Chateaugay Ore & Iron Co. v. Blake

144 U.S. 476, 12 S. Ct. 731, 36 L. Ed. 510, 1892 U.S. LEXIS 2092
CourtSupreme Court of the United States
DecidedApril 11, 1892
Docket189
StatusPublished
Cited by68 cases

This text of 144 U.S. 476 (Chateaugay Ore & Iron Co. v. Blake) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chateaugay Ore & Iron Co. v. Blake, 144 U.S. 476, 12 S. Ct. 731, 36 L. Ed. 510, 1892 U.S. LEXIS 2092 (1892).

Opinion

Mr. Justice Brewer,

after stating the case,, delivered the opinion of the court.

The question in-this case is whether or not the plaintiff fully performed his contract of March 26, 1886. The contract stipulated for payment of one-half of the price' before, and of the other half when the machinery was, completed and success- ' fully running. E ow, in addition to the full payment of the one-half, substantially three-fifths of the other was paid in three successive payments; the first within one and the last not until six weeks.after the commencement of actual operations. There is significance in these latter payments. While not conclusive on the company, they indicate that in its judg-: ment, for a while at least, the plant fully satisfied all the conditions. of the contract, and are properly to be considered, in determining the merits of the defence made to this action. *483 That defence is, that the plant was improperly and unskilfully constructed, of weak and defective parts, of material not adapted to the work which it was designed to perform, and that its actual working capacity did not exceed 350 tons a day. The answer, besides its defensive allegations, contained a counter-claim.

The first matter we notice is the alleged- error in the testimony of Charles S. Brown, who, from certain account books which he presented, was permitted to testify as to the actual working of the plant between October 18 and November 7, giving in that testimony the actual hours the plant was working, the number, of tons crushed, the hours of delay, and the causes therefor. This witness was sent by Mr. Blake to superintend the erection of the plant, to watch its workings when completed, and to make any needed repairs, improvements or changes. At his suggestion, after the plant commenced work, the defendant’s superintendent directed the foremen of the mill to keep these books. The foremen, of whom there were four, generally made the entries' on the books, though sometimes Brown did the writing at their dictation. The entries were made daily; at least, that was the intention and the general practice. The amount of ore crushed, as disclosed by these books, corresponded within a few tons with the amount testified to by the officers of the defendant company. Brown, himself, was-present at the mill most of the time during the day, ,and had a general knowledge of the accuracy of these entries, so far as respects the work during that time. ~We think tb e testimony was competent. The books were kept by the direction of the. defendant’s superintendent, and the entries made by its foremen. They were intended to be, and in fact generally were, contemporaneous with the matters stated; and their substantial accuracy is corroborated by the personal knowledge of the witness, and the near coincidence of the general result with that vouched for by the defendant. They may not have been account books of the defendant, in the technical sense of the.term, such as are generally admissible against a party, but they were memoranda made under the direction of the defendant for the purpose of preserving a *484 record of certain facts, and made under such, circumstances ,as , to be worthy of a measure of credence as against it.

A second matter is this: The general manager of the defendant was asked what, in his judgment, was the daily capacity of the mill. This question was objected to on the ground that the witness was not shown to be competent to testify as an expert, which objection was sustained. How much knowledge a witness must .possess before a party is entitled to his opinion as an expert is a matter which, in the nature of, things; must .be left largely to the discretion of the trial court, and its ruling thereon will • not be disturbed unless clearly erroneous. Stillwell & Bierce Mfg. Co. v. Phelps, 130 U. S. 520; Montana Railway Company v. Warren, 137 U. S. 348; Inland & Seaboard Coasting Co. v. Tolson, 139 U. S. 551. This witness testified that he had been general manager of the defendant company for six years; and that he was at the mill as' often as twice a month, and usually went there once a week. He does not appear to have been a practical machinist,- or to have had any special knowledge of mining or crushing machinery. He was not superintendent of the workings of the mine or of the machinery, and do’es'not claim to have been there regularly, or, indeed, oftener than once a week, and, as general manager, was apparently more employed in the financial and outside business affairs of the company than 'in the details of the mining or the practical workings of the machinery. ¥e think the ruling of the trial court in excluding his opinion was right; at any rate, it cannot be adjudged clearly erroneous.

Another matter is also, complained of, and to a clear understanding of this question the course^ of -the trial must be stated. The plaintiff opened by proving the construction .of the mill, and, in a general way, that it had the capacity' of 600 tons daily, and also the payments by the defendant. He then rested, and the- defendant introduced testimony to show that the mill was not of the stipulated capacity, and explaining -the circumstances of the subsequent payments. ' This- included evidence of the- actual workings of the mill from the- 1st of October, 1886, to the 1st -of January, .1888, the' difficulties *485 that were encountered in its workings, the stoppages, what was done on such occasions, and the efforts to remedy supposed defects, as also the opinions of competent witnesses as to its capacity.. In other words, it went fully into the matter of- the actual workings of the mill; and its alleged incapacity ■ to do the stipulated amount of crushing. In rebuttal, plaintiff called the witness Brown, who gave the testimony heretofore referred to from the memorandum books. It appeared from his testimony that the books had been kept from October 18 till he left, in March following. He had made out from them a statement of the facts respecting the workings of the mill from October 18 tqj the Yth of November, which he had .forwarded to the plaintiff, and the details of that statement, as verified by the books, was the sum and substance of his testimony. After he had finished, and the plaintiff had rested in his rebuttal, the defendant called a witness named Hall, who - testified that he' had examined the books, and he was then . asked what the average run per hour.was for the months of November, December and January, separately, as shown by. those books. This testimony was objected, to and ruled out, and of this defendant now complains. We think the ruling. of the court was right. If the defendant had a right after the plaintiff had closed his case in. rebuttal to introduce any testimony at all, such right was limited to the new matters brought out in the rebuttal; and while the fact of the existence of these books, and that they were kept for several months was then disclosed for the first time, the only matters therefrom presented to the consideration of the jury were those transpiring between October 18 and November Y.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Read Corp. v. Portec, Inc.
748 F. Supp. 1078 (D. Delaware, 1990)
Mulholland v. DEC International Corp.
443 N.W.2d 340 (Michigan Supreme Court, 1989)
Reed v. State
391 A.2d 364 (Court of Appeals of Maryland, 1978)
La France v. New York, New Haven & Hartford Railroad
191 F. Supp. 164 (D. Connecticut, 1961)
Aycrigg v. United States
136 F. Supp. 244 (N.D. California, 1954)
Chicago Great Western Ry. Co. v. Beecher
150 F.2d 394 (Eighth Circuit, 1945)
United States v. a Certain Tract or Parcel of Land
47 F. Supp. 30 (S.D. Georgia, 1942)
Wilson v. State
26 A.2d 770 (Court of Appeals of Maryland, 1942)
Troutman v. United States
100 F.2d 628 (Tenth Circuit, 1938)
American Glycerin Co. v. Eason Oil Co.
98 F.2d 479 (Tenth Circuit, 1938)
Morton Butler Timber Co. v. United States
91 F.2d 884 (Sixth Circuit, 1937)
Luke v. United States
84 F.2d 823 (Fifth Circuit, 1936)
Baush MacH. Tool Co. v. Aluminum Co. of America
79 F.2d 217 (Second Circuit, 1935)
The Albisola
6 F. Supp. 392 (E.D. Pennsylvania, 1933)
Lemmons v. United States
62 F.2d 608 (Tenth Circuit, 1932)
District of Columbia v. Chessin
61 F.2d 523 (D.C. Circuit, 1932)
James Baird Co. v. Boyd
41 F.2d 578 (Fourth Circuit, 1930)
Haley v. Pearson
14 S.W.2d 313 (Court of Appeals of Texas, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
144 U.S. 476, 12 S. Ct. 731, 36 L. Ed. 510, 1892 U.S. LEXIS 2092, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chateaugay-ore-iron-co-v-blake-scotus-1892.