-plaintiffs did not do the plastering to the satisfaction of' Porter, and that he refused to give the defendant such certificate by reason of the failure of the plaintiffs to do the work according to such plans and specifications and contract.

The contention that the contract between the plaintiffs and the defendant was made without reference to such specifications and contract previously made between the defendant- and the owners of the Kappa House is without foundation. The interviews between Eindorff and one of the plaintiffs, which resulted in the making of the contract, were without significance or meaning, except when considered with reference to the prior contract and specifications. They say they told Eindorff what the plaintiffs’ “bid would be for the job.” What job was thus referred to ? Certainly the job the plaintiffs had previously looked over “to determine what” their “bid would be for that job.” That manifestly occurred about a week before the conversation with Eindorff, and after the defendant had sent the plans and specifications to the plaintiffs for the purpose of having them give him a bid on the job. At that time they saj they figured and returned the plans- and specifications, which figures the defendant rejected at the Fair Store when the defendant informed the plaintiffs-that they would not get the job at such figures.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arrow Sheet Metal Works, Inc. v. Bryant & Detwiler Co.
61 N.W.2d 125 (Michigan Supreme Court, 1953)
Staley v. New
250 P.2d 893 (New Mexico Supreme Court, 1952)
Seastrand v. D. A. Foley & Co.
159 N.W. 1072 (Supreme Court of Minnesota, 1916)
Modern Steel Structural Co. v. English Construction Co.
108 N.W. 70 (Wisconsin Supreme Court, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
97 N.W. 912, 120 Wis. 288, 1904 Wisc. LEXIS 64, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stein-v-mccarthy-wis-1904.