Whelan v. Young

21 D.C. 51
CourtDistrict of Columbia Court of Appeals
DecidedJune 27, 1892
DocketNo. 11,667
StatusPublished

This text of 21 D.C. 51 (Whelan v. Young) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whelan v. Young, 21 D.C. 51 (D.C. 1892).

Opinion

Mr. Justice Cox

delivered the opinion of the Court:

On the 9th of June, 1888, Hanson C. Walter entered into a written contract with Mrs. Young, the defendant, to build a house for her and complete it by December 1, following, for the sum of $6,063.91, to be paid in eight installments as the work progressed, and the contractor was to forfeit $5 for every day’s delay in completing the house beyond the time agreed on.

Mrs. Young paid six of- the installments, amounting to [52]*52$4,goo, when, on the 17th of December, sixteen days after the house was to have been completed, Walter abandoned the work, leaving the house unfinished and $1,163.91 of the contract price yet unpaid. It is admitted, by stipulation, that Mrs. Young, after Walter’s abandonment of the contract, paid $544.60 in order to complete the house according to contract.

This would leave $620.31 of the contract price unexpended.

• It is further admitted, that without negligence on her part she was unable to have the house completed until May 23, 1889.

If she be allowed to charge the $5 per day as liquidated damages for the delay, the balance of the price would be more than absorbed.

In the meantime, on the 17th of December, 1888, the day Walter abandoned his contract, the complainant Wm. Whelan filed his notice of lien for the sum of $492. He was followed by others, the claims of all amounting to .$2,315.53.

This bill was filed on the 9th of March, 1889, for all the alleged lienors to enforce the liens by a sale. It was dismissed as to Whelan and one other, Chappelear, whose claim was for $51.05, and who has died, but a decree rendered in favor of the rest for claims amounting to $1,772.53, and an appeal taken by both sides.

As far as we can gather from the printed record, Whelan’s claim must have been dismissed, because the proof showed that he had been working for Walter on various houses; had mixed his accounts all up together and received payments from him during the building of Mrs. Young’s house, which probably ought to have been credited to that work, but were not.

There is one question, however, common to all the claims.

• The broad question is, whether a sub-contractor who postpones filing his notice of lien until the principal part of the contract price has been paid, according to the terms of the contract, can, by filing his notice, assert a lien on the owneds property for his entire claim, although it may exceed in [53]*53amount what remains due under the contract. This will depend upon the time from which the lien is to attach and operate.

If we seek the meaning of the existing law by the usual test, i. e. by considering the old law, the mischief and the remedy, what do we find?

By the old law, as embodied in section 709, R. S. D. C., the sub-contractor’s remedy was to give notice of his claim to the owner and that he held said owner responsible, and he thereby acquired simply a formal claim against the owner, not to exceed, however, the amount due from him to his contractor at the time of the notice. What mischief, under this law, Congress intended to remedy one can only conjecture. In argument, it was claimed that the mischief was the possible combination between the owner and the builder to prevent the sub-contractor from receiving anything by so manipulating accounts that nothing would appear to be due when the sub-contractor’s notice should be given.

Assuming this to have been the mischief contemplated, the present case will illustrate the manner in which it is remedied by the act of July 2, 1884, which is the law now in force. That act declares (section- 1), that “ every building hereafter erected or repaired by the owner or his agent in the District of Columbia, and the lot or lots of ground of the owner upon which the same is being erected or repaired, shall be subject to a lien in favor of the contractor, subcontractor, material-man, journeyman and laborer, respectively, for the payment for work and materials contracted for or furnished for or about the erection, construction or repairing of such building, and also for any engine, machinery or other things placed in said building or connected therewith so as to be a fixture: Provided, that the person claiming the lien shall file the notice prescribed in the second section of this act: Provided, further, that the said

lien shall not exceed or be enforced for a greater sum than the amount of the original contract for the erection or repair of said building or buildings.”

[54]*54By the second section, the contractor or sub-contractor, etc., may file the notice of lien at any time during the construction or within three months after the completion of the building. In this case it appears that the contract between the defendant and Walter was dated June 9, 1888. A few days afterward and before the work was begun, Whelan, as sub-contractor, made his bid for the plumbing, according to the plans and specifications, at and for the sum of $492, which was accepted, and the work begun by him in the same month.

Now, if he had immediately filed his notice of lien, which he could have done under the law, Mrs. Young would have had notice of his claim; her property would have been subject to a lien for the whole amount of work to be done under the sub-contract; she could not have made any arrangement with the builder to the prejudice of the plumber, and the latter would have been perfectly protected, and at the same time Mrs. Young, the owner, would have known exactly how much of the money she had contracted to pay her builder ought to go to the sub-contractor, and would have paid this money to the builder with her eyes open and at her own risk. The objects of the law would have been entirely accomplished.

But the position taken by the complainant is, in substance, that if the notice of lien is not filed until after the completion of the work or after the principal part of the contract price has been paid in pursuance of the contract, still, it operates retroactively, so as to give a lien for the whole amount of the claim, as from the beginning of the tvork, making the payments that have been made in the meantime by the owner to his builder, though in good faith and in perfect accordance with his agreement, to be payments in his own wrong and at his own risk, as if they had been made with full notice and anticipation of the lien- or’s rights.

Now, this construction of the law, while it does promote one of its objects, viz., the protection of the sub-contractor, [55]*55in effect, defeats another,' which is the protection of the owner; because it would compel him to pay more than the contract price, against which he is intended to be guaranteed by the second proviso in the first section of the law. That this would be in contravention of the law, in this respect, was held in a somewhat similar case to the present, Doughty vs. Devlin, 1 E. D. Smith’s Rep., 636, where the court says: “The language is that the owner shall not be obliged to ‘pay for or on account of such house,’ etc., any greater sum or amount than the price stipulated in and by his contract. Now, if after the house is finished and paid for by the owner, according to his contract, and without any notice of claim being filed, a laborer or material-man may file such notice, have a lien and compel a further payment, the owner is obliged to pay for his house, in consideration of such lien, a greater amount than he contracted to pay.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carman v. . McIncrow
13 N.Y. 70 (New York Court of Appeals, 1855)
Dore v. Sellers
27 Cal. 588 (California Supreme Court, 1865)
Blythe v. Poultney
31 Cal. 233 (California Supreme Court, 1866)
Henley v. Wadsworth
38 Cal. 356 (California Supreme Court, 1869)
Renton v. Conley
49 Cal. 185 (California Supreme Court, 1874)
Fisher v. Bidwell
27 Conn. 363 (Supreme Court of Connecticut, 1858)
Treusch v. Shryock
51 Md. 162 (Court of Appeals of Maryland, 1879)

Cite This Page — Counsel Stack

Bluebook (online)
21 D.C. 51, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whelan-v-young-dc-1892.