Henley v. Wadsworth

38 Cal. 356
CourtCalifornia Supreme Court
DecidedJuly 1, 1869
StatusPublished
Cited by14 cases

This text of 38 Cal. 356 (Henley v. Wadsworth) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Henley v. Wadsworth, 38 Cal. 356 (Cal. 1869).

Opinion

Sprague, J., delivered the opinion of the Court:

This is an action by a sub-contractor against the employer and original contractor, to recover the amount due plaintiff as sub-contractor and assignee of other claims due other mechanics and material men from the original contractor, and to enforce the amount so due plaintiff, as a lien upon the premises and superstructure thereon erected, under the Mechanics’ Lien Law of April 26, 1862.

On the 26th day of May, 1866, the defendant, T. L. Wads-worth, of the first part, and defendant, Julius Feidler, of the second part, entered into an agreement in writing for the construction of a three-story brick building, with basement, by the party of the second part, for the party of the first part, upon a certain described lot belonging to the party of the first part, in the City of Sacramento, which agreement or contract, in substance, is as follows :

The party of the second part stipulates and agrees to erect and finish a three-story and basement brick building on part of Lot 4, on the north side of K street, between First and Second streets, in the City of Sacramento, for the said party of the first part, the work to be commenced immediately, prosecuted with all due diligence, and completed on or before the 31st day of August, 1866, agreeable to drawings and specifications made by A. A. Bennett, architect, signed by the parties and annexed to the agreement, said building to be finished by the party of the second part within the time aforesaid, to the satisfaction and under the direction of said architect; said party of the second part to furnish all proper and sufficient materials for completing and finishing all the mason work, stone work, iron work, plaster work, carpenter work, hardware, glazing, plumbing work, gas pipes, painting, roofing, and other work of said building mentioned in the specifications, for the sum of $12,500, in gold coin of the United States, which the party of the first part agreed to pay as follows, to wit:

[358]*358jFirst payment—$2,000, when the brick work is up to the high grade, and the timbers laid.
Second payment—$2,000, when the brick walls are up to the second story, and the timbers laid.
Third payment—$2,000, when the walls are up to the tnird story, ready for the roof.
Fourth payment—$2,000, when all the floors are laid in the ’ building.
Fifth payment—$1,450, when the roof is covered and all the plastering completed.
Sixth payment—$3,050 (the balance), to be paid thirty days after the entire building and works are finished and completed, according to the specifications, and accepted as such by the said architect.

The party of the second part, as original contractor, agreed to furnish and provide, at his own proper costs and charges, all manner of materials and labor, scaffolding, implements, molds, models and cartage of every description, for the due performance of the several erections. And it was further stipulated and agreed by and between the parties, that in case the contractor, party of the second part, should at any time during the progress of said works, refuse or neglect to supply a sufficiency of materials or workmen, the owner should have the power to provide the materials and workmen, after three days notice in writing being given, to finish said works, and the expense to be deducted from the amount of the contract. And the party of the second part further agreed to pay to the party of the first part the sum of $10 per day for each and every day that the completion of said works shall be delayed; after the hereinbefore recited time for the completion of the same (rainy days excepted), and the party of the first part should have full power to retain such amount, as liquidated damages, from any money remaining in her hands claimed by said party of the second part.

It appears from the evidence and special findings of facts, as found in the record in this case, that defendant, Feidler, as original contractor under this contract, immediately after its execution, entered upon the performance of its terms on his part, and prosecuted the same until about the 15th of [359]*359September, 1866, at which time, and while the building was being finished on the inside, he quit work and abandoned his contract, for the reason, as he states in his testimony, that he found it would cost him about $4,000 more than the contract price to finish the work in accordance with his contract; and that thereafter, on the 6th of October, 1866, the owner, Mrs. Wadsworth, served upon him the written notice required by the terms of the contract in case the contractor should fail, neglect or refuse to furnish the necessary materials and workmen to finish the building, in accordance "with the contract ; and after waiting about two weeks from the service of such notice for Fiedler to go on, and after he had refused so to do, the owner, Mrs. Wadsworth, proceeded to finish the building in accordance with the original specifications, at a cost of $4,698 78.

That, at the time defendant, Fiedler, quit work and abandoned his' contract, he had been paid thereon $10,854, or $1,404 more than the amount of the first, second, third, fourth and fifth payments stipulated to be paid prior to the completion of the building. It further appears that no subcontractor, material man, mechanic or laborer served upon the owner, Mrs. Wadsworth, any notice of claims against the original contractor until the 15th October, 1866, just one month after the original contractor had quit the work, abandoned his contract, and had been paid every dollar he ever received under his contract, and $1,404 more than he was ever entitled to receive thereunder.

From these facts, it is very clear that at the time of the service upon the owner, Mrs. Wadsworth, of the notices of the several claims against the original contractor, now sought to be enforced as a lien upon the premises, nothing was due the original contractor from the owner upon the contract, nor has anything since become, or likely to become, due him upon such contract.

Disregarding, then, the point made upon the sufficiency of such notices, the controlling question is presented, whether, under the terms of the original contract, any one of the first five instalments were prematurely paid by the owner to the original contractor, to the prejudice of any of the claims now [360]*360sought to be enforced. Unless some one, or some portion of these five payments, were made to the original contractor by the employer before they became due by the terms of the original contract, or after notice had been duly served upon the employer, of the existence of the claim against the original contractor by the holder of such claim, clearly the plaintiff has no right of lien upon the premises by virtue of the demands against the original contractor set out in the complaint, and no legal personal claim whatever, on account thereof, against the defendant, Mrs. Wadsworth.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rosenbaum v. Price Construction Co.
184 S.E. 261 (West Virginia Supreme Court, 1936)
Thelander v. Becker
199 S.W. 848 (Court of Appeals of Texas, 1917)
McIver v. Young Hardware Co.
57 S.E. 69 (Supreme Court of North Carolina, 1907)
Stein v. McCarthy
97 N.W. 912 (Wisconsin Supreme Court, 1904)
Frost v. Falgetter
73 N.W. 12 (Nebraska Supreme Court, 1897)
Whelan v. Young
21 D.C. 51 (District of Columbia Court of Appeals, 1892)
Farmers Loan & Trust Co. v. Canada & St. Louis Railway Co.
11 L.R.A. 740 (Indiana Supreme Court, 1891)
Schroeder v. Galland
19 A. 632 (Supreme Court of Pennsylvania, 1890)
Epley v. Scherer
1 Colo. L. Rep. 492 (Supreme Court of Colorado, 1881)
Dingley v. Greene
54 Cal. 333 (California Supreme Court, 1880)
Jensen v. Brown
2 Colo. 694 (Supreme Court of Colorado, 1875)

Cite This Page — Counsel Stack

Bluebook (online)
38 Cal. 356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/henley-v-wadsworth-cal-1869.